PWS
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| PWS_Cavotec_PM_Repair_5.docx | DOCX document | |
| CAVOTEC_SOL_AMENDMENT.docx | DOCX document | |
| cavotec_solicitation.pdf | ||
| APPENDIX_C_CAVOTEC_18-22.docx | DOCX document | |
| Cavotec_Appendix_A_(Equipment_List).pdf | ||
| Jan_18_wage_determination.txt | TXT text file |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT
FOR
PREVENTATIVE MAINTENANCE (PM) & OVER AND ABOVE (O&A)
OF
CAVOTEC AIR CONDITIONER UNITS SUPPORT
PREPARED BY
OC-ALC/OBCA
8 DECEMBER 2017
Section One
1.1 Scope: The Contractor shall provide all labor, tools, equipment, test equipment, material, parts, quality control, transportation and inspection manuals necessary to perform annual Preventative Maintenance (PM) and Over and Above (O&A) Services of three (3) Cavotec Air Conditioner (A/C) Units for 76 AMXG at the Oklahoma City Air Logistics Complex (OC-ALC) listed in Appendix A.
1.1.1 The Contractor shall be responsible for insuring all services, parts and Original Equipment Manufacturer (OEM) components provided under this contract are in accordance with (IAW) the terms and conditions outlined herein, conform to the manufacturer’s equipment specifications and this PWS.
1.2 Requested Services: This requirement is for a Base year and four (4) option years.
This service will be utilized for PM services and unforeseen repairs, or modifications for the B-1 Cavotec A/C units. The Contractor is responsible for providing PM and over and above repair services for the three (3) Cavotec A/C units when required. The contractor shall perform all PMs and repairs in accordance with the original equipment manufacturer (OEM) specifications.
1.3 Preventive Maintenance The objective of PM is to protect the equipment capability and investment by removing causes of failure, performing routine maintenance and making adjustments to compensate for normal wear before failure occurs. The Contractor shall perform all PM’s In Accordance With (IAW) the OEM specifications. The contractor shall perform one (1) each PM per quarter per the OEM’s manual Chapter 4 on each item listed in Appendix A. The Contractor shall provide a copy of the PM schedule to the Government Point of Contact COR within ten (10) business days after contract award. The Contractor shall notify the COR seven (5) business days prior to each scheduled PM visit.
1.3.1 The contractor shall also provide monthly filter changes on each piece of equipment listed in the Appendix A.
1.3.2 The Contractor shall provide the Government an evaluation report IAW section 1.6 of this PWS
1.4 Over and Above (O&A): O&A is defined as unknown/unplanned required work discovered during the course of performing the PMs that is within the scope of the contract and necessary in order to satisfactorily complete the contract. The Contractor shall complete O&A requirements In Accordance With (IAW) Defense Federal Acquisition Regulation Supplement (DFARS) 252.217-7028. PGI 217.77.
1.4.1 In the event of the equipment listed in Appendix A needing unscheduled maintenance or repair, the Contractor shall demonstrate to the Government Point of Contact (COR) and Subject Matter Expert (SME) that each unit is operational and returned to its OEM specified capability after the services are performed.
1.5 Malfunction and Notification Process: Upon occurrence of an equipment or system malfunction, the COR will contact the Contractor by telephone, email, or fax and provide information below. If the COR notifies the Contractor via telephone, the COR will provide a written copy of the request by email or fax.
· the equipment identification number (ID#)
· a brief description of the malfunction
· location of equipment
· name and telephone number of the Point of Contact (POC)
Upon notification of the system malfunction, the technician shall arrive on site at the equipment location within eight (8) hours. If Contractor fails to report withing the specified time, the Government shall be given agreed upon consideration.
1.6 Equipment Evaluations: The Contractor shall provide a written Estimate Repair Report to the COR by fax or email no later than (NLT) one (1) business day after the completion of the inspection. As a minimum, the information cited on the Estimate Repair Report shall include:
· the equipment ID#
· date of evaluation
· description of findings and recommendations
· required parts and part numbers (P/N)
· cost of parts
· number of parts needed
· estimated labor hours required to complete the repair
Any recommendations cited shall consider:
· the priority of the requested service
· available source for obtaining new parts
· the availability of the new parts
· shipping and delivery schedules of parts
· other factors which may be peculiar to the specific repair requirement
1.7 Authorizations for Repair Actions: Only the Contracting Officer (CO) can authorize O&A actions. The Government POC will coordinate any O&A actions with the Government Subject Matter Expert (SME) and the CO in order to obtain the approval to proceed. The Contractor shall ensure all O&A actions have the documented CO approval, in writing, before initiating any O&A actions.
1.7.1 Once the authorization for O&A action has been received from the CO, the Contractor shall order any required parts within two (2) business days and notify the COR, in writing, of the estimated arrival date of the parts. Upon the receipt of the parts, the Contractor shall perform the O&A actions within five (5) business days. The COR will verify the receipt of any required parts with the Contractor to ensure O&A actions are performed in a timely manner.
1.8 Parts and Materials: The Contractor shall provide and use only new parts and material in performance of this PWS unless otherwise authorized by the CO.
1.9 Service Report: Immediately upon completion of any maintenance services and before leaving the OC-ALC, the Contractor shall provide a written Service Report to the Government SME. When necessary the Government SME will forward the service report to the Government POC within two (2) business days of receipt. The Contractor shall provide, by fax or email, the final service report within five (5) business days to the Government POC. As a minimum, the final service report shall contain the following information:
· name of the company
· requested service date
· contract number
· equipment ID#
· description of services provided
· additional services recommended (if any)
· printed name and signature of technician who performed the services
· printed name and signature of on-site Government SME or Government POC
· start and completion dates
· complete breakdown of the labor cost (hours and rate)
· materials and parts used
· details of any other charges
· printed name and signature stating only new parts and materials were used
· written verification statement that a performance check to verify operational condition was performed and that the equipment is in working order.
1.10 Maintenance Documentation: The Contractor shall notify the Government Subject Matter Expert (SME) upon completion of each evaluation and repair, IAW OC-ALC Operating Instruction (OI) 21-203, Chapter 1, 2, and 3, as applicable.
1.11 Red Tagged Items: Red Tagged items create unsafe conditions for the workplace and are noted by the annotation of a Red X in the Facilities and Equipment Management Web-Based (FEMWEB) system. A Red X indicates the equipment is considered unsafe or unserviceable and will not be used until the unsatisfactory condition is corrected and the Red X is cleared. The Contractor shall not authorize, use or direct equipment to be used until the Red “X” has been properly cleared IAW OC-ALC OI 21-203, Chapter 2.
1.11.1 Red X Clearance: The Contractor shall ensure the Red X’s are cleared IAW OC-ALC OI 21-203, Chapter 2. The Contractor shall immediately notify the shop supervisor or work leader in any instance where the Contractor clears a Red X in his or her assigned work area.
1.11.2 Red X Clearance on Equipment: Red X on Equipment will be cleared in FEMWEB by the shop supervisor, work leader, or supervisor’s designee.
1.12 Continuation of Essential Department of Defense (DoD) Contractor Services During Crisis: This requirement has been determined not to be essential and does not require continued support during a crisis as defined in DFARS 252.237-7023.
1.13 Hours of Operation: The Contractor shall perform the work required under this contract during the following days and hours: Monday through Friday, 6:30am to 12:00am mid-night. If work hours are required outside the hours stated, the Contractor shall contact the Government POC for approval from the CO. Upon approval from the CO, the Government Subject Matter Expert (SME) or Government POC must be present with the Contractor during maintenance actions.
1.13.1 These dates and hours exclude Federal Holidays, base closures due to inclement weather, and furlough days, as applicable.
1.14 Special Qualifications: The contractor shall be OEM trained and certified and provide proof of certification at time of proposal.
1.15 Contractor Personnel: The Contractor shall provide the name of the Contract Manager (CM) and any alternates who shall act for the Contractor when the CM is absent. They shall be designated to the CO and Government POC, in writing, within five (5) business days after the contract award date. The Contractor shall provide telephone numbers and email addresses where the CM and alternates may be contacted at any time. The CM or alternate shall have full authority to act for the Contractor on all matters relating to operation of this contract at the OC-ALC on Tinker Air Force Base (AFB). The CM or alternate shall be available to meet on the installation with Government personnel designated by the CO to discuss problem areas. The Contractor shall provide a CM who can read, write, speak, and understand English fluently.
1.15.1 The Contractor and Contractor personnel shall be required to identify themselves as contractor personnel by introducing themselves or being introduced as Contractor personnel. The Contractor personnel shall also display distinguishing badges or other visible identification for meetings with Government personnel or while performing work for the OC-ALC on Tinker AFB. The Contractor and Contractor personnel shall identify themselves as Contractor employees in telephone conversations and in formal and informal written correspondence.
1.16 Listing of Contractor Employees: The Contractor shall provide an initial listing of names and position titles of employees who will come to Tinker Air Force Base to the COR within five (5) business days after the contract award date. Within five (5) business days, the Contractor shall also provide an updated listing of personnel to the Government POC when employees affecting the work of this contract change status or position.
1.16.1 The Contractor shall not employ persons on this contract if such employee is identified to the Contractor as a potential threat to the health, safety, security, and/or general well-being, or operational mission of the installation and its population. The Contractor shall not employ any person who is an employee of the United States (US) Government if the employment of the person would create a conflict of interest. The Contractor shall not employ any person who is an employee of the Department of the Air Force (AF), either military or civilian, unless such person seeks and receives approval according to the DoD 5500.7-R Joint Ethics Regulations (JER). In addition, the Contractor shall not employ any person who is an employee of the Department of the AF if such employment would be contrary to the policies contained in Air Force Instruction (AFI) 64-106, Air Force Industrial Labor Relations Activities. The Contractor shall be prohibited from employing off-duty Government POCs who are providing surveillance on any contracts/sub-contracts awarded to the Contractor. All contract personnel, depending on particular condition, occasion, or place or job assignment shall be required to wear professional and suitable attire. All Contractor personnel shall conduct themselves in a professional and courteous manner. The selection, assignment, reassignment, transfer, supervision, management, and control of contractor personnel in performance of this PWS shall be the responsibility and prerogative of the Contractor; however, the Contractor shall comply with the requirements set forth in this PWS and Tinker AFB regulations concerning the conduct of employees as referenced herein. The Contractor shall employ and maintain a technically trained and experienced work force.
1.17 Environmental Protection & Safety: The Contractor shall be knowledgeable of and comply with all applicable federal, state and local laws, regulations, instructions and requirements regarding environmental protection and occupational safety and health. The Contractor shall comply with any laws, instructions or regulation changes during the term of this contract.
1.17.1 Contractors shall be compliant with Tinker Air Force Base (TAFB) Supplement to Air Force Instruction (AFI) 32-7086, “Hazardous Materials Management”, Tinker AFB procedures per Tinker Air Force Base Instruction (TAFBI) 32-7004, “Hazardous Waste Management”, and Complex procedures per Oklahoma City Air Logistics Complex (OC-ALC) Supplement to AFI 32-7086, “Hazardous Material Management” and OC-ALCI 32-101 “Air Quality Record Keeping Procedure”. Publications are available digitally on e-Publishing website at www.e-publishing.af.mil for downloading or ordering.
1.18 Technician and Equipment Certification: Prior to installation or recovery of refrigerants or Ozone Depleting Substances (ODS) to or from contracted equipment, the Contractor shall submit to the COR: (a) a copy of the technician(s) certification(s) as required by 40 CFR (Code of Federal Regulations) part 82, subpart F and (b) a copy of the refrigerant recovery and recycling equipment certification (copy of the form signed by the owner of the equipment or another responsible officer and sent to the appropriate EPA (Environmental Protection Agency) Regional Office) as proof that the Contractor acquired recovery equipment per 40 CFR 82.162.
1.19 Refrigerant Installation and Recovery:
Contractor shall submit to the COR within five (5) working days after the service report is submitted, a record of the servicing technician(s) name(s), amount of refrigerant and type of refrigerant added to the contracted equipment or recovered from the equipment. In the case of commissioning new or retrofitted equipment, the Contractor shall provide the refrigerant amount determined to be the "Full Charge" as defined in 40 CFR 82.152. Provide information concerning refrigerant losses to the atmosphere, including that associated with warranty work. All recovered refrigerant will be into government furnished recovery cylinders.
1.19.1 The following chlorofluorocarbon (CFC) and Hydrochlorofluorocarbon (HCFC) that are recovered from contracted equipment will be into government furnished recovery cylinders: Class I ODS, CFC-500, CFC-502 and HCFC-22. The contractor shall not transport these specific refrigerants off base for reclamation or disposal.
1.20 Refrigerant Reclaimer Certification: Proof of reclaimer certification shall be provided to the COR within ten (10) calendar days after contract award date or prior to changing EPA Certified Refrigerant Reclaimer. The contractor shall provide a signed chain of custody report between the contractor and an EPA Certified Refrigerant Reclaimer to the COR within ten (10) working days after contractor acceptance of recovered refrigerant. The contractor shall provide to the COR on the first day of each month a listing of the amount of refrigerant reclaimed from contracted equipment. Any recovered refrigerant that is not reclaimed, shall be properly disposed of IAW 40 CFR part 82 at an EPA approved facility and the contractor shall provide to the COR documentation identifying the disposal method (incineration, etc.).
1.21 Hazardous Material (HAZMAT): If no HAZMAT will be brought on base or used in performance on this contract, the contractor shall certify “No HAZMAT will be brought on base” or “No HAZMAT Usage” in writing on company letterhead. This certification shall be provided to the COR within ten (10) days after award. Upon COR receipt of the certification, the requirements of this section no longer apply. Appropriate penalties for the contractor, or administrative and disciplinary action for the latter shall be assessed if found in violation of above certification.
1.21.1 The Contractor shall comply with applicable federal and military procurement policies IAW OC-ALC Supplement to AFI 32-7086, “Hazardous Material Management”. The Contractor shall obtain access to the standardized Air Force HAZMAT tracking system and manage HAZMAT within the system or have a government designated HAZMART comply. The Contractor shall establish and reconcile the inventory, print the standardized Air Force HAZMAT tracking system bar code labels, and apply the labels to containers of HAZMAT so that the Occupational Safety and Health Administration (OSHA) compliant labels are not covered. Any failure to comply with proper HAZMAT management procedures shall be reported to the CO and COR who will notify 76 MXSG/MXDEU, OC-ALC Environmental and Occupational Health Compliance.
1.22 Safety Data Sheet (SDS) and Labeling: Upon COR receipt of the “No HAZMAT Usage” certification, the requirements of this section no longer apply.
1.22.1 The Contractor shall not transport, ship or use any chemical, material or substance used in the performance of this PWS on Tinker AFB before written approval is provided by 72 ABW/CEIE, Natural Infrastructure Management (Environmental Compliance). The Contractor shall submit to the COR, ten (10) calendar days after contract award date all Safety Data Sheets (SDSs) and a completed OC-ALC Form 152, SDS Information Sheet. The Contractor shall receive approval from the COR prior to shipping any chemical, material or substance to Tinker AFB. A copy of the manufacturer SDS shall accompany the shipment. Contractor shall comply with the effective dates for SDS requirements IAW the Occupational Safety and Health Administrations (OSHA) Hazardous Communication Standard, Title 29, Code of Federal Regulation (CFR) Part 1910.1200. The Contractor shall ensure containers of hazardous chemicals are labeled with the following information, prior to shipping to Tinker AFB IAW OSHA Hazardous Communication Standard, Title 29, CFR Part 1910.1200 (2012): product identifier; signal word; hazard statement(s); precautionary statement(s); pictogram(s); and name, address and telephone number of the chemical manufacturer, importer, or other responsible party. The COR will forward all SDS submittals to 72 ABW/CEIE for approval. A current manufacturer SDS shall be submitted to the COR if the Contractor changes manufacturer or vendor for any chemicals that were prior approved. The Contractor shall maintain copies of manufacturer SDSs for all chemicals and SDSs shall be readily accessible at all times by Contractor personnel as well as government employees.
1.23 Air Quality Recordkeeping: Upon COR receipt of the “No HAZMAT Usage” certification, the requirements of this section no longer apply.
1.23.1 The Contractor shall be responsible for specific recordkeeping and reporting requirements, when applicable, mandated by Tinker Air Force Base Facility-Wide Operating Permit IAW OC-ALCI 32-101. The COR will contact the UEC for environmental requirements. The Contractor shall submit all applicable records on a monthly basis to the COR no later than the third (3rd) day of the month following the reporting period. If the third (3rd) day of the month is a weekend or holiday, the logs are required by the last business day 'PRIOR' to the (third) 3rd. The COR will forward the records to the UEC no later than the fourth (4th) day of the following month or the first subsequent business day. Contractor shall maintain a signed copy of the form(s) required per OC-ALCI 32-101 on site for one (1) year.
1.24 Hazardous Waste: If no HAZWASTE will be generated during performance of this contract, the contractor may certify “NO Hazardous Waste Generation” in writing on company letterhead. This certification shall be provided to the COR within ten (10) days after award. Upon COR receipt of the “No Hazardous Waste Generation” certification, the requirements of this section no longer apply. Appropriate penalties for the contractor, or administrative and disciplinary action for the later shall be assessed if found in violation of above certification.
1.24.1 The Contractor shall dispose of contaminated solid waste, spent or processed chemical solutions, used rags and hazardous waste in government furnished waste containers IAW TAFBI 32-7004.
1.24.2 The Contractor shall be responsible for the Initial Accumulation Point (IAP) within the Contractor assigned space. The IAP shall be under the direct control of the Contractor who generates the waste. Before accumulation begins, the Contractor shall ensure appropriate hazard labels are affixed to government furnished waste containers as specified in 49 Code of Federal Regulation (CFR) 172.400. Management procedures for IAPs include written weekly inspections and reporting. When the container has been filled, the Contractor shall seal the container, mark the Certified Filled Date on the container label using an indelible pen, place the container at a designated pick up location, and call the Hazardous Waste Management Facility (HWMF) at 734-3285 for pick-up service. The Contractor shall ensure the HWMF picks up the container within three (3) calendar days after the Certified Filled Date. If container is not picked up within three (3) calendar days, Contractor shall notify the COR who will notify 76 MXSG/MXDEU, OC-ALC Environmental Engineering Section.
1.24.3 The Contractor shall perform written weekly inspections using Tinker AFB IMT Form 487, Initial Accumulation Point Management Aid. Weekly denotes once per working week. The Contractor shall submit Tinker AFB IMT Form 487 on a monthly basis to the COR no later than the third (3rd) day of the month following the reporting period. If the third (3rd) day of the month is a weekend or holiday, the logs are required by the last business day 'PRIOR' to the third (3rd). The COR will forward the form(s) to the UEC no later than the fourth (4th) day of the following month or the first (1st) subsequent business day. Contractor shall maintain a signed copy of the form(s) on site for one (1) year.
1.25 Discharges: Any discharges into Tinker’s industrial waste treatment plant (IWTP) or sanitary sewer shall be approved and done IAW Tinker Industrial Waste Water Discharge Permit as instructed by 72 ABW/CEIE, Natural Infrastructure Management (Environmental Compliance). Notice of intent documentation shall be provided to the COR within ten (10) days after award. The COR will submit the required notice of intent documentation to the UEC for 72 ABW/CEIE approval. The Contractor shall not discharge into IWTP and sanitary sewer prior to approval issued by 72 ABW/CEIE. The Contractor shall maintain records of written approval issued by 72 ABW/CEIE for discharges into IWTP and sanitary sewer.
1.26 Spills: Upon occurrence of any spill that could enter the storm system or cause any harmful environment effects, the Contractor shall immediately call 911 to report the incident. When possible, the Contractor shall use a base telephone to receive help from Tinker AFB 911. If using a cell phone, the Contractor shall request Tinker AFB 911. The Contractor shall immediately report all environmental violations to the COR and UEC. The Contractor shall provide five (5) copies of a typed or written report about the incident within four (4) clock hours as follows:
1.26.1 One (1) copy to the CO, two (2) copies to the COR, a copy for UEC and one (1) copy for record. The format of the report shall be left up to the Contractor, but the report shall contain the following information:
1.) Name and contact number of person reporting the spill 2.) Date and time of incident 3.) Location and source of spill 4.) Substance or pollutant spilled 5.) Amount spilled and rate of discharge 6.) Any damages or injuries involved 7.) Extent of area impacted 8.) Potential hazards 9.) Actions taken 10.) Organizations contacted 11.) Remarks Section - that addresses the cause of the spill (e.g. human error, equipment, etc.) and whether 911 was called and which agencies responded.
1.27 Environmental Training: Upon COR receipt of the “No Hazardous Waste Generation” certification, the requirements of this section no longer apply.
1.27.1 Contractor personnel performing duties in the service of this PWS shall have training that acquaints the person with the details of Resource Conservation Recovery Act (RCRA) regulations in 40 CFR 260 through 279; applicable State Laws and regulations; DoD, Air Force and local requirements and an annual refresher classes, updates the person on changes to those rules. This training can be obtained through creditable training institutions or companies. All training will be approved by 72 ABW/CEIE, Natural Infrastructure Management (Environmental Compliance). RCRA training is available at http://www.natlenvtrainers.com/RCRA-hazardous-waste.htm, http://www.skillsoft.com/catalog/detail.asp?CourseCode=esh_sah_a34_sh_enus000000, and http://www.lion.com/Storing-Hazardous-Waste-for-LQGs at the Contractor’s expense. Prior to obtaining training, the Contractor shall provide the name of the training institution or company and course description to the COR for approval within ten (10) calendar days after contract award date. Once written approval is received from the COR, the Contractor shall provide the environmental training certificates for employees performing duties in the service of this PWS to the COR within thirty (30) calendar days after contract award date. Annual refresher training certificates for the supervisor and employees managing the initial accumulations points (IAPs) shall be provided to the COR, within ten (10) calendar days after each option year renewal. The COR will forward a copy of the certificates to the UEC.
1.28 Welding and Hot Work Requirements: The Contractor shall obtain an AF Form 592, USAF Welding, Cutting and Brazing Permit, prior to the use of any welding, cutting or brazing equipment. The Contractor shall contact the 72nd ABW Fire & Emergency Services Division's Fire Prevention Office at 405-734-3981 regarding all work that involves welding, cutting, brazing, soldering, tar kettles, and open flame devices. The Contractor personnel who are performing the work shall keep this form with them at all times with them while at the worksite.
The Contractor shall meet the requirements of OSHA Standard 29 CFR 1910 Subpart Q (as applicable) and NFPA Standard 51B Standard for Fire Prevention during welding, cutting, and other hot work and as well as the AF Occupational Safety and Health (AFOSH) Standard 91-5, Welding, Cutting, and Brazing.
1.29 Forms, Technical Orders (T.O.), AFI, Air Force Material Command Instructions (AFMCI), and Publications: The Contractor shall obtain the forms and publications expressly required to perform the work in this contract via the internet at www.e-publishing.af.mil. In the event a form or publication is not available online, the Government POC will provide the form, instruction, or publication to the Contractor upon the Contractor’s written request (e-mail is acceptable). In the event, laws, regulations, T.O.’s, AFI’s, or AFMCI’s change during the term of this contract, the Contractor shall be required to comply as the changes come into effect. Contractors delivering or handling official United States Air Force (USAF) records shall comply with the applicable records management regulations in AFI 33-322, Chapter 3, in its entirety.
1.30 Housekeeping: The Contractor shall keep the work areas clean and neat IAW industry standards, OSHA, fire and safety standards, and this PWS.
1.31 FOD and DOP: Contractor personnel who work in or travel though areas near operational and production aircraft, engines, munitions, missiles, drones, space systems, support equipment, Aerospace Ground Equipment (AGE), trainers, and the Contactor personnel operating vehicles and equipment on flight lines, runways, taxiways, parking ramps, and in aircraft hangers and maintenance areas are required to receive the FOD/DOP training and to comply with AFI 36-2232, AFMC Supplement 1, paragraph 9.2., and A4.3.4. (Initial)/A4.3.5. (Refresher). The Contractor and Contractor personnel shall acknowledge the FOD/DOP training either by viewing the Digital Versatile Disc (DVD) provided by the Government POC or the You Tube site, http://www.youtube.com/watch?v=tYcbodjFPnM. The Contractor shall provide a contractor devised certificate to the Government POC for each employee within five (5) business days after the contract award date. The certificates shall have the title of the training, the name of the person who received the training, and the date of the training. The Contractor shall also ensure all new employees view the FOD/DOP training and provide a contractor devised certificate of training to the Government POC prior to the employees starting work in the OC-ALC shops. On an annual basis, the Contractor and Contractor personnel shall be required to review the FOD/DOP training and to provide an updated contractor devised certificate of training to the Government POC within five (5) business days of the new period of performance (PoP) start date.
1.32 Tool Control and Accountability: While performing contract services in or around Maintenance Production Shops, which includes ramp areas, the Contractor shall comply with AFI 21-101_AFMC Supplement 1, 21-101, Chapter 10 (all paragraphs) and OC-ALCI 21-112, paragraph 14.1. and 14.5.3. The Contractor shall provide the completed MXRIWRS Form 032 prior to performing work in the OC-ALC industrial areas. The MXRIWRS Form 032 is available from the Government POC. The Contractor shall provide a Contractor Tool Listing, MXRIWRS Form 032, to the Government POC within five (5) business days after (insert type of action, i.e. PM, RM, etc.) actions. The Contractor or Contractor’s personnel shall inventory the container or bag of tools at the beginning of each work day and at the end of each work day. The Contractor personnel shall immediately notify the Government POC of any tools that are missing or lost from the work area or container (e.g. tool or job box or tool bag). The Government POC will report any missing Contractor’s tools which have not been located within one (1) hour after notification to the appropriate Government personnel. The Contractor shall obtain the Form 32 from the Government POC. The CM shall ensure each employee on the job site receives a briefing from the Government POC about Housekeeping, FOD/DOP, and Tool Control prior to starting work in OC-ALC Industrial Areas.
1.33 Privately Owned Motor Vehicles (POV): Contractor personnel shall comply with the directives pertaining to operation of POVs on Tinker AFB per AFMAN 31-116, in its entirety, “Motor Vehicle Traffic Supervision”. The Contractor shall comply with Tinker AFBI 24-302, in its entirety for the operation of POVs within Tinker AFB.
1.34 Required Initial and Refresher Courses for On-Base Driver’s Training: The Contractor and all Contractor employees shall take and pass the on-base Driver’s Training Course before driving on or in the Ramp areas. The Contractor shall contact the Government POC to schedule training. On an annual basis, the Contractor shall take the refresher on-base Driver’s Training Course. The Contractor shall submit each employee’s on-base Driver’s Training Course certificates to the Government POC upon completion of the initial or refresher courses.
1.35 FOD Training for Vehicle Operations: Vehicle operators shall complete all FOD awareness and prevention training as well as testing requirements before driving any vehicle on the flight line (Reference Tinker AFBI 13-202 in its entirety).
1.35 Restricted Area Badge Holders: The Contractor shall contact the COR within five (5) business days after the contract award date for details and forms. The Contractor employees shall submit a request for an identification credential, AFMC 496, within seven (7) business days of the contract award date. After the contractor badge is issued, the Contractor’s security manager shall initiate the AF 2583, Installation Records Check, by taking the form to Building (Bldg.) 6611. The Contractor shall also fill out the AF 2586, Restricted Area Badge paperwork, then submit it with the AF 2583 to the Security Forces, 72 SFS Pass and Registration section, at Bldg. 6611. Prior to the Contractor entering the restricted area, the COR will provide Phase I Security Training which explains the do's and don’ts for the restricted areas applicable to the Contractor.
1.36 Contractor IDs: All contractor badges shall be surrendered when the contract expires, are no longer needed, or when the contract personnel are no longer working under the contract or for the Contractor. The contractor IDs expire on the last day of the current contract PoP. If the contract is extended, the Contractor and Contractor personnel shall obtain new ID badges. The requirement to obtain new badges includes the CAC ID, the DBIDS ID, and AF Form 1199C, Controlled/Restricted Area Badge.
1.36.1 All CAC cards shall be returned to the Pass and Registration, Bldg. 6611, upon the completion of the contract, when no longer needed or contract personnel are no longer working under the contract or working for the Contractor. Upon issue of the CAC by Pass and Registration, the Contractor shall be responsible for employees displaying and surrendering the card IAW the Installation Integrated Defense Plan, Tinker Plan 31-101, in its entirety. Upon five (5) calendar days of the badge being returned to Pass and Registration, the Contractor shall provide copies of the turn-in receipts to the COR either by US Postal Service or email.
1.36.2 Contractors are assessed a fine of $50.00 if CAC IDs, AF Form 1199C’s, AFMC Form 387s, or DBIDS IDs are lost, stolen, or not returned to the Pass and Registration, Bldg. 6611 when the badges have expired or are no longer required. The 72 Security Forces Squadron (SFS) will attempt to fine the contract if money cannot be collected from the Contractor.
1.37 Foreign Nationals: The Contractor shall notify the Government POC before sending a Foreign National representative to perform services. Special rules apply for foreign nationals visiting a US Government facility.
1.38 Safety and Health on Government Installations: While performing work under this contract on a Government installation, the Contractor shall comply with federal, state and local regulations, and AFI 91-203, “Air Force Consolidated Occupational Safety Instruction”, as established by this contract and Appendix C. The Contractor shall notify the CO, Government POC, and Government Contract Administrator (CA) within one (1) business day of any injuries that occur to contractor personnel while they are on the installation. The Contractor shall notify the CO, Government POC, and Government CA within one (1) business day of damage to Government property or equipment during the execution of the contract.
1.39 Emergency Procedures: The Contractor personnel shall follow the direction of the Government personnel with regard to emergency procedures, such as fire, tornado, active shooter, bomb threats, or other emergency. It is the responsibility of the Contractor to provide guidance and to establish procedures for its employees to respond to an emergency. It is the Contractor’s responsibility to account for their employees following an emergency evacuation. The Contractor personnel shall participate with the Government personnel in all fire and tornado drills at no additional cost to the Government.
1.40 Training – General: The Government POC will provide training via slides, video, or classroom prior to the Contractor performing work at the OC-ALC. The Government will be responsible for all approved costs associated with the training identified below. The Government POC will document training on and maintain copies of the completed AF IMT 1151, Training Attendance and Rating, as part of the contract surveillance file. For purposes of identification and compliance with Personally Identifiable Information (PII) requirements, only the last four (4) of the contractor employee’s Social Security Number (SSN) will be input on the form.
1.40.1 The Contractor shall contact the Government POC prior to work being performed in order to accomplish the required training or to verify the required training as listed below has been completed:
| Contractor Required Courses |
| Course Number |
| FOD and DOP Awareness Training Course Initial |
| CHPMAS0000400SU |
| AFMC FOD and DOP Awareness Training Refresher |
| CHPMAS0001301CB |
| Initial Fire Safety and Prevention Training |
| CTESAF0000100SU |
| Refresher Fire Safety and Prevention Training, Computer Based Training (CBT) |
| CTEMAS0002900CB |
| OC-ALC Environmental Accountability/Solid Waste Training, CBT |
| MTEMAS9713800BR |
| OC-ALC Human Factors Training, CBT |
| MTEMAS9700501BR |
| Environmental Management Systems (EMS) - General Awareness Training |
| MTEENV9733070BR |
| Contractor Initial Airfield Driving Block Training Course (OC-ALC Contractors Only) |
| C03530C |
| Airfield Driving Annual Refresher, CBT |
| C03530 |
| Contractor Airfield Driving Annual Refresher (OC-ALC Contractors Only) |
| C03530CR |
| Flightline Drivers Training Initial Course |
| MTEMAS0000135SU |
| Flightline Renewal Briefing |
| MTEMAS0006135JT |
| Airfield Driver Competency Card Initial/Annual Training Update |
| MTESAT0006134JT |
| Controlled Area Training |
| MTEMAS9712900BR |
| Controlled/Restricted Area Training |
| MTEMAS9710130BR |
Section Two (Reserved)
Section Three
Government Furnished Property (GFP) And Services
3.1 Government Furnished Property.
3.1.1 Government Property Repair/Maintenance On-Base is not considered Government Furnished Property (GFP). FAR Parts 45 and 52.245 plus supplements are not applicable to Government Property Repair/Maintenance On-Base. The responsible Government Organizations (76 AMXG) for Government Property Repair/Maintenance On-Base will be responsible for the Government Property inventory, record keeping, reporting requirements (including Report of Survey), and disposal of all Government Property requiring repair/maintenance on-base during the performance of this contract.
3.1.2 GFP Exceeds $150,000 - Repair/Maintenance Off-Base. Not Applicable.
3.1.3 GFP Not Exceed $150,000 - Repair/Maintenance Off-Base. Not Applicable.
3.2 Shared Property of the Government. Not Applicable.
3.3 Government Furnished Services (GFS) are applicable during the performance of this contract. The Government will furnish the following services at Tinker AFB, OK:
3.3.1 Security Forces. The Government will provide general on-base security forces’ service. The security forces’ telephone numbers are 911 for emergencies, 405-734-2000 for crimes in progress and 405-734-3737 for non-emergency calls. The off-base 911 center receives 911 cell phone calls. Cell phone callers need to advise the 911 off-base center they are on TAFB in order to be connected with the on-base 911 center.
3.3.2 Fire Emergency and Routine Services. The Government will provide general on-base fire protection services. The Contractor shall comply with fire prevention rules and regulations enforced by the TAFB Fire Prevention Branch. Call 911 for emergencies. For routine fire prevention matters call 405-734-3981 or 405-734-3982 and 405-734-7964 for after hours and weekends. For routine calls to dispatch call 405-734-7964.
3.3.2.1 NOTE: If applicable, Government Contracting Officer Representative (COR) or Government Point of Contact (GPOC) verify if the Government will provide, inspect, and maintain the fire extinguishers in Contractor occupied space.
3.3.4 Utilities. The Government will provide utility services. These utilities include natural gas, electricity, water, and sewer for the sole purpose of accomplishing this contract. If the contractor requires additional utility services, it shall be the contractor’s responsibility to provide. Contractor shall use due care and diligence in efforts to conserve utilities to reduce utility costs.
3.3.5 Workspace. The Government will provide access to the equipment and adequate workspace around the equipment.
3.4 Intangible Government Property. Not Applicable.
3.5 Contractor Acquired Property (CAP), Time & Material (T&M), Labor Hour (LH), Cost, or Travel Contract Line Item Numbers (CLINS).
Not Applicable.