DIDs,_CDRLs_Trans_Pkg.pdf

PDF 1 MB Posted

Attached to
Repair of Fuel Quantity Indicator Federal contract opportunity
Solicitation number
FA8117-18-Q-0011
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Tinker Air Force Base

About this file

DIDs, CDRLs, Transportation, Pkging

View the file

Other files for this federal contract opportunity

Other files attached to Repair of Fuel Quantity Indicator, newest first.
File Type Posted
2595702_PWS.docx DOCX document
FA811718Q0011.pdf PDF
SynopsisFD20301802882.doc DOC document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

For the best experience, open this PDF portfolio in

Acrobat X or Adobe Reader X, or later.

Get Adobe Reader Now!

http://www.adobe.com/go/reader

DATA ITEM DESCRIPTION

Title: TEARDOWN DEFICIENCY REPORT

Number: DI-PSSS-81534A Approved Date: 20160608

AMSC Number: F9670 Limitation: N/A

DTIC Applicable: No GIDEP Applicable: No

Preparing Activity: 11 (AFLCMC/EZSC) Project Number: PSSS-2015-024

Applicable Forms: N/A

Use/Relationship: The Teardown Deficiency Report provides a factual narrative analysis of a deficiency which has been noted on equipment.

a. This Data Item Description (DID) is applicable when contractors are responsible for maintaining custodial records for government property being repaired.

b. This DID contains the format, content and intended use information for the data deliverable resulting from the work task described in the solicitation.

c. This DID supersedes DI-ALSS-81534.

Requirements:

1. Reference documents. None.

2. Format. The Teardown Deficiency Report shall be in the contactor’s format.

3. Content. This report shall include an analysis of the deficiency which includes cause of failure, recommended corrective action and recommendations for actions to prevent recurrence of the failure/deficiency, and the applicable category of the failure defined as follows:

a. Workmanship and non-conformance. Any deficiency (e.g., physical, chemical, electrical, functional) noted in materiel which is attributed to non-conformance to applicable specifications, drawing, standards, or Technical Order (TO); or workmanship during manufacture, repair modification or maintenance.

b. Material failure. The failure of an end item which was attributable to neither the repair nor the manufacturing process, but was due to an unpredictable failure of an internal component or sub-assembly.

c. No defect found/could not duplicate: Investigation of the exhibit revealed no deficiency.

Equipment conforms to specifications and TO standards and procedures.

d. Technical data, deficiency: Technical data (including TOs, drawings, and work specifications) was deficient or inadequate so as to cause the deficiency/failure on the item.

e. Field induced deficiency. Deficiency confirmed by the investigation to have been caused by operator error, i.e., wrong voltage applied, misaligned, maladjusted, mishandling, or not used for intended purpose.

DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited.

Source: https://assist.dla.mil -- Downloaded: 2016-06-27T17:52Z Check the source to verify that this is the current version before use.

DI-PSSS-81534A

f. Maintenance deficiency. An unfavorable characteristic of an item that impedes the accomplishment of maintenance operations which results in excessive maintenance operations and/or in excessive maintenance man-hour consumption.

g. Design deficiency. A condition that limits or prevents the use of material for purpose intended or required where the material meets all other specifications.

h. Handling or shipping deficiency. A deficiency induced by improper handling or shipping, i.e., improper packaging, which prohibits the use for intended purpose.

i. Packaging specifications inadequate - not complied with. Unsatisfactory conditions including item damage resulting from improper packaging.

End of DI-PSSS-81534A.

Source: https://assist.dla.mil -- Downloaded: 2016-06-27T17:52Z

TITLE: COUNTERFEIT PREVENTION PLAN

Number: DI-MISC-81832 Approval Date: 20110121 AMSC Number: 9181 Limitation:

DTIC Applicable: No GIDEP Applicable: No Office of Primary Responsibility: NRO Applicable Forms: N/A

Use/Relationship: The Counterfeit Prevention Plan will be used by the procurement activity to determine and evaluate the effectiveness of the contractor’s counterfeit protection plan and award fee.

a. This Data Item Description contains the format and content preparation instructions for the data product generated by the specific and discrete task requirements delineated in the statement of work.

b. This DID is related to Parts, Materials and Processes Selection List (PMPSL).

c. This DID is related to “As Designed” and “As Built” Parts List.

d. The Counterfeit Prevention Plan will be updated as counterfeiting methods evolve to include any new indicators, as well as new prevention processes needed (either discovered directly or provided by the Government).

1. The Counterfeit Prevention Plan shall be in contractor format and shall include the following, as a minimum:

a. Procurement practices and procedures to include procurement of all parts and materials from original qualified parts/materials equipment manufacturer (OEM) or it franchised/authorized distributor.

b. Procurement practices and internal processes used for exceptions to buying from

OEM or OEM franchised distributors in cases where items are no longer available including a process to qualify/certify non-OEM parts & materials.

c. Monitoring procedures to include the delivery of test results from random sampling and supply chains surveillance that does not assume any source is safe to identify possible penetration of OEM supply chain.

d. Training/certification program for receiving inspectors.

e. Process to verify counterfeit.

DI-MISC-81832

- 2 -

f. Processes to identify, store, and report counterfeit parts.

g. Process to ensure subcontracts contain the following requirements (As a minimum):

(1) Requirements to procure only from Original Equipment Manufacturer

(OEM) or OEM franchised distributors

(2) Procurement practices and internal processes used for exceptions to buying from OEM or OEM franchised distributors including a process to qualify/certify non-OEM parts & materials obtained

(3) Requirements to monitor supply (including delivery of test results from random sampling and supply chain surveillance that does not assume any source is safe) to identify possible penetration of OEM supply chain

(4) Training/certification program for receiving inspectors

(5) Process to verify counterfeit

(6) Processes to identify, store, and report counterfeit parts.

(7) Notification procedure (tailored to specific sub-contractor based on following Notification Procedure)

h. Self-audit of internal processes.

i. Monitor processes at all subcontractor levels processes and verify compliance through on-site audits.

j. Notification Procedure:

(1) Step 1: The contractor shall quarantine all suspect products pending further direction. The contractor shall provide a statement, with problem description, justifying why this is considered suspect and how it was detected. The contractor shall NOT notify the supplier that the items are suspected as being counterfeit items. However, consultation with the OEM is authorized. Make certain the parts and all members of the lot procured for use on this contract are stored in correct environmental controls. These parts need to be protected as evidence.

(2) Step 2: Contractors that identify suspect items shall immediately notify their customer that is the next link toward the prime contractor.

Notification shall be passed up the customer chain until reaching the prime contractor. The prime contractor shall immediately notify the cognizant Contracting Officer (CO) and Contracting Office Technical Representative (COTR) of all suspect items identified.

- 3 -

(3) Step 3: The contractor shall make certain that the original documentation is secured as evidence and maintain any and all documentation associated with the part to include:

a. Part information such as part identifying number, lot date code, manufacturer information and originator/point of contact information

b. Any information reflecting part procurement/acquisition traceability which should include a copy of the purchase order, any and all correspondence between the buyer and the supplier to include: e-mails, records of phone conversations and paper letters of correspondence

c. Part documentation from the purported original manufacturer, distributors and suppliers (certificate of compliance and certificate of conformance)

d. All visual examination and physical analysis/testing results and the technical data package showing that the parts passed the required screening and qualification tests

e. List of company products affected

(4) Step 4: Determine that the part is or is not counterfeit (Usually accomplished as part of root cause analysis of non-conforming parts and/or materials)

(5) Step 5: If the parts are found to be counterfeit, they shall be isolated and controlled pending direction from law enforcement.

(6) Step 6: The contractor shall provide any additional required information to the government’s investigation team

END OF DI-MISC-81832

PACKAGING REQUIREMENTS

PURCHASE INSTRUMENT NUMBER: FD20301802882-00 VERSION: 1

MIL-STD 129 REVISION: R MIL-STD 2073-1 REVISION: E

THE FOLLOWING STATEMENT IS IN COMPLIANCE WITH THE UNITED NATIONS-IMPLEMENTED RESTRICTIONS ON WOOD PACKAGING MATERIAL (WPM). THIS REQUIREMENT IS SPECIFICALLY CONCERNED WITH INVASIVE SPECIES SUCH AS THE PINEWOOD NEMATODE. WPM IS DEFINED AS WOOD PALLETS, SKIDS, LOAD BOARDS, PALLET COLLARS, WOODEN BOXES, REELS, DUNNAGE, CRATES, FRAMES, AND CLEATS. THE STATEMENT BELOW CITES THE REQUIREMENTS IN DETAIL AND COVERS LUMBER FOR BUILDING CONTAINERS AND PALLETS USED FOR DELIVERIES RESULTING IN SHIPMENTS WORLDWIDE (DIRECT, OR THROUGH AIR LOGISTICS CENTERS (ALC), CONTAINER CONSOLIDATION POINTS (CCP), OR OTHER BASES). WOODEN LUMBER, WOODEN

PALLET AND PACKAGING/CONTAINER STATEMENT:

ALL WOODEN LUMBER, WOODEN PALLET'S, AND WOODEN CONTAINERS PRODUCED ENTIRELY OR IN PART OF WOOD PACKING MATERIAL (WPM) SHALL BE CONSTRUCTED FROM DEBARKED WOOD IN ADDITION TO THE APPLICATION OF HEAT-TREATED (HT) MATERIAL (HT TO 56 DEGREES CENTIGRADE OR 133 DEGREES FAHRENHEIT FOR 30 MINUTES). CERTIFICATION/MARKING IS REQUIRED BY AN ACCREDITED AGENCY RECOGNIZED BY THE AMERICAN LUMBER STANDARDS COMMITTEE (ALSC). FOR REFERENCE DOCUMENTATION, SEE LATEST REVISION OF "INTERNATIONAL STANDARDS FOR PHYTOSANITARY MEASURES" (ISPM)NO.15), "REGULATION OF WOOD PACKAGING MATERIAL IN INTERNATIONAL TRADE."

PACRN: PACKAGING REQUIREMENT: PRESERVATION LEVEL: PACKAGING LEVEL: SPI: SPI REV: SPI DATE:

AAA MIL Long Line Packaging MIL B

ITEM(S):

6680015333605RK

CODED DATA:

QUP ICQ

PRES

METH CD

MTL

WRAP

CUSH

DUNN CT

UNIT

CONT

INT

CONT UCL

SPEC

MKG

UNIT PACK

WEIGHT

LENGTH

WIDTH

DEPTH

CUBE OPI

AAA 33 1 00 EA NA A NR EC B 17 4.50 6.3 6.3 10.5 0.241 M

ADDITIONAL PACKAGING AND CONTAINER MARKING REQUIREMENTS:

SUPPLEMENTAL PACKAGING INSTRUCTION TEXT:

VENDOR PACKAGING INSTRUCTIONS:

Military Packaging and Marking Items shall be packaged in accordance with MIL-STD-2073-1, Standard Practice for Military Packaging. Shipping and storage markings shall be in accordance with MIL-STD-129, Standard Practice for Military Marking.

Shipping Container Marking Shipping containers shall be marked meeting the following criteria: (a) MIL-STD-129, Standard Practice for Military Marking. (b) Bar code format shall conform to bar code symbology Format 3 of 9, Code 39 as specified in MIL- STD-129. (c.) Additional marking and/or bar coding requirements exceeding those of MIL-STD-129 (e.g., unit serial numbers, original equipment manufacturers (OEM) name, or OEM model number, as specified on the AFMC Form 158.

Page 1 of 5AFMC 158 Version 1Generated by PRPS using Jasper Reports on 12 Sep 2018

AAB MIL Long Line Packaging MIL B

6680015333625RK

Items shall be packaged in accordance with MIL-STD-2073-1, Standard Practice for Military Packaging. Shipping and storage markings shall be in accordance with MIL-STD-129, Standard Practice for Military Marking.

Shipping Container Marking Shipping containers shall be marked meeting the following criteria: (a) MIL-STD-129, Standard Practice for Military Marking. (b) Bar code format shall conform to bar code symbology Format 3 of 9, Code 39 as specified in MIL- STD-129. (c.) Additional marking and/or bar coding requirements exceeding those of MIL-STD-129 (e.g., unit serial numbers, original equipment manufacturers (OEM) name, or OEM model number, as specified on the AFMC Form

AAC MIL Long Line Packaging MIL B

6680015333624RK

Items shall be packaged in accordance with MIL-STD-2073-1, Standard Practice for Military Packaging. Shipping and storage markings shall be in accordance with MIL-STD-129, Standard Practice for Military Marking.

Shipping Container Marking Shipping containers shall be marked meeting the following criteria: (a) MIL-STD-129, Standard Practice for Military Marking. (b) Bar code format shall conform to bar code symbology Format 3 of 9, Code 39 as specified in MIL- STD-129. (c.) Additional marking and/or bar coding requirements exceeding those of MIL-STD-129 (e.g., unit serial numbers, original equipment manufacturers (OEM) name, or OEM model number, as specified on the AFMC Form

Page 2 of 5AFMC 158 Version 1Generated by PRPS using Jasper Reports on 12 Sep 2018

AAD MIL Long Line Packaging MIL B

6680015333627RK

Items shall be packaged in accordance with MIL-STD-2073-1, Standard Practice for Military Packaging. Shipping and storage markings shall be in accordance with MIL-STD-129, Standard Practice for Military Marking.

Shipping Container Marking Shipping containers shall be marked meeting the following criteria: (a) MIL-STD-129, Standard Practice for Military Marking. (b) Bar code format shall conform to bar code symbology Format 3 of 9, Code 39 as specified in MIL- STD-129. (c.) Additional marking and/or bar coding requirements exceeding those of MIL-STD-129 (e.g., unit serial numbers, original equipment manufacturers (OEM) name, or OEM model number, as specified on the AFMC Form

AAE MIL Long Line Packaging MIL B

6680015333609RK

Items shall be packaged in accordance with MIL-STD-2073-1, Standard Practice for Military Packaging. Shipping and storage markings shall be in accordance with MIL-STD-129, Standard Practice for Military Marking.

Shipping Container Marking Shipping containers shall be marked meeting the following criteria: (a) MIL-STD-129, Standard Practice for Military Marking. (b) Bar code format shall conform to bar code symbology Format 3 of 9, Code 39 as specified in MIL- STD-129. (c.) Additional marking and/or bar coding requirements exceeding those of MIL-STD-129 (e.g., unit serial numbers, original equipment manufacturers (OEM) name, or OEM model number, as specified on the AFMC Form

Page 3 of 5AFMC 158 Version 1Generated by PRPS using Jasper Reports on 12 Sep 2018

AAF No Packaging Data Required

6680OSH1808C5

AAG No Packaging Data Required

6680DTH180299

Page 4 of 5AFMC 158 Version 1Generated by PRPS using Jasper Reports on 12 Sep 2018

AAH No Packaging Data Required

6680OAH180118

ORGANIZATION / OFFICE SYMBOL:

406 SCMS / GULAA

PACKAGING SPECIALIST:

Holinsworth, Howard L

PHONE NUMBER:

405-582-9764 / 852-9764

SIGNATURE:

//SIGNED//Holinsworth, Howard L

DATE:

18226 - 14 AUG 2018

Page 5 of 5AFMC 158 Version 1Generated by PRPS using Jasper Reports on 12 Sep 2018

TRANSPORTATION DATA FOR SOLICITATIONS

COMMODITY: See Continuation

PURCHASE INSTRUMENT NUMBER:

FD20301802882-00

DATE INITIATED:

14 AUG 2018

STOCK NUMBER: See Continuation

X ORIGIN DESTINATION OTHER DATA / FIRST ARTICLE F.O.B. DESTINATION(Specify)

F.O.B. TERMS RECOMMENDED AS BEST SUITED FOR THIS PROCUREMENT

TRANSPORTATION PROVISIONS / CLAUSES FAR CITATION

F.O.B. Origin 52.247-29 F.O.B. Origin - Prepaid Freight Shipment(s) shall be made with freight transportation costs prepaid by the Contractor, who shall verify with the freight shipment company that rates for this/these shipment(s) are equal to or lower than those used for U.S. Government shipments. If rates are not equal to or lower than those for Government shipments, contact the Contracting Officer for additional instructions. Shipping charges are to be shown as a separate item on the payment invoice. If the charges are $100 or more, a copy of the freight charges invoice must be attached to the payment invoice. Failure to properly annotate the invoice and provide a copy of the carrier's bill may result in those costs being disallowed.

Vendor Transportation Instructions

Freight Classification Description 52.247-53 Contact DCMA Transportation Contact DCMA Transportation on ALL "DCMA Administered" contracts prior to shipment for shipping instructions using the DCMA Shipment Instruction Request (SIR) eTool System, at http://www.dcma.mil <http://www.dcma.mil/> for ALL FOB:

Origin, Foreign Military Sales (FMS), and FOB: Destination OCONUS/Export movements to obtain the appropriate DOD regulatory clearances, shipping documentation and instructions from your cognizant DCMA Transportation Office. If you are new to DCMA, and do not already have a SIR eTool account, you will first need to request an account via DCMA External Web Access Management (EWAM) application which can be accessed at http://www.dcma.mil. If you need additional assistance, email DCMA Transportation Group at: Transportation.Division@dcma.mil. Do not move any freight to a water or aerial port prior to contacting DCMA or it will become frustrated. Failure to contact the responsible DCMA may result in vendor incurring additional expenditures.

Vendor Transportation Instructions

IAW BASIC CONTRACT FD20301802882-00

Note to Contractor: Contact CTO if problems arise. Ship Door-to-Door commercial express carrier service for movement of MICAP and project codes (TP-1 and TP-2/RDD 777): 122, 123, 700, 780 (With restrictions), 879, 880, 9FF, 9FV, 9FX, 9GF, 9GJ, 9GV, 9GS, 9GD, Surge and 720.

TACRN:

AAA

TRANSPORTATION FUNDS INFORMATION:

Purchase Instrument Line LOA: 97X4930.FC04 648 47GT 159999 01K010 00000 UJDBLZ 503000 F03000 FSR: 013340 PSR: K15100

First Destination Transportation Account Code:

Miscellaneous Obligation / Reimbursement Document:

Second Destination Transportation Account Code: F2RS

FMS LOA:

Additional Funding Information:

ITEM / SHIP TO(s):

NSN / Pseudo NSN: 6680015333605RK

Purchase Instrument Line Item Number: 0001

Ship to (DoDAAC / MAPAC): SW3211

Mark For: Acct 09

Ship To (Address): DLA DISTRIBUTION DEPOT OKLAHOMA

TINKER AFB OK 73145-8000

73145 - 8000

USA

WPOD:

APOD:

BBP / CCP:

RIC: 1

Requisition Number:

Supplemental Address:

FMS Case:

3301 F AVE CEN REC BLDG 506 DR 22

Ship To (Remarks):

Page 1 of 6DD FORM 1653 Version 1Generated by PRPS using Jasper Reports on 12 Sep 2018

NSN / Pseudo NSN: 6680015333605RK

Purchase Instrument Line Item Number: 0002

NSN / Pseudo NSN: 6680015333609RK

Purchase Instrument Line Item Number: 0003

NSN / Pseudo NSN: 6680015333609RK

Purchase Instrument Line Item Number: 0004

Page 2 of 6DD FORM 1653 Version 1Generated by PRPS using Jasper Reports on 12 Sep 2018

NSN / Pseudo NSN: 6680015333624RK

Purchase Instrument Line Item Number: 0005

NSN / Pseudo NSN: 6680015333624RK

Purchase Instrument Line Item Number: 0006

NSN / Pseudo NSN: 6680015333625RK

Purchase Instrument Line Item Number: 0007

Page 3 of 6DD FORM 1653 Version 1Generated by PRPS using Jasper Reports on 12 Sep 2018

NSN / Pseudo NSN: 6680015333625RK

Purchase Instrument Line Item Number: 0008

NSN / Pseudo NSN: 6680015333627RK

Purchase Instrument Line Item Number: 0009

NSN / Pseudo NSN: 6680015333627RK

Purchase Instrument Line Item Number: 0010

Page 4 of 6DD FORM 1653 Version 1Generated by PRPS using Jasper Reports on 12 Sep 2018

NSN / Pseudo NSN: 6680DTH180299

Purchase Instrument Line Item Number: 0011

NSN / Pseudo NSN: 6680OAH180118

Purchase Instrument Line Item Number: 0012

NSN / Pseudo NSN: 6680OSH1808C5

Purchase Instrument Line Item Number: 0013

EVALUATION OF PORT BID OR PROPOSAL:

SOLICITATION DATA NOTES:

OTHER TRANSPORTATION DATA:

Page 5 of 6DD FORM 1653 Version 1Generated by PRPS using Jasper Reports on 12 Sep 2018

NAME

Langford-Scott, Dorothy A

ORGANIZATION / OFFICE

SYMBOL

406 SCMS / GULAA

COMMERCIAL / DSN

PHONE

478-327-6592 / 497-6593

SIGNATURE

//SIGNED//Langford-Scott, Dorothy A

DATE

14 AUG 2018

Page 6 of 6DD FORM 1653 Version 1Generated by PRPS using Jasper Reports on 12 Sep 2018

Title: COMMERCIAL ASSET VISIBILITY AIR FORCE (CAV AF)/GOVERNMENT

FURNISHED MATERIAL REPORT

Number: DI- MGMT-81634C Approved Date: 20150911 AMSC Number: 9581 Limitation: N/A DTIC Applicable: No GIDEP Applicable: No Preparing Activity: 11 (AFMC/A4RM) Project Number: MGMT-2015-025 Applicable Forms: N/A Use/Relationship: CAV AF is a web based system used to permit the reporting of end item repair and Government Furnished Material (GFM) transactions incident to the execution of Contract Depot Maintenance (CDM) contracts for the purpose of providing visibility and oversight of these assets.

a. This Data Item Description (DID) contains the format and content preparation instructions for the data product generated by the specific and discrete task requirements as delineated in the contract.

b. This DID may be used on any depot-level repair contract.

c. This DID supersedes DI-MGMT-81634B.

1. Reference documents. The applicable issue of the documents cited herein, including their approval dates and dates of any applicable amendments, notices, and revisions, shall be as specified in the contract.

2. Format. Format. The CAV AF System transactions are processed via the World Wide Web, https://www.cavaf.com. Input formats are found in the CAV AF Users Guide. Repair contractors will be furnished with a copy of the CAV AF Users Guide.

3. Content. The contractor reporting shall contain the following transactions and report types as described in the CAV AF Users Guide:

a. End Items:

(1) Receipt

(2) Induction

(3) Awaiting Parts (AWP)

(4) Re-induction

(5) Survey/Scrap

(6) Completion

(7) Shipment

(8) Proof of Shipment

(9) Reversals

Source: https://assist.dla.mil -- Downloaded: 2016-04-12T17:40Z https://www.cavaf.com/

DI-MGMT-81634C

(10) Assets Beyond Economic Repair (BER) and Maintenance Expenditure Limit (MEL)

(11) Bulk Process

(12) Borrow/Payback

b. Government Furnished Material (GFM):

(1) Requisitions:

(a) Create

(b) Modify

(c) Cancel

(d) Follow-up as appropriate

(2) Receive material:

(a) Modify/reverse material option

(3) Issue material:

(a) Reverse issue of material

(4) Transfer material.

(5) Turn-in material:

(a) Reverse material turn in

(6) Condemnation/Plant Clearance of material:

(a) Condemn an item

(b) Reverse Condemnation

(c) Plant Clearance

(d) Reverse Plant Clearance

(7) Shipping of material:

(a) Material Release Order (MRO)

(b) Redistribution Order (RDO)

(c) After Receipt of Order (ARO)

(d) Reverse Material Shipment

End of DI-MGMT-81634C

Source: https://assist.dla.mil -- Downloaded: 2016-04-12T17:40Z

Title: CONTRACT DEPOT MAINTENANCE (CDM) PRODUCTION REPORT

Number: DI-PSSS-81995 Approved Date: 20150904 AMSC Number: 9576 Limitation: N/A DTIC Applicable: No GIDEP Applicable: No Preparing Activity: 11 (AFMC/A4) Project Number: PSSS-2015-009 Applicable Forms: N/A Use/Relationship: The Contract Depot Maintenance (CDM) Production Report is a two-part report which provides the Government with monthly maintenance production figures, status and accountability of assets at the contractor facility, performance to schedule, anticipated production for the next month, and a summary of unresolved problems at the end of the report period.

a. This Data Item Description (DID) contains the format, content and preparation instructions for the data product generated by the specific and discrete task requirement as delineated in the contract.

b. This DID may be used on any depot level maintenance contract.

1. Format. This report shall be provided in the format of Table I.

2. Content. The report shall consist of two parts and contain the following information:

a. Part I:

(1) As of date: The year, month and day applicable to the report. Data must be through the end of the month.

(2) Block 1, Issuing/Procuring Agency. Include address and Point of Contact.

(3) Block 2, Contractor and activity address code (AAC). The name of the business and the DoDAAC assigned to your business for shipment of material.

(4) Block 3, Contract number and Program or Weapon System supported.

(5) Block 4, Government item manager or technical Point of Contact.

(6) Block A, Item identification. The National Stock Number (NSN), A-1 is the Federal Supply Class (FSC) and A-2 is the National Item Identification Number (NIIN) of the item being reported.

(7) Block B, Delivery/Call Order number. When the awarded contract is a call/delivery order type, this is the applicable order number. When an item is awarded on more than one order, it is repeated for each order until completed. If the current report completes the call, the word “completed” will be added.

(8) Block C, The contract line item number (CLIN). The CLIN assigned to the NSN in the contract.

Source: https://assist.dla.mil -- Downloaded: 2016-04-12T17:42Z

DI-PSSS-81995

(9) Block D, The document/voucher number the item was received under. The document number listed on the shipping documentation the item was received against.

(10) Block E, Quantity on contract or call. E-1 is the quantity of the end items to be repaired on each call/delivery order or contract quantity when orders do not apply. E-2 is the total quantity scheduled for repair cumulative to date.

(11) Block F, Reparables received. Number of reparable items received for repair. F-1 is the quantity of reparables received during the report month. F-2 is the quantity of reparables received cumulative from the start of the contract through report month.

(12) Block G, Reparables inducted into repair during report month.

(13) Block H, Reparables on hand. Number of reparables on hand waiting induction into repair.

(14) Block I, Quantity produced. The quantity produced during the month.

(15) Block J, Serviceables shipped. Serviceables shipped from repair facility. J-1 is the serviceables shipped through report month. J-2 is serviceables shipped cumulative from start of contract.

(16) Block K, Serviceables on hand. The quantity of serviceables on hand awaiting shipping action.

(17) Block L, Quantity condemned. The quantity condemned. L-1 is the quantity condemned during report month. L-2 is the quantity condemned cumulative from start of contract.

(18) Block M, Forecast to complete. The quantity of items scheduled to be produced next month.

(19) Block N, Report date. Enter date of report.

b. Part II, Production problems. Report shall be in narrative format and only required if:

(1) Previous reports production forecast was not shipped.

(2) Current forecast does not equal contract scheduled quantity.

(3) Contract anticipates a problem in the near future.

TABLE I. Contract Depot Maintenance (CDM) Production Report format.

CONTRACT DEPOT MAINTENANCE (CDM) PRODUCTION REPORT Month and As-Of Date

(YYYYMMDD)

Part I

1. ISSUED BY: 2. CONTRACTOR AND ACTIVITY ADDRESS CODE 3. CONTRACT NUMBER/PRGM/WS 4. GOVERNMENT ITEM MANAGER OR TECHNICAL POC

DURING REPORT PERIOD/TOTAL TO DATE

A.

ITEM

IDENTIFICATION

B.

DELIVERY/

CALL NUMBER

C.

CONTRACT

LINE ITEM

(CLIN)

D.

DOCUMENT/

VOUCHER

NUMBER

E.

QTY ON

CONTRACT

OR

DO/CALL

F.

REPARABLES

RECEIVED

G.

QTY

IND TO

WORK

H.

REPS ON

HAND

I.

PROD

J.

SERVICEABLES

SHIPPED

K.

SERV ON

HAND

L.

CONDEMNED

M.

FORECAST PROD

N.

REPORT DATE

FSC NIIN

1 2 1 2 3 1 2 1 2 1 2

Part II, Production Summary

End of DI-PSSS-81995.

Title: GOVERNMENT PROPERTY INVENTORY REPORT

Number: DI-MGMT-80441C Approval Date: 20171101 AMSC Number: 9865 Limitation:

DTIC Applicable: No GIDEP Applicable: No Preparing Activity: MDA Project Number: MGMT-2017-059 Applicable Forms: None

Use/Relationship: This report enables the contractor to periodically provide to the DoD Service/Agency an inventory listing of Government Property (i.e., both Government Furnished Property (GFP) and Contractor Acquired Property (CAP)) in the contractor’s possession (to include subcontractors) by contract.

This DID is applicable to all contracts where Government Property will be furnished by the Government (i.e., GFP) or acquired, fabricated, or otherwise provided by a contractor (i.e., CAP) in performance of a contract.

This DID contains the format and content preparation instructions for the data deliverable resulting from the work task described in the solicitation.

This DID supersedes DI-MGMT-80441B.

Requirements:

1. Format. The report shall be electronic .xls or .xlsx compatible.

2. Content. The report shall contain the following columns/data fields:

A. Contract Number B. Manufacturer CAGE Code (if known) C. Item Name D. Item Description E. Manufacturer Name F. Manufacturer Part Number G. Manufacturer Model Number H. Material Control Number (MCN) (if applicable) I. Serial Number J. National Stock Number (NSN) K. Quantity L. Unit of Measure M. Unit Acquisition Cost N. Location O. Sub Location (if applicable) P. Unique Item Identifier (as registered in the IUID Registry) Q. Type of Government Property (i.e., Government Furnished Property (GFP) or

Contractor Acquired Property (CAP) R. Classification of Government Property (i.e., Communication Security (COMSEC), Equipment (EQP), Material (MAT), Special Test Equipment (STE), or Special Tooling

(ST))

Source: https://assist.dla.mil -- Downloaded: 2018-05-22T20:41Z

DI-MGMT-80441C

S. Posting Reference T. Date of Transaction / Date of Acquisition U. Date Placed in Service V. Date of Last Physical Inventory W. Condition Code

END OF DI-MGMT-80441C

Source: https://assist.dla.mil -- Downloaded: 2018-05-22T20:41Z

AMSC Number: 9865 Limitation:

Requirements:

Title: DEFICIENCY REPORT (DR)

Number: DI-PSSS-81535A Approved Date: 20160524 AMSC Number: F9660 Limitation: N/A DTIC Applicable: No GIDEP Applicable: No Preparing Activity: AF 11 (AFLCMC/EZSC) Project Number: PSSS-2016-013 Applicable Forms: N/A

Use/Relationship: The Deficiency Report (DR) provides complete and accurate deficiency identification on government furnished material (GFM) in repair contracts by contractors to the Government. This information is used by the Government to identify necessary corrective action in accordance with T.O. 00-35D-54, USAF Deficiency Reporting, Investigation, and Resolution.

(Copies of this document are available online at http://www.tinker.af.mil/technicalorders/.)

a. This Data Item Description (DID) contains the format, content, and intended use information for the data deliverable resulting from the work task described in the solicitation.

b. This DID is applicable when contractors are responsible for maintaining custodial records for government property being repaired.

c. This DID interrelates with DI-MGMT-80258, Material Improvement Project (MIP) Report.

(Copies of this document are available online at http://quicksearch.dla.mil.)

d. This DID supersedes DI-ALSS-81535.

1. Reference documents. The applicable issue of the documents cited herein, including their approval dates and dates of any applicable amendments, notices, and revisions, shall be as specified in the contract.

2. Format. The Contractor format is acceptable.

3. Content. The Deficiency Report content shall be as described in Table I.

Source: https://assist.dla.mil -- Downloaded: 2016-06-27T19:20Z http://www.tinker.af.mil/technicalorders/ http://quicksearch.dla.mil/

DI-PSSS-81535A

TABLE I. Deficiency report content.

1. From: Address of Originating Activity

2. To: Office of Primary Responsibility (OPR) for the equipment. Refer to D043 or D086 for guidance.

Subject First Part as applicable:

a. Category I Deficiency Report (CAT I DR)

b. Category II Deficiency Report (CAT II DR)

c. Report Control Number (RCN): An RCN consists of three parts. The first part will be the DoD Activity Address Code (DoDAAC).

The second part will be the last two digits of the calendar year.

The third part will be a 4-digit sequence number that is locally assigned.

3. Description of Deficiency:

Describe in detail what is wrong, the circumstances prior to the difficulty, probable cause, any action taken, and recommendations. Attach copy of supporting documents. Continue on separate sheet if necessary. Ensure that the description answers the questions listed in the instructions on the back of this form

4. Date of Deficiency: Year, month, day deficiency was discovered.

5. National Stock

Number (NSN) NSN and applicable Material Management Aggregation Code (MMAC) of item (see D043 and D086).

6. Nomenclature Noun of item for which report is submitted. Software DRs shall provide nomenclature of programmable hardware.

7. Operating Time at Failure

Hours, cycles, days, miles rounds or others

8. Deficient Item Part Number

Complete Manufacturer part number. If Computer Identification Number (CPIN) is associated with a computer program it shall also be provided.

9a. Manufacturer’s CAGE Code

Unique code assigned to suppliers of government or defense agencies.

9b. Manufacturer/Shipper/ City/State

Complete address of manufacturer or shipper.

10. Quantity Number received, inspected, deficient, and in stock.

11. Serial, lot or batch number Complete item serial number.

12a. Item new, repaired or overhauled

Use one to identify item as appropriate.

12b. Date Manufacturer, Repaired or Overhauled

Year/Month/Day

12c. Last Repair Facility CAGE/DoDAAC/Address

DI-PSSS-81535A

13a. Contract Number Obtain contract number from records service tag, manufacturer/container label, etc. Contract number is critical to processing reports.

13b. Requisition/Document Number

Obtain from tags/labels on item packaging.

13c. Purchase Order Number.

The Purchase Order Number associated with the defective part. This can usually be found on the attached shipping document.

14. Government Furnished Material (GFM)

Yes/No/Unknown

15a. Item Under Warranty Yes/No/Unknown 15b. Warranty Expiration

Date Provide if known.

16. End Item Enter the applicable Equipment Item Code (EIC), Work Unit Code (WUC), or Table of Authorized Material Control Number (TAMCN) for the deficient material.

17. Next Higher Assembly a. NSN – National Stock Number associated with the next higher assembly.

b. NOMENCLATURE – Item name of the next higher assembly.

c. PART NUMBER – Part number assigned to the next higher assembly.

d. SERIAL NUMBER – Serial number from the next higher assembly.

18. End Item a. NSN – National Stock Number associated with the end item.

b. NOMENCLATURE – Name of the end item.

c. TYPE/MODEL – Type or model assigned to the end item configuration.

d. SERIAL NUMBER – Serial number from the end item equipment or system.

19. Current Disposition of Deficient Item

Holding/Disposed or Destroyed/Repaired/Other

20. Location of Deficient Material

Enter the name and location or supply activity that is currently holding the exhibit/deficient material.

End of DI-PSSS-81535A.

Source: https://assist.dla.mil -- Downloaded: 2016-03-18T19:05Z

TITLE: COUNTERFEIT PREVENTION PLAN

Number: DI-MISC-81832 Approval Date: 20110121 AMSC Number: 9181 Limitation:

DTIC Applicable: No GIDEP Applicable: No Office of Primary Responsibility: NRO Applicable Forms: N/A

Use/Relationship: The Counterfeit Prevention Plan will be used by the procurement activity to determine and evaluate the effectiveness of the contractor’s counterfeit protection plan and award fee.

a. This Data Item Description contains the format and content preparation instructions for the data product generated by the specific and discrete task requirements delineated in the statement of work.

b. This DID is related to Parts, Materials and Processes Selection List (PMPSL).

c. This DID is related to “As Designed” and “As Built” Parts List.

d. The Counterfeit Prevention Plan will be updated as counterfeiting methods evolve to include any new indicators, as well as new prevention processes needed (either discovered directly or provided by the Government).

1. The Counterfeit Prevention Plan shall be in contractor format and shall include the following, as a minimum:

a. Procurement practices and procedures to include procurement of all parts and materials from original qualified parts/materials equipment manufacturer (OEM) or it franchised/authorized distributor.

b. Procurement practices and internal processes used for exceptions to buying from

OEM or OEM franchised distributors in cases where items are no longer available including a process to qualify/certify non-OEM parts & materials.

c. Monitoring procedures to include the delivery of test results from random sampling and supply chains surveillance that does not assume any source is safe to identify possible penetration of OEM supply chain.

d. Training/certification program for receiving inspectors.

e. Process to verify counterfeit.

- 2 -

f. Processes to identify, store, and report counterfeit parts.

g. Process to ensure subcontracts contain the following requirements (As a minimum):

(1) Requirements to procure only from Original Equipment Manufacturer

(OEM) or OEM franchised distributors

(2) Procurement practices and internal processes used for exceptions to buying from OEM or OEM franchised distributors including a process to qualify/certify non-OEM parts & materials obtained

(3) Requirements to monitor supply (including delivery of test results from random sampling and supply chain surveillance that does not assume any source is safe) to identify possible penetration of OEM supply chain

(4) Training/certification program for receiving inspectors

(5) Process to verify counterfeit

(6) Processes to identify, store, and report counterfeit parts.

(7) Notification procedure (tailored to specific sub-contractor based on following Notification Procedure)

h. Self-audit of internal processes.

i. Monitor processes at all subcontractor levels processes and verify compliance through on-site audits.

j. Notification Procedure:

(1) Step 1: The contractor shall quarantine all suspect products pending further direction. The contractor shall provide a statement, with problem description, justifying why this is considered suspect and how it was detected. The contractor shall NOT notify the supplier that the items are suspected as being counterfeit items. However, consultation with the OEM is authorized. Make certain the parts and all members of the lot procured for use on this contract are stored in correct environmental controls. These parts need to be protected as evidence.

(2) Step 2: Contractors that identify suspect items shall immediately notify their customer that is the next link toward the prime contractor.

Notification shall be passed up the customer chain until reaching the prime contractor. The prime contractor shall immediately notify the cognizant Contracting Officer (CO) and Contracting Office Technical Representative (COTR) of all suspect items identified.

- 3 -

(3) Step 3: The contractor shall make certain that the original documentation is secured as evidence and maintain any and all documentation associated with the part to include:

a. Part information such as part identifying number, lot date code, manufacturer information and originator/point of contact information

b. Any information reflecting part procurement/acquisition traceability which should include a copy of the purchase order, any and all correspondence between the buyer and the supplier to include: e-mails, records of phone conversations and paper letters of correspondence

c. Part documentation from the purported original manufacturer, distributors and suppliers (certificate of compliance and certificate of conformance)

d. All visual examination and physical analysis/testing results and the technical data package showing that the parts passed the required screening and qualification tests

e. List of company products affected

(4) Step 4: Determine that the part is or is not counterfeit (Usually accomplished as part of root cause analysis of non-conforming parts and/or materials)

(5) Step 5: If the parts are found to be counterfeit, they shall be isolated and controlled pending direction from law enforcement.

(6) Step 6: The contractor shall provide any additional required information to the government’s investigation team

END OF DI-MISC-81832

CONTRACT DATA REQUIREMENTS LIST Form Approved OMB No. 0704-0188(1 Data Item)

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Executive Services Directorate (0704-0188).

Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY

TDP TM OTHER X

D. SYSTEM / ITEM

E-3 / Multiple Items

E. CONTRACT / PR NO.

FD20301802882

F. CONTRACTOR

1. DATA ITEM NO.

A001

2. TITLE OF DATA ITEM

Commercial Asset Visibility Air Force (CAV AF) End Item Reporting

3. SUBTITLE

CAV AF

4. AUTHORITY

(Data Acquisition Document No.) 5. CONTRACT REFERENCE

PWS/SOW

6. REQUIRING OFFICE

422 SCMS/GUMB

7. DD 250 REQ

NO

8. APP CODE

N/A

9. DIST STATEMENT

REQUIRED

10. FREQUENCY

DAILY

11. AS OF DATE

See Block 16

12. DATE OF FIRST

SUBMISSION

13. DATE OF SUBSEQUENT

a. ADDRESSEE

Draft Final

ReproReg

b. COPIES

14. DISTRIBUTION

16. REMARKS

Zilar, Dale NNAME: 02 MAR 2018DATE:

1. The contractor shall report End Item transactional data through electronic submission in CAV AF using the CAV AF web site or CICA XML IAW the referenced DID and/or Contract Repair PWS. This information will be accessed by the program office PMS and by 422 SCMS/GUBAB Contract Monitors in order to ascertain production status.

2. Transactions and data will be submitted by the contractor daily IAW CAV AF Contractor User Guide, Version 9.0.4 or higher. The Contractor shall obtain a valid DoD PKI certificate to log into CAV AF. Each user shall have an Identity Certificate only; an encryption certificate is not required. Reporting must be accomplished for each Contractor facility/location AND any subcontractor locations.

3. Transactional Training will be provided by 422 SCMS/GUBAB Contract Monitors, (405) 736-7171.

4. This DD Form 1423-1 applies to end item repair CAV AF reporting only contracts, commonly referred to as Contractor Furnished Material (CFM) type contracts.

5. It is imperative the CAV AF Proof of Shipment reporting actions are accomplished by the contractor.

Block 10:

a. Contractor reporting requirements to CAV AF shall be accomplished daily and/or one business day of a maintenance action IAW Contractor Users Guide.

b. The method of communication from the contractor to the Air Logistics Complex (ALC) will be mechanized using the CAV AF Online web site IAW CAV AF Contractor User's Guide.

Block 11: Data shall be current within one business day of last End Item maintenance occurrence and reflect an accurate representation/status of all assets at a contractor for repair.

Block 12: Date of first submission shall be within one business day following a maintenance transaction after the contract award date and government training as specified in IAW CAV AF Users Guide.

Block 13: Within one business day of each maintenance action/occurrence.

The contractor's CAV AF reporting shall reflect their inventory property control management system data records which shall represent timely and accurate accountability of AF inventory assets at the physical location(s) of the contractor's repair facility (including subcontractor facilities); shop floor, bond room and/or receiving/shipping docks, etc. for each

COORDINATORS:

OC-ALC 0 1 0

0 1 015. TOTAL

Page 1 of 20DD FORM 1423-1, FEB 2001 Version 2Generated by PRPS using Jasper Reports on 12 Sep 2018

PREVIOUS EDITION MAY BE USED.

G. PREPARED BY

Zilar, Dale N

424 SCMS / GUBAA

405-736-7976

H. DATE

10 SEP 2018

I. APPROVED BY

//DIGITALLY SIGNED//

JOSLIN.STANLEY.C.1124246721

422 SCMS / GUMB 405-582-6794 / 852-6794

J. DATE

A002

Contract Depot Maintenance (CDM) Production Report

CDM Prod

PWS

MTHLY

SEE BLOCK 16

Zilar, Dale NNAME: 20 AUG 2018DATE:

Manual Report:

Ref Block 11, 12, and 13:

Contractor shall report by contract delivery order on all applicable categories, totals and on-hand balances, IAW DI- PSSS-81995, providing TABLE I for EACH repair location, including subcontractor facilities, for the contracts maintenance occurrence actions during the reporting period.

Contractor shall report on production, providing TABLE I for EACH repair location, including subcontractor facilities, for which the contractor produced assets during the reporting period.

Reports will continue to be forwarded unless terminated by the 422 SCMS/GUMB Production Management Specialist (PMS). The report following the final reporting period on contract will be annotated "Final Report".

Complete address for distribution:

3001 Staff Drive, Annex 4, Suite 1AF1 92A Tinker AFB, OK 73145-3033

Commercial phone number: (405)-582-67946 Email preferred: Stanley.Joslin.2@us.af.mil

CONTRACTOR FORMAT ACCEPTABLE UNLESS OTHERWISE DEFINED BY APPLICABLE DATA ITEM

DESCRIPTION (DID).

DID Requirements are NOT tailored.

Delivery CANNOT be deferred.

The contractor's CAV AF reporting shall reflect their inventory property control management system data records which shall represent timely and accurate accountability of AF inventory assets at the physical location(s) of the contractor's repair facility (including subcontractor facilities); shop floor, bond room and/or receiving/shipping docks, etc. for each repair, The report shall be provided within 5 business days of the previous month's last calendar date.

3001 Staff Drive, Annex 4, Suite 1AF1 92A

Attention: Stanley C. Joslin

0 1 0

Page 2 of 20DD FORM 1423-1, FEB 2001 Version 2Generated by PRPS using Jasper Reports on 12 Sep 2018

A003

Teardown Deficiency Report

TDR

LT

D

Zilar, Dale NNAME: 10 SEP 2018DATE:

Changes to the office symbols shall be made by letter through the PCO/ACO without revision to this CDRL.

Block 9: Distribution Statement D: Distribution authorized to the Department of Defense and US DOD Contractors only, Critical Technology. Other requests shall be referred to 422 SCMS/GUEA.

Control Warning Notice: Warning - This document contains technical data whose export is restricted by the Arms Export Control Act (Title 22, USC, Sec 2751 Et Seq) or the Export Administration Act of 1979, Title 50, USC, App 240 I Et Seq, as amended. Violations of these export laws are subject to severe criminal penalties. Disseminate in accordance with provisions of DOD Directive 5230.25.

Destruction Notice for Unclassified Documents: destroyed by any method that will prevent disclosure of contents or reconstruction of the document.

Destruction Notice for Classified Documents: Follow the procedures in DOD 5220.22-M, National Industrial Security Program Operating Manual (NISPOM), Section 5-705, or DOD 5220.0 I M, Information Security Program , Vol 3, Protection of Classified Information.

BLOCKS 10, 11, 12, and 13: To be negotiated upon government's request.

422 SCMS/GUMB 0 1 0

Page 3 of 20DD FORM 1423-1, FEB 2001 Version 2Generated by PRPS using Jasper Reports on 12 Sep 2018

A004

Counterfeit Prevention Plan (CPP)

CPP

422 SCMS/GUEA

BLOCK 9: Distribution Statement D: Distribution authorized to the Department of Defense and US DOD Contractors only, Critical Technology. Other requests shall be referred to 422 SCMS/GUEA.

Control Warning Notice: Warning - This document contains technical data whose export is restricted by the Arms Export Control Act (Title 22, USC, Sec 2751 Et Seq) or the Export Administration Act of 1979, Title 50, USC, App 240 I Et Seq, as amended. Violations of these export laws are subject to severe criminal penalties. Disseminate in

Destruction Notice for Unclassified Documents: destroyed by any method that will prevent disclosure of contents or

Destruction Notice for Classified Documents: Follow the procedures in DOD 5220.22-M, National Industrial Security Program Operating Manual (NISPOM), Section 5-705, or DOD 5220.0 I M, Information Security Program , Vol 3, The plan shall be delivered in electronic PDF format through the Wide Area Workflow (WAWF) system no later than 90 calendar days after contract award. (FA8117)

Contractor format acceptable unless otherwise defined by applicable Data Item Description (DID).

3001 Staff Drive Tinker AFB, OK 73145

Page 4 of 20DD FORM 1423-1, FEB 2001 Version 2Generated by PRPS using Jasper Reports on 12 Sep 2018

B001

1. The contractor shall report End Item transactional data through electronic submission in CAV AF using the CAV AF web site or CICA XML IAW the referenced DID and/or Contract Repair PWS. This information will be accessed by the

2. Transactions and data will be submitted by the contractor daily IAW CAV AF Contractor User Guide, Version 9.0.4 or higher. The Contractor shall obtain a valid DoD PKI certificate to log into CAV AF. Each user shall have an Identity Certificate only; an encryption certificate is not required. Reporting must be accomplished for each Contractor

4. This DD Form 1423-1 applies to end item repair CAV AF reporting only contracts, commonly referred to as

5. It is imperative the CAV AF Proof of Shipment reporting actions are accomplished by the contractor.

a. Contractor reporting requirements to CAV AF shall be accomplished daily and/or one business day of a maintenance action IAW Contractor Users Guide.

b. The method of communication from the contractor to the Air Logistics Complex (ALC) will be mechanized using the

Block 11: Data shall be current within one business day of last End Item maintenance occurrence and reflect an accurate

Block 12: Date of first submission shall be within one business day following a maintenance transaction after the

The contractor's CAV AF reporting shall reflect their inventory property control management system data records which shall represent timely and accurate accountability of AF inventory assets at the physical location(s) of the contractor's repair facility (including subcontractor facilities); shop floor, bond room and/or receiving/shipping docks, etc. for each

Page 5 of 20DD FORM 1423-1, FEB 2001 Version 2Generated by PRPS using Jasper Reports on 12 Sep 2018

B002

Contractor shall report by contract delivery order on all applicable categories, totals and on-hand balances, IAW DI- PSSS-81995, providing TABLE I for EACH repair location, including subcontractor facilities, for the contracts

Contractor shall report on production, providing TABLE I for EACH repair location, including…

This is the start of the file's text. The full file is on GovTribe.