QA_Pass_ _ID.docx
DOCX document 18 KB Posted
- Attached to
- Construct Pass & ID Facility Federal contract opportunity
- Solicitation number
- FA5702-13-R-0029
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| QA_Pass__ID_13-R-0029.docx | DOCX document | |
| 11-0143A-A-C-3-ADDENDUM2.pdf | ||
| FA5702-13-R-0029-1.pdf | ||
| Additional_Drawings.zip | ZIP file | |
| Additional_Specs.zip | ZIP file | |
| FA5702-13-R-0029.zip | ZIP file |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Q&A, Pass and ID Facility 11-0143A Note: Responses to Contractor pre-proposal questions provided by 379 ECES (27-Aug-2013)
1. SOW of all four RFP’s Paragraph 9.4.4 talks about establishing a free zone area around the construction site and having minimum number of escorts, on the other hand the RFP’s document states that escorts will be provided by the US Government. Please confirm which will be implemented.
Response: ECES will provide all escorts for the site/base entry.
2. Will the access to the base and the job sites be through the North gate? Or through another gate?
Response: All access will be through the North Gate.
3. Should a domestic water tank be included in the Pass and ID Facility building? The civil drawing indicates that there might be, but the plumbing line diagram does not. If a DWT is included, what is the capacity, and what construction?
Response: Yes, 3000 gal fiberglass water tank.
4. There is a 200 cont. CMU Bond Beam as per sheet D/A-5 Bldg. Section A-A Will this be the same detail you have provided at sheet $/SS-3 which is the bond beam reinforcing splice at corner Detail B?
Response: Yes
5. Below Hallow Metal doors for ID Pass but did not mentioned if fire rated and what is the hours required.
Response: There are no rated doors in this facility.