Schedule of Material Submittals
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| QUESTIONS_AND_ANSWERS_FOR_ATFP_PROJECTS.pdf | ||
| 18R00040001.pdf | ||
| Statement_of_Work,_English,_Revised_II.pdf | ||
| FA5575-18-R-0004,_ATFP_Perimeter_Ditch.pdf | ||
| Part_6,_Concept_and_Record_Drawings_Revised.pdf | ||
| Statement_of_Work,_Spanish,_Revised.pdf | ||
| Statement_of_Work,_English,_Revised.pdf | ||
| Attachment_A,_Integrated_Natural_Resources_Management_Plan_for_Morón_Air_Base.pdf | ||
| Statement_of_Work,_English.pdf | ||
| Statement_of_Work,_Spanish.pdf | ||
| Attachment_B,_Final_Governing_Standards_for_Spain,_May_2014.pdf | ||
| Part_6,_Concept_and_Record_Drawings.pdf | ||
| Construction_Cost_Estimate_Breakdown,_Contractor.xlsx | XLSX spreadsheet | |
| Attachment_A,_Integrated_Natural_Resources_Management_Plan_for_Morón_Air_Base.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Material Submittals Schedule
| SCHEDULE OF MATERIAL SUBMITTALS | PROJECT NUMBERS | ||
| QUUG 18-1007 | PROJECT TITLES |
ATFP SUS AIRFIELD PERIMETER DITCH
SOLICITATION / CONTRACT NO.
| (To be completed by Project Engineer) | (To be completed by Contract Administrator) | ||||||||||||||
| NUMBER OF COPIES REQUIRED | |||||||||||||||
| LINE NUMBER | ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL | CERTIFICATION OF COMPLIANCE | SHOP DRAWINGS | SAMPLES | COLOR SELECTION | MANUFACTURER'S RECOMMENDATION | MANUFACTURER'S WARRANTY | CATALOG DATA | OPERATING INSTRUCTIONS | SCHEDULES, LISTINGS, REPORTS, PLANS | TECHNICAL DATA | TEST REPORTS | FIELD REPORTS | REQUIRED SUBMISSION DATE |
fergusog: Enter the due date from the Contractor (MM/DD/YY)
DATE RECEIVED IN CONTRACTING
fergusog: Enter the date received from the Contractor. (MM/DD/YY)
DATE TO CIVIL ENGINEERING
fergusog: Enter the date submittal was given to CE for review. (MM/DD/YY)
RETURN SUSPENSE DATE
fergusog: Enter the date the submittal is due back from CE
(MM/DD/YY)
SUBMITTAL NUMBERS
fergusog: Enter the Submittal Number
DATE CONTRACTOR NOTIFIED CONTRACTOR RESUBMITTAL
fergusog: Enter Resubmittal Number
FINAL APPROVAL
fergusog: Enter the submittal final approval date
(MM/DD/YY)
REMARKS
fergusog: Enter any comments pertaining to the submittal
APPROVED
fergusog: Enter date the Contractor was notified of submittal approval
(MM/DD/YY)
fergusog: Enter Resubmittal Number
DISAPPROVED
fergusog: Enter date the Contractor was notified of submittal disapproval
(MM/DD/YY)
fergusog: Enter the submittal final approval date fergusog: Enter any comments pertaining to the submittal
SECTION 01 11 00
SCOPE OF WORK, DRAWINGS AND SPECIAL CONDITIONS
| 01 | Construction Schedule | 1 | CNTP+7 | |
| 02 | Work Plan | 1 | CNTP+7 | |
| 03 | Government furnished material request | 1 | Work-15 | |
| 04 | Inventory of the excess supplies, materials and equipment imported free duty | 1 | Prior to FI | |
| 05 | Classification certificate | 1 | DNTP+30 | |
| 06 | Quality certificate | 1 | DNTP+30 | |
| 07 | Environment certificate | 1 | DNTP+30 | |
| 08 | Asphalt batch plant certificate | 1 | DNTP+30 | |
| 09 | Quarry certificate | 1 | DNTP+30 | |
| 10 | Concrete batch plant certificate | 1 | DNTP+30 | |
| 11 | Laboratory certificate | 1 | DNTP+30 | |
| 12 | Request of training about vehicle operations on the aerodrome | 1 | DNTP+15 | |
| SECTION 01 11 01 |
GENERAL CONDITIONS
| 13 | Warranty letter | 1 | Acceptance+15 |
| 14 | Work Clearance Request | 1 | CNTP+5 |
| 15 | Base utility connection/disconeection request | 1 | CNTP+15 |
| 16 | Base utility outage request | 1 | Work-15 |
| 17 | Welding work request | 1 | Work-15 |
| 18 | Transit control plan | 1 | Work-10 |
| 19 | Access route plan | 1 | CNTP+10 |
| 20 | Progress Schedule | 1 | CNTP+10 |
| 21 | Mobility Plan | 1 | CNTP+15 |
| 22 | Project Sign | 1 | CNTP+15 |
| 23 | Quality Control Plan | 1 | CNTP+15 |
| 24 | Pre-final inspection request | 1 | Date-15 |
| 25 | Final inspection request | 1 | Date-15 |
| 26 | Environmental protection plan | 1 | CNTP+15 |
| 27 | Waste & construction debris management certificate | 1 | Acceptance+15 |
| 28 | As-Built drawings | 1 | Acceptance+15 |
| 29 | Spatial Data | 1 | As-Built+10 |
| 30 | Key Personnel | 1 | DNTP+15 |
| 31 | Personnel Listing | 1 | DNTP+15 |
| 32 | Health and safety program | 1 | CNTP+15 |
| SECTION 01 32 16.00 20 | |||
| 33 | Design-Build Schedule | 1 | DNTP+10 |
| 34 | Monthly Updates | 1 | Every 1st of month |
| Contractor shall complete list of submittals when developping final constructiohn specifications, including those outlined in the Performance Technical Specifications provided with the SOW |
&"Arial,Bold"&8Schedule of Material Submittals, Feb 05 (SAF/AQCP) Page &P of &N
MSS Spanish
| RESUMEN MUESTRAS DE MATERIAL | NÚMEROS PROYECTO: | |||
| QUUG 18-1007 | TÍTULOS DE PROYECTO: | |||
| ATFP MANTENER CUNETA PERIMETRAL DEL AERÓDROMO | SOLICITACIÓN / CONTRATO NO. |
| (A cumplimentar por el ingeniero del proyecto) | (A cumplimentar por administrador del contrato) | ||||||||||||||
| NUMBER OF COPIES REQUIRED | |||||||||||||||
| LÍNEA NÚMERO | PARTIDA O DESCRIPCIÓN DE PARTIDA, REFERENCIA DEL CONTRATO, TIPO DE PRESENTACIÓN | CERTIFICADO DE CUMPLIMIENTO | PLANOS DE TALLER | MUESTRAS | SELECCIÓN DE COLOR | RECOMENDACIONES DEL FABRICANTE | GARANTÍA DEL FABRICANTE | DATOS DE CATÁLOGO | INSTRUCCIONES DE FUNCIONAMIENTO | PROGRAMAS, LISTADOS, INFORMES, PLANES | DATOS TÉCNICOS | PRUEBAS | INFORMES DE TRABAJOS DE CAMPO | FECHA DE ENTREGA REQUERIDA |
fergusog: Enter the due date from the Contractor (MM/DD/YY)
FECHA RECEPCIÓN EN CONTRATACIÓN
fergusog: Enter the date received from the Contractor. (MM/DD/YY) FECHA EN INGENIERíA CIVIL fergusog: Enter the date submittal was given to CE for review. (MM/DD/YY)
FECHA LÍMITE DE DEVOLUCIÓN
fergusog: Enter the date the submittal is due back from CE
(MM/DD/YY)
NÚMERO DE MUESTRA
fergusog: Enter the Submittal Number
FECHA NOTIFICACIÓN A CONTRATISTA SEGUNDA PRESENTACIÓN DEL CONTRATISTA
fergusog: Enter Resubmittal Number
APROBACIÓN FINAL
fergusog: Enter the submittal final approval date
(MM/DD/YY)
OBSERVACIONES
fergusog: Enter any comments pertaining to the submittal
APROBADO
fergusog: Enter date the Contractor was notified of submittal approval
(MM/DD/YY)
fergusog: Enter Resubmittal Number
DESAPROBADO
fergusog: Enter date the Contractor was notified of submittal disapproval fergusog: Enter the submittal final approval date fergusog: Enter any comments pertaining to the submittal
SECCIÓN 01 11 00
OBJETO DEL TRABAJO, PLANOS Y CONDICIONES ESPECIALES
| 01 | Programa de obra | 1 | CNTP+7 | |
| 02 | Plan de obra | 1 | CNTP+7 | |
| 03 | Solicitud de material suministrado por el Gobierno | 1 | Trabajo-15 | |
| 04 | Inventario del excedente de suministros, materiales y equipos importados libre de impuestos | 1 | Antes de IF | |
| 05 | Certificado de clasificación | 1 | DNTP+30 | |
| 06 | Certificado de calidad | 1 | DNTP+30 | |
| 07 | Certificado de medioambiente | 1 | DNTP+30 | |
| 08 | Certificado de la planta de asfalto | 1 | DNTP+30 | |
| 09 | Certificado de la cantera | 1 | DNTP+30 | |
| 10 | Certificado de la planta de hormigón | 1 | DNTP+30 | |
| 11 | Laboratorio | 1 | DNTP+30 | |
| 12 | Solicitud de entrenamiento de operaciones de vehículos en el aeródromo | 1 | DNTP+15 | |
| SECCIÓN 01 11 01 |
CONDICIONES GENERALES
| 13 | Carta de garantía | 1 | Recepción+15 |
| 14 | Permiso de excavación | 1 | CNTP+5 |
| 15 | Petición de conexión a servicios de la base | 1 | CNTP+15 |
| 16 | Solicitud de cortes de servicios de la base | 1 | Trabajo-15 |
| 17 | Solicitud de trabajo de soldadura | 1 | Trabajo-15 |
| 18 | Plan de control de tránsito | 1 | Trabajo-10 |
| 19 | Plan de rutas de acceso | 1 | CNTP+10 |
| 20 | Programa de avance de obras | 1 | CNTP+10 |
| 21 | Plan de movilización | 1 | CNTP+15 |
| 22 | Cartel de proyecto | 1 | CNTP+15 |
| 23 | Plan de control de calidad | 1 | CNTP+15 |
| 24 | Solicitud de inspección pre-final | 1 | Fecha-15 |
| 25 | Solicitud de inspección final | 1 | Fecha-15 |
| 26 | Plan de protección medioambiental | 1 | CNTP+15 |
| 27 | Certificado de gestión de residuos y escombros | 1 | Recepción+15 |
| 28 | Planos As-Builts | 1 | Recepción+15 |
| 29 | Datos espaciales | 1 | As-Built+10 |
| 30 | Personal clave | 1 | DNTP+15 |
| 31 | Listado de personal | 1 | DNTP+15 |
| 32 | Plan de salud y seguridad | 1 | CNTP+15 |
| SECCIÓN 01 32 16.00 20 | |||
| 32 | Cronograma de Diseñoy Construcción | 1 | DNTP+10 |
| 33 | Actualizaciones mensuales | 1 | Cada día 1 de mes |
| El Contratista completará el listado de presentaciones cuando desarrolle las especificaciones finales de construcción, incluyendo aquellas presentaciones apuntadas en el Pliego de Condiciones Técnicas suministradas con este OdT. |
&"Arial,Bold"&8Resumen de muestras de material, Feb 05 (SAF/AQCP) Página &P de &N