Solicitation_FA5270-15-T-0104.pdf
PDF 710 KB Posted
- Attached to
- Renovate 164 Arnold Terrace Federal contract opportunity
- Solicitation number
- FA5270-15-T-0104
About this file
- Solicitation for FA5270-15-T-0104
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| RFIs.pdf | ||
| SOW_LXEZ144310.pdf | ||
| Amendment_1(0002).pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Repair GOH 164 Arnold Terrace, Kadena Air Base
1. The magnitude of this project is betw een $25,000 and $100,000
2. CONTRACTOR LICENSING REQUIREMENTS: Any contract resulting from this solicitation w ill be aw arded and performed in its entirely in the country of Japan. Contractors must be duty authorized to operate and conduct business in Japan and must fully comply w ith all applicable law s, decrees, labor standards, and regulations of Japan during the performance of the contract. Prior to aw ard, offerors must be registered to do business in Japan and possess a construction license (Kensetsu-Gyo Kyoka) issued by the Ministry of Land, infrastructure and
Transport, or prefectural government.
3. While funds are NOT presently available to fund this project, w e anticipate funds w ill become available. If current Fiscal Year (FY 2015) funds become available, contract w ill be made no later than 30 September 2015. Accordingly, offers shall be valid until 30 Sep 15. If FY 15 funds are not available, no aw ard w ill be made. The Government reserves the right to cancel this request before aw ard but after closing date w hen cancellation is clearly in the Government's best interest.
4. Offerors proposed price shall be reflected in Yen.
REHMAN, QADEER M 634-4741
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
15-Jul-2015
(RFP)
(IFB)
CALL:
Renovate 164 Arnold Terrace
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______5 calendar days and complete it w ithin ________184 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________CONST-F-7160
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
YES X NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________05 Aug 2015 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______ calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
18 CONS/INFRASTRUCTURE ACQUISITION
POC: QADEER REHMAN
UNIT 5199, BLDG 95 KADENA AB
APO AP 96368
FA5270
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
02:00 PM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
LXEZ 14-4310
8. ADDRESS OFFER TO (If Other Than Item 7)
FAX:TEL: 634-4741 TEL: FAX:
FA5270-15-T-0104 55
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued)
(Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Renovate 164 Terrace
FFP
Project LXEZ 14-4310; Remove existing single pane wood frame doors and windows. Replace with high efficiency, argon, filled, double pane windows with a low-e coating in a thermally broken aluminum frame. Frames shall have a bronze finish to match existing window units throughout the residence. The wooden floor will be repaired as impacted by the window replacement. In addition, the current lock system for patio door will be replaced.
PSC:Z2FA
FOB: Destination
SIGNAL CODE: A
NET AMT
Section E - Inspection and Acceptance
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 Destination Government Destination Government
CLAUSES INCORPORATED BY REFERENCE
52.246-12 Inspection of Construction AUG 1996
Section F - Deliveries or Performance
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS UIC
0001 184 dys. ADC 18 CONS/LGCC
QADEER REHMAN
UNIT 5199
5, KAB
APO AP 96368-5199
634-4741
FOB: Destination
FULGCC
52.211-10 Commencement, Prosecution, and Completion of Work APR 1984
CLAUSES INCORPORATED BY FULL TEXT
CONST-F-7160 ISSUANCE OF NOTICE TO PROCEED
The United States Government will issue Notice to Proceed within 40 calendar days after contract award.
(End of clause)
Section G - Contract Administration Data
CONST-G-7180 POST AWARD ADMINISTRATIVE INFORMATION
The contracting officer will provide to the contractor, a listing of the names of the Administrative Contracting
Officer, Contract Administrator, and Construction Inspector (also referred to as the Contracting Officer’s
Representative (COR) or Technical Representative of the Contracting Officer (TRCO), their organizational codes and telephone numbers at the time of award or at the pre-construction conference. This provision in no way authorizes any person other than the contracting officer to commit the United States Government to changes in the terms or conditions of this contract. Reference Section I, DFARS 252.201-7000 entitled Contracting Officer’s
Representative (DEC 1991).
PAYING OFFICE: Accounting and Finance
DFAS-BVNF/JA
Yokota Air Force Base
Fussa-shi
Tokyo, Japan 197-0001
GEN-G-0001
SUBMIT INVOICES ELECTRONICALLY
Wide Area Work Flow Clause
This contract contains DFARS Clause 252.232-7003, Electronic Submission of Payment Requests. This clause requires invoices for supplies and services purchased by the DoD be submitted via electronic means. The Wide Area
Workflow (WAWF) system satisfies this mandatory requirement. WAWF can be accessed on the internet at https://wawf.eb.mil/.
Before using WAWF, ensure your company’s Electronic Business POCs listed in your System for Award
Management (SAM) are the same individuals that will invoice through WAWF. If they aren't, changes can be made to your company’s SAM profile at https://www.sam.gov/portal/public/SAM/. Click on "Update” or “Renew” using
“TPIN". SAM customer support can be reached at 1-866-606-8220.
If your company’s electronic businesses POCs are correct, contact the WAWF helpdesk at 1-866-618-5988 or by e-mail at cscassig@ogden.disa.mil and ask to establish a group for your company’s CAGE code. The group administrator will also have to call the WAWF helpdesk to request account activation. Once the group is established and the account is activated, your company will be able to create a combination invoice/receiving report using the codes below and instructions available from our contract administrator/buyer.
Questions concerning payment should be directed to the Defense Finance Accounting Services (DFAS) Air Force
Pacific at 011-81-3117-55-3068. Please have the order number and invoice number ready when calling about payment status. The accounts payable mailing address can be located in Block 18a of the order. Payment information can be easily accessed using the DFAS web site at http://www.dfas.mil. The purchase order/contract number or invoice will be required to inquire status of payment. Go to DFAS on the web at:
www/dfas.mil/money/vendor.
The contractor shall create one of the following:
[ ] “2-n-1 format” for services only
[ ] “Receiving report combo” for supplies or combination of supplies & services
[ ] “Invoice ” for medical supplies
[X] “Construction Invoice” for construction
THE FOLLOWING CODES WILL BE REQUIRED TO ROUTE YOUR INVOICES THROUGH WAWF
ISSUE BY DODAAC: [FA5270]
ADMIN DODAAC: [FA5270]
INSPECT BY DODAAC: [F2H2B9]
SERVICE ACCEPTOR: [F2H2B9]
“SHIP TO” DODAAC: [F2H2B9]
PAY OFFICE DODAAC: [F68800]
Please send additional emails to all listed:
EMAIL POINT OF CONTACT LISTING: 18 CONS.WAWF@US.AF.MIL
SERVICE ACCEPTOR/INSPECTOR: gary.wynder@us.af.mil
CONTRACT ADMINISTRATOR: qadeer.rehman.1@us.af.mil
Section H - Special Contract Requirements
GEN-H-7951 TAX EXEMPTION CERTIFICATE (AUG 2001)
The Contractor will submit requests for gasoline or diesel oil tax exemption certificates to the Contracting Officer.
This request will show the actual amount of gasoline or diesel oil used exclusively for the performance of this contract, with documentary evidence and detailed item breakdown to certify the accurate consumption of gasoline or diesel oil, or other necessary information and data as may be required. The Contracting Officer will issue to the
Contractor a Tax Exemption Certificate for the actual amount of gasoline or diesel oil used exclusively for the performance of this contract. The Contractor shall claim all tax and customs exemptions as listed in clause CONST-
K-7250, entitled, “EXEMPTION FROM JAPANESE CUSTOMS DUTIES AND TAXES PURSUANT TO
STATUS OF FORCES AGREEMENT”.
CONST-H-7200 U.S. DOLLAR VERSUS YEN EQUIVALENT
For the duration of this solicitation the contractor shall use the following exchange rate in determining the Yen equivalent to referenced US dollar amounts in this solicitation provisions/contract clauses $1.00 = ¥120.12 evaluation of the award. All referenced US dollar amounts in this solicitation provisions/contract clauses are modified to include "or Yen equivalent". Yen rate will be established per delivery order or task order.
CONST-H-7201 REQUIRED INSURANCE (In addition to that required by Japanese Law)
a. The contractor shall procure and maintain during the entire period of his performance under this contract the following minimum insurance on each vehicle used by the contractor at the work site.
Type: Automobile Property Damage and Bodily Injuries
Amount: JPY3,000,000 for automobile property damage
JPY30,000,000 for bodily injuries
b. Prior to the commencement of work hereunder, the contractor shall furnish to the contracting officer a certificate or written statement of the above required insurance. The policies evidencing required insurance shall contain an endorsement to the effect that cancellation or any material change in the policies adversely affecting the interests of the US Government in such insurance shall not be effective for such period as may be prescribed by the laws of the country of Japan in which this contract is to be performed and in no event less than thirty (30) days after written notice thereof to the contracting officer.
c. The contractor agrees to insert the substance of this clause, including this paragraph (c) in all subcontracts hereunder.
CONST-H-7207 BASE DEFENSE ACT/WORKMAN'S COMPENSATION/WORK ON AN
OVERSEAS INSTALLATION ( JUN 2004 )
This contract includes FAR 52.228-3, Workers’ Compensation Insurance (Defense Base Act) (Apr 1984), and FAR
52.228-4, Worker’s Compensation and War-Hazard Insurance Overseas (Apr 1984). FAR 52.228-3 applies only if the contractor has United States’ citizen or national employees, regardless of whether they have SOFA status or a status of residence in Japan. FAR 52.228-4 applies if the contractor has non-United States’ citizen or national employees. One or both clauses may apply to the contractor.
GEN-H-7952 JAPANESE ROAD LAWS (AUG 2001)
The Contractor shall comply with Japanese Road Laws while on U.S. military installations to specifically include:
Article 43, The Road Law (Japan) (prohibitive acts relative to roads). No person shall commit the following described acts:
Damaging the road, causing roads to be littered with debris, polluting the roads with debris or fall out from motor vehicles or otherwise defacing roads unreasonably or without due cause.
Article 43-2 (Measures to be taken to prevent cargo or things loaded on motor vehicles from falling out)
The agency managing a road may, when there is reasonable cause for him to feel that items or cargo being carried in or on a motor vehicle may fall out and damage, pollute, or otherwise deface the road in such manner as to hinder or obstruct the traffic, order the operator of the vehicle in question to take steps or measures necessary to prevent occurrence of such hindrance by stopping operation of the vehicle, correcting the method of loading or traveling, or operation of the vehicle.
GEN-H-7953 REGISTRATION OF MOTOR VEHICLES (AUG 2001)
All company-owned and privately-owned motor vehicles required to be on U.S. Government facilities during the performance of this contract must be registered with Vehicle Registration, Camp Foster. Necessary decals and/or permits will be issued and displayed on the vehicles in the manner as directed by the Vehicle Registration Officer.
Vehicle decals shall be removed from vehicles and turned in to Vehicles Registration, Camp Foster, at the end of the contract period or sooner when vehicles are no longer used in the performance of the contract or as directed by the
Contracting Officer.
Section I - Contract Clauses
52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011
52.204-13 System for Award Management Maintenance JUL 2013
52.213-4 Terms and Conditions--Simplified Acquisitions (Other Than
Commercial Items)
MAY 2015
52.222-50 Combating Trafficking in Persons MAR 2015
52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts
SEP 2013
52.223-17 Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts
MAY 2008
52.223-18 Encouraging Contractor Policies To Ban Text Messaging
While Driving
AUG 2011
52.225-14 Inconsistency Between English Version And Translation Of
Contract
FEB 2000
52.228-3 Worker's Compensation Insurance (Defense Base Act) JUL 2014
52.232-18 Availability Of Funds APR 1984
52.232-27 Prompt Payment for Construction Contracts MAY 2014
52.232-33 Payment by Electronic Funds Transfer--System for Award
Management
JUL 2013
52.232-39 Unenforceability of Unauthorized Obligations JUN 2013
52.233-1 Disputes MAY 2014
52.233-3 Protest After Award AUG 1996
52.233-4 Applicable Law for Breach of Contract Claim OCT 2004
52.236-2 Differing Site Conditions APR 1984
52.236-3 Site Investigation and Conditions Affecting the Work APR 1984
52.236-5 Material and Workmanship APR 1984
52.236-7 Permits and Responsibilities NOV 1991
52.236-10 Operations and Storage Areas APR 1984
52.236-11 Use and Possession Prior to Completion APR 1984
52.236-12 Cleaning Up APR 1984
52.236-13 Accident Prevention NOV 1991
52.236-17 Layout of Work APR 1984
52.236-21 Specifications and Drawings for Construction FEB 1997
52.236-26 Preconstruction Conference FEB 1995
52.237-2 Protection Of Government Buildings, Equipment, And
Vegetation
APR 1984
52.242-14 Suspension of Work APR 1984
52.242-17 Government Delay Of Work APR 1984
52.246-21 Warranty of Construction MAR 1994
52.249-1 Termination For Convenience Of The Government (Fixed
Price) (Short Form)
APR 1984
52.249-10 Default (Fixed-Price Construction) APR 1984
52.253-1 Computer Generated Forms JAN 1991
252.201-7000 Contracting Officer's Representative DEC 1991
252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013
252.222-7002 Compliance With Local Labor Laws (Overseas) JUN 1997
52.219-4 NOTICE OF PRICE EVALUATION PREFERENCE FOR HUBZONE SMALL BUSINESS
CONCERNS (OCT 2014)
(a) Definitions. See 13 CFR 125.6(e) for definitions of terms used in paragraph (d).
(b) Evaluation preference. (1) Offers will be evaluated by adding a factor of 10 percent to the price of all offers, except--
(i) Offers from HUBZone small business concerns that have not waived the evaluation preference; and
(ii) Otherwise successful offers from small business concerns.
(2) The factor of 10 percent shall be applied on a line item basis or to any group of items on which award may be made. Other evaluation factors described in the solicitation shall be applied before application of the factor.
(3) When the two highest rated offerors are a HUBZone small business concern and a large business, and the evaluated offer of the HUBZone small business concern is equal to the evaluated offer of the large business after considering the price evaluation preference, award will be made to the HUBZone small business concern.
(c) Waiver of evaluation preference. A HUBZone small business concern may elect to waive the evaluation preference, in which case the factor will be added to its offer for evaluation purposes. The agreements in paragraphs
(d) and (e) of this clause do not apply if the offeror has waived the evaluation preference.
___ Offeror elects to waive the evaluation preference.
(d) Agreement. A HUBZone small business concern agrees that in the performance of the contract, in the case of a contract for
(1) Services (except construction), at least 50 percent of the cost of personnel for contract performance will be spent for employees of the concern or employees of other HUBZone small business concerns;
(2) Supplies (other than procurement from a nonmanufacturer of such supplies), at least 50 percent of the cost of manufacturing, excluding the cost of materials, will be performed by the concern or other HUBZone small business concerns;
(3) General construction. (i) At least 15 percent of the cost of contract performance to be incurred for personnel will be spent on the prime contractor's employees;
(ii) At least 50 percent of the cost of the contract performance to be incurred for personnel will be spent on the prime contractor's employees or on a combination of the prime contractor's employees and employees of HUBZone small business concern subcontractors;
(iii) No more than 50 percent of the cost of contract performance to be incurred for personnel will be subcontracted to concerns that are not HUBZone small business concerns; or
(4) Construction by special trade contractors. (i) At least 25 percent of the cost of contract performance to be incurred for personnel will be spent on the prime contractor's employees;
(ii) At least 50 percent of the cost of the contract performance to be incurred for personnel will be spent on the prime contractor's employees or on a combination of the prime contractor's employees and employees of HUBZone small business concern subcontractors;
(iii) No more than 50 percent of the cost of contract performance to be incurred for personnel will be subcontracted to concerns that are not HUBZone small business concerns.
(e) A HUBZone joint venture agrees that the aggregate of the HUBZone small business concerns to the joint venture, not each concern separately, will perform the applicable percentage of work requirements.
(f)(1) When the total value of the contract exceeds $25,000, a HUBZone small business concern nonmanufacturer agrees to furnish in performing this contract only end items manufactured or produced by HUBZone small business concern manufacturers.
(2) When the total value of the contract is equal to or less than $25,000, a HUBZone small business concern nonmanufacturer may provide end items manufactured by other than a HUBZone small business concern manufacturer provided the end items are produced or manufactured in the United States.
(3) Paragraphs (f)(1) and (f)(2) of this section do not apply in connection with construction or service contracts.
(g) Notice. The HUBZone small business offeror acknowledges that a prospective HUBZone awardee must be a
HUBZone small business concern at the time of award of this contract. The HUBZone offeror shall provide the
Contracting Officer a copy of the notice required by 13 CFR 126.501 if material changes occur before contract award that could affect its HUBZone eligibility. If the apparently successful HUBZone offeror is not a HUBZone small business concern at the time of award of this contract, the Contracting Officer will proceed to award to the next otherwise successful HUBZone small business concern or other offeror.
52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
http://farsite.hill.af.mil/
52.252-6 AUTHORIZED DEVIATIONS IN CLAUSES (APR 1984)
(a) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 1) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the clause.
(b) The use in this solicitation or contract of any Defense Federal Acquisition Regulation Supplement (48 CFR
Chapter 2) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
252.225-7043 ANTITERRORISM/FORCE PROTECTION POLICY FOR DEFENSE CONTRACTORS
OUTSIDE THE UNITED STATES (MAR 2006)
(a) Definition. United States, as used in this clause, means, the 50 States, the District of Columbia, and outlying areas.
(b) Except as provided in paragraph (c) of this clause, the Contractor and its subcontractors, if performing or traveling outside the United States under this contract, shall--
(1) Affiliate with the Overseas Security Advisory Council, if the Contractor or subcontractor is a U.S. entity;
(2) Ensure that Contractor and subcontractor personnel who are U.S. nationals and are in-country on a non-transitory basis, register with the U.S. Embassy, and that Contractor and subcontractor personnel who are third country nationals comply with any security related requirements of the Embassy of their nationality;
(3) Provide, to Contractor and subcontractor personnel, antiterrorism/force protection awareness information commensurate with that which the Department of Defense (DoD) provides to its military and civilian personnel and their families, to the extent such information can be made available prior to travel outside the United States; and
(4) Obtain and comply with the most current antiterrorism/force protection guidance for Contractor and subcontractor personnel.
(c) The requirements of this clause do not apply to any subcontractor that is--
(1) A foreign government;
(2) A representative of a foreign government; or
(3) A foreign corporation wholly owned by a foreign government.
(d) Information and guidance pertaining to DoD antiterrorism/force protection can be obtained from [Contracting
Officer to insert applicable information cited in PGI 225.7403-1].
252.229-7001 TAX RELIEF (SEPT 2014)
(a) Prices set forth in this contract are exclusive of all taxes and duties from which the United States Government is exempt by virtue of tax agreements between the United States Government and the Contractor's government. The following taxes or duties have been excluded from the contract price:
NAME OF TAX: (Offeror Insert) RATE (PERCENTAGE): (Offeror Insert)
(b) The Contractor's invoice shall list separately the gross price, amount of tax deducted, and net price charged.
(c) When items manufactured to United States Government specifications are being acquired, the Contractor shall identify the materials or components intended to be imported in order to ensure that relief from import duties is obtained. If the Contractor intends to use imported products from inventories on hand, the price of which includes a factor for import duties, the Contractor shall ensure the United States Government's exemption from these taxes. The
Contractor may obtain a refund of the import duties from its government or request the duty-free import of an amount of supplies or components corresponding to that used from inventory for this contract.
252.232-7003 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS AND RECEIVING REPORTS
(JUNE 2012)
(a) Definitions. As used in this clause–
(1) Contract financing payment and invoice payment have the meanings given in section 32.001 of the Federal
Acquisition Regulation.
(2) Electronic form means any automated system that transmits information electronically from the initiating system to all affected systems. Facsimile, e-mail, and scanned documents are not acceptable electronic forms for submission of payment requests. However, scanned documents are acceptable when they are part of a submission of a payment request made using Wide Area WorkFlow (WAWF) or another electronic form authorized by the Contracting
Officer.
(3) Payment request means any request for contract financing payment or invoice payment submitted by the
Contractor under this contract.
(4) Receiving report means the data required by the clause at 252.246-7000, Material Inspection and Receiving
Report.
(b) Except as provided in paragraph (c) of this clause, the Contractor shall submit payment requests and receiving reports using WAWF, in one of the following electronic formats that WAWF accepts: Electronic Data Interchange, Secure File Transfer Protocol, or World Wide Web input. Information regarding WAWF is available on the Internet at https://wawf.eb.mil/.
(c) The Contractor may submit a payment request and receiving report using other than WAWF only when–
(1) The Contracting Officer administering the contract for payment has determined, in writing, that electronic submission would be unduly burdensome to the Contractor. In such cases, the Contractor shall include a copy of the
Contracting Officer's determination with each request for payment;
(2) DoD makes payment for commercial transportation services provided under a Government rate tender or a contract for transportation services using a DoD-approved electronic third party payment system or other exempted vendor payment/invoicing system (e.g., PowerTrack, Transportation Financial Management System, and Cargo and
Billing System);
(3) DoD makes payment for rendered health care services using the TRICARE Encounter Data System (TEDS) as the electronic format; or
(4) When the Governmentwide commercial purchase card is used as the method of payment, only submission of the receiving report in electronic form is required.
(d) The Contractor shall submit any non-electronic payment requests using the method or methods specified in
Section G of the contract.
(e) In addition to the requirements of this clause, the Contractor shall meet the requirements of the appropriate payment clauses in this contract when submitting payments requests.
252.236-7001 CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000)
(a) The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.
(b) The Contractor shall--
(1) Check all drawings furnished immediately upon receipt;
(2) Compare all drawings and verify the figures before laying out the work;
(3) Promptly notify the Contracting Officer of any discrepancies;
(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and
(5) Reproduce and print contract drawings and specifications as needed.
(c) In general--
(1) Large-scale drawings shall govern small-scale drawings; and
(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.
(d) Omissions from the drawings or specifications or the misdescription of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.
(e) The work shall conform to the specifications and the contract drawings identified on the following index of drawings:
CD-Rs with Drawings will be available upon request
5352.201-9101 Ombudsman
As prescribed in 5301.9103, insert the following clause:
OMBUDSMAN (NOV 2012)
(a) An ombudsman has been appointed to hear and facilitate the resolution of concerns from offerors, potential offerors, and others for this acquisition. When requested, the ombudsman will maintain strict confidentiality as to the source of the concern.
The existence of the ombudsman does not affect the authority of the program manager, contracting officer, or source selection official. Further, the ombudsman does not participate in the evaluation of proposals, the source selection process, or the adjudication of protests or formal contract disputes. The ombudsman may refer the interested party to another official who can resolve the concern.
(b) Before consulting with an ombudsman, interested parties must first address their concerns, issues, disagreements, and/or recommendations to the contracting officer for resolution. Consulting an ombudsman does not alter or postpone the timelines for http://farsite.hill.af.mil/reghtml/regs/far2afmcfars/af_afmc/affars/5301.htm#p53019103 any other processes (e.g., agency level bid protests, GAO bid protests, requests for debriefings, employee-employer actions, contests of OMB Circular A-76 competition performance decisions).
(c) If resolution cannot be made by the contracting officer, the interested party may contact the Center/MAJCOM/DRU or
AFISRA ombudsmen, Name: James B. Ting, CMSgt, USAF
Address: AFICA/KH, 25E Street, Suite D-360, Hickam AFB HI 96853-5427
Phone No: 808-449-8569
Facsimile No: 808-449-8571
Email: james.ting@us.af.mil
Concerns, issues, disagreements, and recommendations that cannot be resolved at the Center/MAJCOM/DRU or AFISRA level, may be brought by the interested party for further consideration to the Air Force ombudsman, Associate Deputy Assistant
Secretary (ADAS) (Contracting), SAF/AQC, 1060 Air Force Pentagon, Washington DC 20330-1060, phone number (571) 256-
2397, facsimile number (571) 256-2431.
(d) The ombudsman has no authority to render a decision that binds the agency.
(e) Do not contact the ombudsman to request copies of the solicitation, verify offer due date, or clarify technical requirements.
Such inquiries shall be directed to the Contracting Officer.
5352.242-9000 Contractor access to Air Force installations.
As prescribed in 5342.490-1, insert a clause substantially the same as the following clause in solicitations and contracts:
CONTRACTOR ACCESS TO AIR FORCE INSTALLATIONS (AUGUST 2007)
(a) The contractor shall obtain base identification and vehicle passes, if required, for all contractor personnel who make frequent visits to or perform work on the Air Force installation(s) cited in the contract. Contractor personnel are required to wear or prominently display installation identification badges or contractor-furnished, contractor identification badges while visiting or performing work on the installation.
(b) The contractor shall submit a written request on company letterhead to the contracting officer listing the following: contract number, location of work site, start and stop dates, and names of employees and subcontractor employees needing access to the base. The letter will also specify the individual(s) authorized to sign for a request for base identification credentials or vehicle passes. The contracting officer will endorse the request and forward it to the issuing base pass and registration office or security police for processing. When reporting to the registration office, the authorized contractor individual(s) should provide a valid driver’s license, current vehicle registration, valid vehicle insurance certificate to obtain a vehicle pass.
(c) During performance of the contract, the contractor shall be responsible for obtaining required identification for newly assigned personnel and for prompt return of credentials and vehicle passes for any employee who no longer requires access to the work site.
(d) When work under this contract requires unescorted entry to controlled or restricted areas, the contractor shall comply with [AFI 31-101, Volume 1, The Air Force Installation Security Program, and AFI 31-501, Personnel
Security Program Management,] citing the appropriate paragraphs as applicable.
http://www.whitehouse.gov/omb/circulars/a076/a76_rev2003.pdf mailto:james.ting@us.af.mil http://farsite.hill.af.mil/reghtml/regs/far2afmcfars/af_afmc/affars/5342.htm#P35_364 http://www.e-publishing.af.mil/search.asp?keyword=AFI+31-101&Go.x=8&Go.y=10 http://www.e-publishing.af.mil/pubfiles/af/31/afi31-501/afi31-501.pdf
(e) Upon completion or termination of the contract or expiration of the identification passes, the prime contractor shall ensure that all base identification passes issued to employees and subcontractor employees are returned to the issuing office.
(f) Failure to comply with these requirements may result in withholding of final payment.
Section J - List of Documents, Exhibits and Other Attachments
HEPA VACCUM CLEANER
SOW
STATEMENT OF WORK
Project No: LXEZ 144310
Project Title: Renovate 164 Arnold Terrace
Location: Kadena Air Base, Okinawa, Japan
CE Project Manager: 2d Lt. Jonathon McKnight
Telephone: 632-7075
1.0 General Scope:
The Contractor shall furnish all tools, equipment, materials, testing, labor and personnel necessary to plan, manage, supervise and construct the project to replace windows, frames, doors and thresholds. The
Contractor shall determine the best technical design solution in conformance with current codes and regulations, not specifically stated elsewhere in this project statement of work to provide a complete and useable facility upon completion. The scope of work is further defined in the Description of Work section.
2.0 Project Schedule and Time Constraints:
2.1 Completion of Work: The Contractor shall be required to complete the entire work, ready for use, not later than 184 calendar days after the date of Notice to Proceed (NTP). Proposed schedule shall include time to develop shop drawings, government review, material submittals, procurement and construction. The Contractor shall submit a Project Schedule at the pre-design conference and shall resubmit updates as necessary until project completion.
2.2 Construction Schedule: The Contractor shall determine the most efficient work plan to minimize inconvenience to the user.
2.3 Start Work Notification: Before starting on-site work the Contractor shall notify the Contracting Officer and the Project Manager in writing, thirty (30) calendar days prior to on-site work starting. After approval of on-site work, the Contractor shall provide written notice to all Military Family Housing Occupants affected by the Task
Order within a minimum of Fourteen (14) calendar days before starting on-site work.
2.4 Construction Access: The Contractor shall be allowed to work from 0800 to 1630, Monday through Friday, excluding U.S. Federal holidays, and other days specifically designated by the Contracting Officer.
2.4 Performance Time: The Contractor shall begin performance within five (5) calendar days after receiving the Noticed to Proceed (NTP) for construction.
Schedule Shall Be Completed Within
a) Design Submittal 21 calendar days
b) Design Review 14 calendar days
c) Corrected Design 10 calendar days
d) Shop Drawings/ Material Submittals: 30 calendar days
e) Government Material Review: 14 calendar days
f) Procurement of Materials: market research 60 calendar days
g) Construction Time: 30 calendar days
h) Unfavorable Weather 5 calendar days
Construction Subtotal 184 calendar days
3.0 Construction Requirements:
The design and shop drawings shall conform to Unified Facility Criteria (UFC), criteria as Risk Category
IV for seismic and wind speed, National Fire Protection Association (NFPA), National Electric Code
(NEC), Japan Environmental Governing Standards (JEGS), Japanese Industrial Standards (JIS) and all other applicable criteria. The specifications shall be prepared using the Unified Facilities Guide
Specifications (UFGS). In accordance with Corps of Engineers Guide Specifications (CEGS), drawings for doors shall be shown as such:
NOTE: On the drawings, show:
1. Size of door openings; thickness, swing and travel of doors; whether flush, paneled, glazed, or louvered; width of stiles and rails
2. Elevations of each door and frame type, at 1:50 1/4 inch scale
3. Details of head, jamb, sill, mullions, and transom sections; key sections to door frame elevations; type and spacing of anchors
4. Type and thickness of glazing required and method of glazing
SECTION 08 11 16 Page 3
5. Details of weather stripping for exterior doors
6. Amount of free area for louvers
7. A separate number for each door opening on door schedule
3.1 As-built drawings will be provided to the Contractor for reference in their present form. The Government bears no responsibility for the accuracy of these drawings. Actual field investigation and survey of the facility must be conducted by the Contractor to ascertain existing conditions before start of design.
3.2 Submit all shop drawings and catalog cuts of materials and equipment to be used for approval, (ref. submittal log.
Note: The 100% submittal is provided after construction completion as Construction As Built
Drawings. Submit one set (hard copy and CD) submittals to 18 CONS/LGCC and the remainder to 718 CES/CENMA directly at each design stage.
Submittal shall be Windows compatible CD-ROM with drawings in US version of AutoCAD and
PDF, the complete specifications in Microsoft Word, and AF Form 66 in Microsoft Excel.
3.3 As-Built Documents: The Contractor shall provide as built drawings in white paper and 2 copies of CD containing all drawings in electronic CADD and PDF and all documents in WORD or EXCEL and PDF. Prior to
Final inspection, the Contractor shall provide all the approved material catalog cuts and maintenance manuals in binders to Operations/ Housing Maintenance Office.
3.4 Construction Project Signs: The Contractor shall provide and maintain construction sign on the project site.
Sign shall be installed by the contract start date and shall be removed by the contract completion date. Location of project signs will be coordinated with the Project Manager. Request for company sign will be submitted to
Contractor Officer and the Project Manager in writing for approval.
3.5 Storage of Material, Latrines and Field Office: Storage of materials and field office shall be authorized after approval by the Contracting Officer. The contractor shall propose the location 30 days prior to construction start to
718CES/CENMA for approval.
Availability of Latrine: Latrine is not available in the work area. The Contractor shall be responsible for providing latrines for his personnel.
3.6 Any work that closes or prohibits or limits facility access shall be coordinated with 718CES/CENMD.
3.7 The Contractor shall provide a weather delay request within 48 hours of inclement weather that caused the work delay. An extension to the construction completion date may be provided if the total amount of inclement work days exceeds the estimated unfavorable weather days listed in para 2.4 (e).
3.8 Joint job site inspection shall be conducted by the project engineer, user, contractor, and 18 CONS/LGCC representatives.
4.0 Special Requirements:
4.1 Asbestos Containing Materials (ACM) and Lead Based Paint (LBP) survey: Follow the latest JEGS requirements.
a. Available ACM and LBP results on record will be provided to the Contractor for reference only.
The Contractor shall remain responsible for additional testing of existing materials that will be affected by the scope of work.
b. Prior to field sampling, the following must be submitted to 18 AMDS/SGPB (Bioenvironmental
Engineering) and 718 CES/CEIE (Environmental) for review and approval: Certificate of
Training, Sampling Plan and Protective Equipment Plan.
c. Building access must be coordinated with the proper agencies through the 718CES/CENMA.
d. Building must be visually surveyed for existing finish, materials and painted surfaces which are suspected containing ACM or LBP.
e. Floor plan (small scale) of the building shall be submitted showing specific locations where samples were taken; e.g., duct flange gasket, duct flexible connection, paint on ductwork, walls, ceilings, interior and exterior paint, etc.. Test results shall be submitted no later than with the
65% design submittal.
f. Destructive sampling shall be taken from areas that are not easily visible and shall be patched to match existing finish.
g. Protection of properties: The Contractor shall protect all equipment, furniture and other items not removed in the work area with approved protective materials while accomplishing sampling.
4.2 Asbestos Containing Materials (ACM) and Lead Based Paint Abatement:
a. HEPA Vacuum Cleaner: Where ACM or LBP is found after testing, the Contractor shall apply the HEPA vacuum cleaner for a drilling work of existing wall, floor and ceiling for new piping and conduit installation to avoid escape of the waste media into the surrounding environment, and the waste media shall be disposed in accordance with all applicable Federal, FEGS, GOJ, JEGS, Prefectural and local regulations.
b. This project does not directly call for abatement, simply fastening new materials to the existing structure. However, should asbestos containing material be found, all abatement work shall be completed and the waste media shall be disposed in accordance with all applicable Federal, FEGS, GOJ, JEGS, Prefectural and local regulations.
c. All LBP/ACM materials removed through demolition shall also be disposed of in accordance with all applicable Federal, FEGS, GOJ, JEGS, Prefectural and local regulations.
4.3 Cost Breakdown:
The Contractor’s cost proposal shall include the cost for abatement of ACM and LBP. If any
ACM and/or LBP test results are negative, such costs will be deducted from the contract costs and credited back to the Government.
5.0 Description of Work: The work consists of the following elements in addition to the drawings and specifications.
5.1 Architectural
5.1.1 Remove 9 transoms above existing patio door assemblies. Remove four sets of four-single pane sidelights, and four sets of two- single pane doors.
5.1.2 Provide and install new high-efficiency, argon filled, double pane windows with a low-e coating in a thermally broken aluminum frame. New double doors for entry onto the patio from the house shall also be aluminum framed and contain low e coated double paned glass. Door swings for newly installed doors shall open onto the patio NOT inward towards the house interior to prevent moisture from entering the home. (see renovation highlights )Frames shall have a bronze finish to match existing window units throughout the residence. The new aluminum doors shall be provided with hinges, lockset, closers, door bolts, door stops and threshold.
5.1.3 Aluminum door and windows shall comply with the following UFGS:
UFGS 08 11 16 Aluminum Doors and Frames
UFGS 08 51 13 Aluminum Windows
UFGS 08 71 00 Door Hardware
UFGS 08 81 00 Glazing
5.1.4 Paint to disturbed interior/exterior areas shall match that of the existing interior/exterior as shown in the attached pictures.
5.1.5 The outer surface of the three structural columns in the desired area of renovation shall be stripped of wood trim and covered with textured paint to match the other exterior columns (see interior finishes drawing) The outer most columns where the patio screen transitions onto the house exterior shall match all other exterior column finishes (See elevation drawing).
5.1.6 Patch and repair work shall include proper sealing of adjoining members on exterior columns to prevent rain water from entering the patio.
5.1.7 Reference drawings shall include floor plan, current window and door details, exterior elevations and current photographs of finishes and areas of work to be completed.
5.2 Demolition Work: Project requires the removal of multiple window frames along the western interior wall adjacent to the sunroom. Demolition shall include necessary baseboard, door header, window frame, and wood trim attached to the structural columns. Wood flooring at the base of the existing window frames and door shall be removed during the construction process. Upon completion, new wood flooring shall be installed. All interior curtains shall be removed and reinstalled upon completion of this project.
5.2.1 Contractor shall provide drywall barrier for interior work to separate workspace from the rest of the interior of the house.
5.3 Design Analysis:
a. Schematic Project Scope
b. Schematic Code Analysis including life safety and the Americans with Disabilities Act (ADA)
Accessibility
5.4 Electrical Work: Electrical work shall include the relocation of one exterior light switch box located on structural column to the adjacent interior wall (See Modified plan), allowing user control from the interior of the house. An exterior dual outlet, exterior light switch for patio lights and an interior dual outlet are already in-tact and shall remain in place upon completion of this project.
6.0 Government Furnished Equipment of Materials: None
7.0 Attachments:
As-built Drawings
ACM/LBP Sampling Data
HEPA Vacuum Cleaner (Notes for Drilling & Drill Waste Removal)
JEGS
Env Spec: SECTION 01 56 00, ENVIRONMENTAL PROTECTION
ENVIRONMENTAL PROTECTION SPECS
SECTION 01 56 00
ENVIRONMENTAL PROTECTION
PART 1 - GENERAL
1.01 REFERENCES: The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only. Environmental specific management plans and policies are avail on request, by calling or emailing the Environmental
Element 634-2600 or 718ces.cean@us.af.mil. All plans and policies requested will be sent as an electronic file. The Contractor will comply with applicable laws and regulations of the Governments of the United States and Japan, however denominated, including those applicable political subdivisions, departments, and other entities, to include but not be limited to, the most current versions of the following:
A. CODE OF FEDERAL REGULATIONS (CFR)
29 CFR 1910 Occupational Safety and Health Standards
B. UNITED STATES AIR FORCE INSTRUCTIONS (AFI)
C.
AFI
23-204 KABSUP_I
Organizational Fuel Tanks Kadena Air Base Supplement - 30
Sept 13
AFI
32-1066
Backflow Prevention Program – 8 Oct 07
AFI
32-1067
Water Systems – 4 Feb 15
Environmental Management (Rpl 7006 & 7080) - 6 Jun 13 mailto:718ces.cean@us.af.mil
AFI
32-7001
AFI
32-7041
Water Quality Compliance – 1 Mar 09
AFI
32-7042
Waste Management – 7 Nov 14
AFI
32-7086
Hazardous Materials Management – 4 Feb 15
AFI
48-144
Safe Drinking Water Surveillance Program – 2 Oct 14
D. UNITED STATES FORCES JAPAN
JEG
S
Japan Environmental Governing Standards 17 Dec 2012
E. HQ PACAF POLICIES
PACAF
UST POLICY
PACAF Underground Storage Tank (UST) Management
Policy for Air Force Installations in Japan and Republic of
Korea, - 15 Mar 1999
F. LOCAL REGULATIONS, PLANS, POLICIES
18W
G AMP
th WG Asbestos Management Plan –Jul 12
18W
G AST STANDARDS
th WG Above Ground Fuel Storage Tank Installation
Details and
Specifications –Sept 09
18W
G HMMP
th WG Installation Hazardous Materials Management Plan
–Mar 12
18W
G HWMP
th WG Admin Plan 544–Hazardous Waste Management
Plan–Jun 10
18W
G ICRMP
th WG Integrated Cultural Resources Management Plan –
May 13
18W
G INRMP
th WG Integrated Natural Resources Management Plan –
Sept 10
18W
G SPRP
th WG Admin Plan 545 – Spill Prevention and Response –
Apr 13
18W
G SWPPP
18W
G UEC POLICY
th Wing Storm Water Pollution Prevention Plan – Jun14
Kadena Air Base Unit Environmental Coordinator Policy -
23 Feb 15
FA5270-15-T-0104
1.02…
This is the start of the file's text. The full file is on GovTribe.