YVEW190001
Replace
Generators (B310)
Wheeler Army Air Field
611th Civil Engineer Squadron 15 January 2020
YVEW190001 Replace Generators (B310) January 15, 2020
1. GENERAL:
1.1. The Contractor shall provide all management, tools, equipment, transportation, supervision and labor necessary to remove and replace (2) 450kW Generators and associated hardware at Wheeler Army Airfield, Oahu, HI. The Contractor shall perform all work in accordance with this Statement of Work (SOW). The Contractor shall coordinate all work with the Contracting Officer and is subject to the work schedule as stated in this document.
1.2. ALL CHANGES to this statement of work must be approved by the Contracting Officer. Contractor shall not perform any work outside the scope of this contract.
1.3. Unless otherwise noted in writing by the Contracting Officer, the Contracting Officer is the only person with the authority to change, modify, deny or approve any part and has the sole authority for all aspects of contract, SOW’s, contract changes, approvals, payments and project changes.
2. STATEMENT OF WORK:
PROJECT NARRATIVE
Contractor shall remove and replace the two (2) existing 450kW diesel generators and upgrade the existing interior power distribution system. Within the scope of this project, the Contractor shall provide all electrical equipment, including conduit, conductor, and associated hardware, to ensure a complete and functional power distribution system for normal and standby power. The existing Main Distribution Panel A (MDPA) and associated Automatic Transfer Switch will be removed and replaced. A new Automatic Transfer Switch will be installed to provide standby power capabilities to the existing Main Distribution Panel B (MDPB). This addition will expand the buildings standby power capabilities, making it possible to energize the entire building rather than just the Operations Core during a power outage. To complete this upgrade, the Contractor shall install a new Power Panel inside of the Building 310 Operations Room.
Building 310 at Wheeler Army Airfield is a Hawaii Air National Guard (HIANG) facility and it houses the Pacific Air Defense Sector (PADS) mission. This is a 24/7, 365, National Defense Mission. The Contractor shall ensure that all temporary power is in place during outages to ensure the Mission remains continuous and uninterrupted.
SPECIFIC REQUIREMENTS
2.1. Remove and replace the two (2) existing 450kW Generators with Generators of the same capacity.
Pictures of existing provided in the appendix below.
2.1.1. Contractor shall provide temporary stand-by power at all times that Generators are not serviceable.
2.1.2. Contractor shall dispose of the two existing Generators. If applicable, Contractor shall provide Hazardous Waste Generator reports to 611th CES at time of disposal.
2.1.3. When switching to temporary power, Contractor shall notify and schedule with on-site personnel.
Contractor must provide a minimum of one (1) week notification prior to making the switch and receive approval from on-site personnel. This applies for any and all planned outages.
2.2. Remove and replace 800A/480V three-phase main distribution panel A (MDPA) and the existing Automatic Transfer Switch (ATS) inside of the Electric Room.
2.2.1. MDPA and ATS shall match existing capacity, match new circuit breakers, and have an 800A service-rated main circuit breaker.
2.2.2. Contractor shall demolish and dispose of the existing ATS, MDPA, and all abandoned or superfluous conduit, raceway, and associated hardware.
2.2.3. Contractor shall patch, finish, and paint all penetrations.
2.3. Contractor shall install a new 400A/480V three-phase Automatic Transfer Switch (ATS) in the
Generator Room.
2.3.1. ATS shall provide standby power to existing 400A/480V three-phase Main Distribution Panel B
(MDPB).
2.3.2. Contractor shall install adequately sized pull box between MDPA and MDPB. Pull box will be used to intercept and reconnect the two sets of service conductors being routed to the two now ATS’s serving MDPA and MDPB during outages.
2.3.3. Contractor shall install a 400A/480V Enclosed Circuit Breaker (ECB) or fused disconnect to de-rate the standby power feeder from the generator to the ATS.
2.3.4. Contractor shall provide stand by power from common generator source with MDPA to ensure parallel configuration. Contractor shall configure so that both ATS’s activate concurrently to switch to standby power when either or both services lose power.
2.3.4.1. Note: Power will switch back to primary power feed only after both services have power restored. The MDPs (MDPA and MDPB) are fed from separate services (protected at 800A and 400A, respectively) from a recently installed dual 1200A switch; these two feeds are parallel and come from the dual switch and 1000kW transformer located outside of building
310. One-Line Diagram provided in the appendix.
2.4. Contractor shall install an additional 125A three-phase 120/208V Power Panel in the Operations Room.
2.4.1. This panel must be energized when building is switched to standby power.
2.4.2. The Operations Room is a Secure Area. Contractor will require a Government Escort to perform work inside the Operations Room. The Contractor must coordinate with on-site personnel to accomplish the installation.
2.5. Contractor shall verify that existing building grounding electrode system is adequate. If electrode system is found inadequate, Contractor shall notify CO and 611th CES immediately and await for direction.
2.6. Contractor shall test and fully commission both generators and all associated equipment. Commission reports shall be provided to and approved by 611th CES prior to project closeout.
2.7. All material removed/demolished throughout the course of this project must be removed from the site and be properly disposed of IAW Federal, State and Local Regulations.
2.8. Project shall be completed NLT 60 days after the issuance of the NTP.
3 SPECIFICATIONS:
3.1 All work shall be done in accordance with Air Force Manual (AFMAN) 31-1084, the National Electric
Code (NEC), and the following Unified Facilities Criteria (UFC’s) and United Facilities Guide Specifications (UFGS).
3.1.1 UFC 3-501-01, Electrical Engineering
3.1.2 UFC 3-520-01, Interior Electrical Systems
3.1.3 UFC 3-540-01, Engine-Driven Generator Systems for Prime and Standby Power Applications
3.1.4 UFC 3-540-07, Operations and Maintenance (O&M); Generators
3.1.5 UFC 4-010-06, Cybersecurity of Facility-Related Control Systems
3.1.6 UFGS 26 20 00, Interior Distribution System
3.1.7 UFGS 26 26 16.00, Panelboards
3.1.8 UFGS 26 28 21.00 40, Automatic Transfer Switch (ATS)
3.1.9 UFGS 26 36 23.00 20, Automatic Transfer Switch (ATS)
3.1.10 UFGS 26 32 15.00 10, Diesel Generator Set Stationary 100-2500kW
3.1.11 UFGS 26 05 26.00 40, Grounding and Bonding for Electrical Systems
3.1.12 NFPA 70, National Electric Code
3.1.13 IEEE C2, National Electric Safety Code
3.2 In accordance with Federal Acquisition Regulation (FAR) 52.236-7, the Contractor shall be liable for any damage caused to public or private property as a result of negligent acts by the Contractor, subcontractor, employee, agent, or representative of the Contractor.
3.3 SITE WORK:
3.3.1 GOVERNMENT OCCUPANCY: Coordinate with the Contracting Officer Representative
(COR) and cooperate fully with the occupant(s) during construction operations to minimize conflicts and to facilitate government usage. Perform the work so as not to interfere with the government’s operations. Immediately report any issues/conflicts to the Contracting Officer or
COR.
4 SCHEDULING AND PHASING OF WORK:
4.1 Upon receipt of award notification for this project, the Contractor is to immediately commence with scheduling of all construction activities and provide the Contracting Officer with a schedule of work.
The construction schedule shall be provided to the contracting officer within ten (10) calendar days of award.
4.2 A Pre-Construction (Pre-Con) meeting is required prior to construction. Some topics to be covered are:
Submittal Submissions, Site Access, Approved Contractor Lay down Areas, Safety, Period of Performance and Contractor questions. Pre-Con members include the Contracting Officer and Civil Engineer. Pre-Con shall be scheduled within 10 calendar days of award.
4.3 Notify 611 Civil Engineer Squadron (CES/CEN) at 907-552-1448, 766 SCONS Contracting Officer (CO) at 808-448-2987, and 611 Air Support Squadron Project Manager (ASUS/PM) at 907-552-5020 one week prior to project site visits, construction start and construction completion.
4.4 Notice to Proceed (NTP) shall be issued following a Pre-Con meeting scheduled by the Contracting Officer.
4.5 General Schedule:
4.5.1 Award: Begin scheduling construction activities.
4.5.2 Pre-Con Meeting and additional time for questions to be addressed: The NTP will be issued.
4.5.3 10 days from issue of NTP: Contractor must begin construction activities.
4.5.4 Total Period of Performance from issue of NTP: Contractor must have completed all work.
4.5.6 Period of Performance: 60 Days from issue of NTP.
5 STORAGE AND DISPOSAL OF CONTRACTOR MATERIALS:
5.1 The Contractor shall be responsible for the receipt, unloading, security and handling of all equipment and materials required for the completion of this work. The Contractor shall identify storage requirements and coordinate with the COR.
5.2 The Contractor shall secure all material and equipment at the end of each working day. No hazardous materials or waste may be left on site at the end of the work day. All material removed/demolished throughout the course of this project must be removed from site and be properly disposed of IAW Federal, State and Local regulations.
5.3 All materials are the responsibility of the Contractor; Government will not reimburse contractor for stolen items or delivery related additional incurred costs (such as weather related materials delays).
5.4 The Contractor shall remove and dispose of all construction debris prior to final inspection.
6 CONTRACTOR FURNISHED ITEMS AND SERVICES:
6.1 The Contractor shall furnish all necessary supplies, fuels, lubricants, solvents, parts, materials, equipment, products, tools, electricity, any other items, and all services that are required to perform this statement of work.
7 INSPECTIONS/QUALITY CONTROL:
7.1 The Contractor shall comply with the general terms of the overall contract with respect to construction quality control, inspections, and acceptance by the Government.
7.2 SAFETY:
7.6.1 The Contractor shall conduct his operation in accordance with all Federal, State and Local regulations and/or standards pertinent to "Safe Practices". The COR shall inspect the job site to insure safety standards are met. All contract workers must wear proper personal protection equipment per OSHA requirements.
7.6.2 The Contractor shall furnish, erect, and maintain all barricades, warning signs, “rope-offs”, detours, markings and other protection for hazards.
7.6.3 The Project Engineer, COR or the Contracting Officer may stop work at any time for a potential safety hazard. The Contracting Officer is the only personnel allowed to restart work in writing.
8 SUBMITTAL REQUIREMENTS:
8.1 GENERAL: For each facet of construction, the Contractor shall submit material samples, drawings and related calculations to the Contracting Officer for approval at minimum of seven (7) calendar days prior to procurement, placement of that particular material and construction respectively. Upon review by the Contracting Officer, the submittals along with any comments will be returned to the Contractor.
If required, the Contractor shall modify the submittals per the Contracting Officer comments and resubmit within three (3) calendar days for final approvals. Upon final approval, the Contractor shall commence with the procurement and construction activity accordingly.
8.2 The Contractor shall provide a comprehensive schedule in support of their proposal. This original schedule shall contain key milestones, critical path, and proposed start/completion dates and shall be considered as the project baseline schedule upon award. The Contractor shall update this schedule monthly or as critical tasks are exceeded more than 7 calendar days.
8.3 The Contractor shall have an established, maintained, and readily available to review Quality Control and Accident Prevention program.
8.4 The Contractor shall submit Material Safety Data Sheets (MSDS) for all permanently installed materials prior to procurement.
8.5 The Contractor shall provide two (2) complete set of all documents:
8.5.1 SUBMITTALS: The Contractor shall submit materials the Contractor anticipates to install for Contracting Officer approval. The submittals shall include the physical size of the equipment, performance characteristics at design conditions, ratings (structural or otherwise), and other pertinent standards. All project submittals will be accompanied by a completed AF Form 3000, Material Approval Submittal.
8.5.2 SUBCONTRACTING: The Contractor shall submit a fully executed SF 1413, Statement and Acknowledgment, upon award of each subcontract.
8.5.3 SHOP DRAWINGS/AS-BUILTS: The Contractor shall submit As-Builts and other submittals to the Contracting Officer and COR for approval.
8.6 ACCEPTANCE AND APPROVALS: Acceptance and Approval shall be required from the COR and Contracting Officer on all submittals prior to procurement and installation.
9. Attachments:
9.1 Photo of existing two (2) 450 kW diesel transformers & Photo of existing MDPA and ATS
9.2 Building 310 Electric Plan
9.3 One-Line Diagram & Red-Lined One-Line Diagram
9.1 – Photos
Generators
MDPA & ATS
9.2. Building 310 Electric Plan (Existing)
(Continued on Next Page)
9.3. One Line Diagram & Red-Line
Note: One-Line represents current configuration. New work notated was accomplished during the 2019 transformer and switchgear replacement project. A shop drawing of the red-line diagram for this project is found on the next page.
Red-Line Diagram