Contractor_Question.pdf
PDF 298 KB Posted
- Attached to
- Tactical Mobility Training Federal contract opportunity
- Solicitation number
- FA485518R0015
About this file
Questions & Responses
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SOW_-_Overland_Mobility_PWS.pdf | ||
| Combined_Synopsis-Solicitation.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Contractor Question/Concern
"One contractor is recommending performance dates of (May 2018) due to permit reservations and possible limitations on shooting the RPG due to range constraints. The reason behind recommendation of training dates 30-45 days out is due to the solicitation award/approval date being only 2 weeks from the expected performance date. For this type of training we require 30-45 days prior to training in order to reserve the Arizona shooting range and to gain permit approval from the AZ Bureau of Land Management for our overland movement in Western Arizona.
Other concern is the timeline for conducting a site survey. According to the PWS posted on the solicitation, upon approval the Air Force will require a site survey to ensure the training site is adequate which is more feasible if the performance date is adjusted."
Response
We are unable to change the original performance dates from the solicitation due to schedule conflicts.
The training requirement or period of performance required stays as stated in the solicitation.