Q and A Document.pdf
PDF 68 KB Posted
- Attached to
- Transformers Federal contract opportunity
- Solicitation number
- FA4626-20-Q-0046
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 001.pdf | ||
| (Revised) 20-Q-0046 Combined Synopsis Solicitation.pdf | ||
| Atch 1. Specifications Sheet.pdf | ||
| 20-Q-0046 Combined Synopsis Solicitation.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUESTION AND ANSWER DOCUMENT
Requirement: Transformers
20 July 2020
Q1: In reference to gauges, is the customer requesting a liquid level, pressure vacuum, or liquid temperature gauge?
A1: Temperature gauges.
Q2: Can the delivery period be extended from 30 days?
A2: Yes, please see Amendment 001.
Q3: Who is responsible for unloading the transformers?
A3: The contractor will be responsible for the product until it is off the truck and ready to be inspected and accepted by the Government.
Q4: Where specifically do these transformers get delivered to on base?
A4: Delivery will be made clear after award on the award document and through direct communication with the customer.
Q5: Is the delivery area accessible to a freight truck and a forklift?
A5: Yes, you can expect enough room for a freight truck and forklift.