BAFB_Combined_Price_List-_revised_quote_sheet.xlsx XLSX spreadsheet
SOW_Water_Remediation.doc DOC document
Bid_Sheet_Water_Remediation.xlsx XLSX spreadsheet
Wage_Determination.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Quote Sheet

Advanta Clean
CONTRACT LINE ITEM NO. (CLIN)SUPPLIES/SERVICEUNITUNIT PRICE ($)AMOUNT ($)
0001NON-PERSONAL SERVICES: Provide all supervision, personnel, equipment, transportation, material, and other items and services necessary to performWater Remediation at Barksdale AFB Base LA for a period 5 years in accordance with the PWS.
WATER REMEDIATION DESCRIPTION - SERVICES
0002Emergencey service call - after business hoursEA$$
0003Emergencey service call - during business hoursEA$$
0004Hazardous Waste/Mold Cleaning - Supervisor/AdminHR$$
0005Cleaning Remediation Supervisor/AdministrativeHR$$
0006Cleaning Remediation TechnicianHR$$
0007Apply anti-microbial agentSF$$
0008Apply anti-microbial agent - micromisterCF$$
0009Haul debris - per pickup truck load - including dump feesEA$$
0010HEPA VacuumHR$$
0011Seal/coat {V} - one coats (anti-microbial coating)SF$$
0012Sand exposed framingSF$$
0013Ducting - lay flat - largeLF$$
0014Deordorize building - Hot thermal fogCF$$
0015Deordorize chamber - OzoneCF$$
0016Box and liner - used for hazardous waste cleanup - mediumEA$$
Content Cleaning
0017Clean and deodorize carpetSF$$
0018Clean floors (all hard floors)SF$$
0019Clean walls and ceilingSF$$
0020Clean ceiling gridsSF$$
0021Clean chairsEA$$
0022Clean and deodorize mattress or box spring - fullEA$$
0023Clean tables - end tablesEA$$
0024Clean tables - coffee tablesEA$$
0025Clean tables - diningEA$$
0026Clean bookcase contentsLF$$
0027Clean bookcaseSF$$
0028Clean desk contentsLF$$
0029Clean deskEA$$
$ - 0
Content Manipulation
0030Contents- manipulation - hourly chargeHR$$
0031Contents- manipulation - after hours hourly chargeHR$$
0032Block and pad furniture - hourly chargeHR$$
0033General LaborHR$$
0034Inventory, Packing, Boxing, and Moving chargeHR$$
0035Move out then reset - large roomEA$$
0036Moving Van (17' - 20') and equipmentEA/DA$$
0037Protect contents - Cover with plasticSF$$
0038Protect contents - Cover with plastic - after hoursSF$$
$ - 0
Equipment & Filters
0039Power distribution boxEA/DA$$
0040Thermal imagingEA$$
0041Dehumidifier (per 24 hour period) - Xlarge - No monitoringEA/DA$$
0042Dehumidifier (per 24 hour period) - Small - Desiccant - No monitoringEA/DA$$
0043Dehumidifier (per 24 hour period) - Large - Desiccant- No monitoringEA/DA$$
0044Air mover (per 24 hour period) - No monitoringEA/DA$$
0045Air mover axial fan (per 24 hour period) - No monitoringEA/DA$$
0046Vane axial fan 1hp air mover (per 24 hour period) - No monitoringEA/DA$$
0047Wood floor drying-Inj. Type (per 24 hour period) - No monitoringEA/DA$$
0048Hydrodoxal GeneratorEA/DA$$
0049Neg. air fan/Air scrub-Large (per 24 hour period) - No monitoringEA/DA$$
0050Neg. air fan/Air scrub-XLarge (per 24 hour period) - No monitoringEA/DA$$
0051HEPA filters for neg. airEA$$
0052Add for HEPA filter (for canisters/backpack vacuum)EA$$
0053Equipment Setup/Take Down and Monitoring (Business Hours)HR$$
0054Equipment Setup/Take Down and Monitoring (After Business Hours)HR$$
0055Single axle dump truck - per load - including dumping feesEA$$
0056Dumpster LoadEA$$
$ - 0
Heat Drying
0057Thermal air mover - electricDA$$
$ - 0
Decontamination
0058Equipment decontamination charge - per piece of equipmentEA$$
Extraction
0059Water extraction from floorSF$$
0060Water extraction from floor - HeavySF$$
0061Water extraction from floor - Category 2 water (Gray water)SF$$
0062Water extraction from floor - Category 3 water (Sewage)SF$$
0063Water extraction from floor - Weight - assistedSF$$
0064Lifted carpet for dryingSF$$
00652" Submersible pum with hose (per 24 hour period)EA/DA$$
0066Portable extractor with hoses and flood toolEA$$
$ - 0
Containments
0067Containment Barrier/Airlock/Decon. ChamberEA$$
0068Containment Barrier/Airlock/Decon. Chamber - after hoursSF$$
0069Containment Barrier - tension post - per dayEA/DA$$
0070Peel & seal zipperEA$$
$ - 0
Perpsonal Protective Equipment
0071Eye protection - plastic goggles- DisposableEA$$
0072Respirator replacement cartridge (per pair)EA$$
0073RespiratorEA$$
0074GlovesEA$$
0075Add for personal protective equipment (hazardous cleanup)EA$$
$ - 0
Demo
0076Baseboard - detachLF$$
0077Tear out trim/baseLF$$
0078Add-on for tearing out trim/base from tile/groutLF$$
0079Tear out wet drywall, cleanup, bag for disposal - up to 2' tallLF$$
0080Tear out wet non-salvageable carpet, cut & bag for disposalSF$$
0081Tear out wet non-salvageable carpet, cut & bag - Category 3 waterSF$$
0082Tear out wet carpet pad and bag for disposalSF$$
0083Tear out wet carpet pad and bag - Category 3 waterSF$$
0084Tear out tackless strip and bag for disposalLF$$
0085Tear out non-salvageable vinyle & underlay, cut and bag for disposalSF$$
0086Tear out non-salvageable underlayment & bag for disposalSF$$
0087Tear out non-salvageable Laminate floor and bag for disposalSF$$
0088Tear out non-salvageble Laminate floor and bag - Category 3 waterSF$$
0089Tear out and bag wet insulationSF$$
0090Tear out and bag wet insulation in crawl spaceSF$$
0091Remove unsalvageble pipe insulationLF$$
0092Remove unsalvageable ceiling tilesSF$$
0093Drill holes for wall cavity dryingEA$$
0094General DemolitionHR$$
$ - 0
Material Only
0095Barricade 6 mil adhesive plyRL$$
0096Fiberlock IAQ 6000 1 galEA$$
0097Fiberlock IAQ 6000 5 galEA$$
0099Foam for pressure containmentRL$$
0100Poly hangersBX$$
0101Sticky MatRL$$
0102Caution TapeRL$$
0103Provide box , packing paper, & tape - medium sizeEA$$
0104Provide stretch film/wrapRL$$
0105Provide bubble wrap - add on cost for fragile itemsLF$$
0106Provide furniture lightweight blanket/padEA$$
0107Plastic Bag - used for disposal of contaminated itemsEA$$
0108Ceiling tile - 2" X 2"SF$$
$ - 0ERROR:#REF!
HVAC SYSTEM REMEDIATION DESCRIPTION
0109On-site Evaluation and/or Supervisor/AdministratorHR$$
0110Cleaning Remediation Supervisor/AdministrativeHR$$
0111Cleaning Remediation TechnicianHR$$
0112Clean ductwork - Interior (Per Register)EA$$
0113Clean ductwork - Interior - Heavy clean (Per Register)EA$$
0114Clean ductwork - ExteriorLF$$
0115Clean all accesible AHU components & housingEA$$
0116Anti-microbial Agent ApplicationSF$$
0117Deodorizer ApplicationCF$$
0118Clean filtersEA$$
0119Replace filtersEA$$
0120Replace RegistersEA$$

After Disaster

CONTRACT LINE ITEM NO. (CLIN)SUPPLIES/SERVICEQTYUNITUNIT PRICE ($)
0001NON-PERSONAL SERVICES: Provide all supervision, personnel, equipment, transportation, material, and other items and services necessary to perform Mold Remediation at Joint Base Langley Eustis (Ft. Eustis) for the period 5 years in accordance with the PWS.
WATER REMEDIATION DESCRIPTION - SERVICES
0002Emergency service call - after business hoursEA$145.00
0003Emergency service call - during business hoursEA$95.00
0004Hazardous Waste/Mold Cleaning Technician - after hoursHR$85.00
0005Hazardous Waste/Mold - Labor MinimumHR$150.00
0006Hazardous Waste/Mold Cleaning - Supervisor/Admin - after hours1HR$110.00
0007Hazardous Waste/Mold Cleaning - Supervisor/Admin1HR$70.00
0008Cleaning Remediation Supervisor/Administrative1HR$53.90
0009Cleaning Remediation Technician1HR$39.20
0010Soda Blasting1SF$1.64
0011Soda Blasting - Heavy1SF$1.98
0012Soda Blasting - Extra Heavy1SF$2.34
0013Dry Ice Blasting - Heavy1SF$3.05
0014Dry Ice Blasting - Extra Heavy1SF$3.71
0015Add on confined space blasting1SF$0.44
0016Apply anti-microbial agent1SF$0.16
0017Apply anti-microbial agent - after hours1SF$0.22
0018Apply anti-microbial agent - micromister1CF$0.05
0019Haul debris - per pickup truck load - including dump fees1EA$110.00
0020HEPA Vacuum1HR$45.00
0021Seal/coat {V} - one coats (anti-microbial coating)1SF$0.85
0022Sand exposed framing1SF$1.09
0023Ducting - lay flat - large1LF$0.49
0024Deordorize building - Hot thermal fog1CF$0.04
0025Deordorize chamber - Ozone1CF$0.07
0026Box and liner - used for hazardous waste cleanup - medium1EA$3.87
Content Cleaning
0027Clean and deodorize carpet1SF$0.25
0028Clean floors (all hard floors)1SF$0.24
0029Clean walls and ceiling1SF$0.22
0030Clean ceiling grids1SF$0.17
0031Sofa - Heavy cleaning1LF$27.00
0032Clean chairs (upholstered)1EA$55.00
0033Clean and deodorize mattress or box spring - full1EA$49.00
0034Clean tables - end tables1EA$7.00
0035Clean tables - coffee tables1EA$8.91
0036Clean tables - dining1EA$10.75
0037Clean bookcase contents1LF$5.10
0038Clean bookcase1SF$0.67
0039Clean desk contents1LF$5.10
0040Clean desk1EA$14.15
0041Clean computer printer - small (desk top) wipe down1EA$10.50
0042Clean computer CPU box - exterior wipe down1EA$8.15
0043Clean computer keyboard - exterior wipe down1EA$7.91
0044Clean computer monitor - exterior wipe down1EA$8.15
0045Clean footlockers (chest)1EA$13.82
Content Manipulation
0046Contents- manipulation - hourly charge1HR$22.00
0047Contents- manipulation - after hours hourly charge1HR$32.00
0048Block and pad furniture - hourly charge1HR$44.71
0049General Labor1HR$23.09
0050Inventory, Packing, Boxing, and Moving charge1HR$23.09
0051Move out then reset - large room1EA$44.84
0052Moving Van (17' - 20') and equipment1EA/DA$125.00
0053Off site storage &insurance - per month1SF$0.79
0054Off site storage &insurance - climate controlled - per month1SF$1.15
0055Protect contents - Cover with plastic1SF$0.14
0056Protect contents - Cover with plastic - after hours1SF$0.27
Equipment & Filters
0057Power distribution box1EA/DA$33.47
0058Thermal imaging1EA$220.50
0059Dehumidifier (per 24 hour period) - Xlarge - No monitoring1EA/DA$107.80
0060Dehumidifier (per 24 hour period) - Small - Desiccant - No monitoring1EA/DA$53.90
0061Dehumidifier (per 24 hour period) - Large - Desiccant- No monitoring1EA/DA$73.50
0062Air mover (per 24 hour period) - No monitoring1EA/DA$24.92
0063Air mover axial fan (per 24 hour period) - No monitoring1EA/DA$31.15
0064Vane axial fan 1hp air mover (per 24 hour period) - No monitoring1EA/DA$34.43
0065Wood floor drying-Inj. Type (per 24 hour period) - No monitoring1EA/DA$205.80
0066Hydrodoxal Generator1EA/DA$222.11
0067Neg. air fan/Air scrub-Large (per 24 hour period) - No monitoring1EA/DA$122.50
0068Neg. air fan/Air scrub-XLarge (per 24 hour period) - No monitoring1EA/DA$137.90
0069HEPA filters for neg. air1EA$210.56
0070Add for HEPA filter (for canisters/backpack vacuum)1EA$51.00
0071Equipment Setup/Take Down and Monitoring (Business Hours)1HR$41.50
0072Equipment Setup/Take Down and Monitoring (After Business Hours)1HR$64.16
0073Single axle dump truck - per load - including dumping fees1EA$165.00
0074Dumpster Load1EA$470.00
Heat Drying
0075Artic Cub - ind.fired heater w/ducting - 170 kBtuh1EA/DA$453.10
0076Thermal air mover - electric1DA$177.30
Decontamination
0078Equipment decontamination charge - per piece of equipment1EA$28.63
Extraction
0079Water extraction from floor1SF$0.42
0080Water extraction from floor - Heavy1SF$0.52
0081Water extraction from floor - Category 2 water (Gray water)1SF$0.68
0082Water extraction from floor - Category 3 water (Sewage)1SF$1.07
0083Water extraction from floor - Weight - assisted1SF$0.65
0084Lifted carpet for drying1SF$0.26
00852" Submersible pum with hose (per 24 hour period)1EA/DA$14.70
0086Portable extractor with hoses and flood tool1EA$122.50
Containments
0087Containment Barrier/Airlock/Decon. Chamber1SF$0.56
0088Containment Barrier/Airlock/Decon. Chamber - after hours1SF$0.80
0089Containment Barrier - tension post - per day1EA/DA$9.80
0090Peel & seal zipper1EA$22.05
Perpsonal Protective Equipment
0091Eye protection - plastic goggles- Disposable1EA$11.76
0092Respirator replacement cartridge (per pair)1EA$12.05
0093Respirator (half face)1EA$1.64
0094GlovesEA$0.33
0095Add for personal protective equipment (hazardous cleanup)EA$7.35
Demo
0096Baseboard - detachLF$0.31
0097Tear out trim/baseLF$0.31
0098Add-on for tearing out trim/base from tile/groutLF$0.38
0099Tear out wet drywall, cleanup, bag for disposal - up to 2' tallLF$2.25
0100Tear out wet non-salvageable carpet, cut & bag for disposalSF$0.37
0101Tear out wet non-salvageable carpet, cut & bag - Category 3 waterSF$0.53
0102Tear out wet carpet pad and bag for disposalSF$0.35
0103Tear out wet carpet pad and bag - Category 3 waterSF$0.50
0104Tear out tackless strip and bag for disposalLF$0.61
0105Tear out non-salvageable vinyle & underlay, cut and bag for disposalSF$1.19
0106Tear out non-salvageable underlayment & bag for disposalSF$0.98
0107Tear out non-salvageable Laminate floor and bag for disposalSF$1.13
0108Tear out non-salvageble Laminate floor and bag - Category 3 waterSF$1.64
0109Tear out and bag wet insulationSF$0.50
0110Tear out and bag wet insulation in crawl spaceSF$0.94
0111Remove unsalvageble pipe insulationLF$0.56
0112Remove unsalvageable ceiling tilesSF$0.26
0113Drill holes for wall cavity dryingEA$0.36
0115General DemolitionHR$27.44
Material Only
0116Barricade 6 mil adhesive plyRL$95.00
0117Fiberlock IAQ 6000 1 galEA$68.40
0118Fiberlock IAQ 6000 5 galEA$339.00
0119Foam for pressure containmentRL$38.35
0120Poly hangersBX$28.00
0121Sticky MatEA$45.00
0122Caution TapeRL$27.58
0123Provide box , packing paper, & tape - medium sizeEA$3.14
0124Provide stretch film/wrapRL$65.00
0125Provide bubble wrap - add on cost for fragile itemsLF$0.18
0126Provide furniture lightweight blanket/padEA$5.46
0127Plastic Bag - used for disposal of contaminated itemsEA$2.76
0128Ceiling tile - 2" X 2"SF$0.82
HVAC SYSTEM MOLD REMEDIATION DESCRIPTION
0129On-site Evaluation and/or Supervisor/AdministratorHR$43.68
0130Cleaning Remediation Supervisor/AdministrativeHR$53.90
0131Cleaning Remediation TechnicianHR$39.20
0132HVAC TechnicianHR$84.50
0133Furnace - check, clean replace filters and serviceEA$109.23
0134Furnace-check, heavy clean replace filters and serviceEA$171.65
0135Clean ductwork - Interior (Per Register)EA$27.22
0136Clean ductwork - Interior - Heavy clean (Per Register)EA$35.28
0137Clean ductwork - ExteriorLF$2.52
0138Clean all accesible AHU components & housingEA$135.00
0139Anti-microbial Agent ApplicationSF$0.16
0140Deodorizer ApplicationCF$0.05
0141Clean filters (est. 14x20)EA$5.00
0142Replace filters (est. 14x20)EA$22.00
0143Replace Registers (standard)EA$28.00
0144Clean coils, fan motors, and air handling housingEA$135.00
0145Remove & Replace Fiberglass duct wrap, 1 1/2" thickSF$4.01
0146Remove & Replace Fiberglass duct wrap, 2" thickSF$4.85
0147Remove & Replace - flexible - insulated 6" - roundLF$6.69
0148Remove & Replace - flexible - insulated 7" - roundLF$7.04
0149Remove & Replace - flexible - insulated 8" - roundLF$7.53
0150Remove & Replace - flexible - insulated 10" - roundLF$9.03
0151Remove & Replace - flexible - insulated 12" - roundLF$9.41

Turner Strategic

CONTRACT LINE ITEM NO. (CLIN)SUPPLIES/SERVICEQTYUNITUNIT PRICE ($)
0001NON-PERSONAL SERVICES: Provide all supervision, personnel, equipment, transportation, material, and other items and services necessary to perform Mold Remediation at Joint Base Langley Eustis (Ft. Eustis) for the period 5 years in accordance with the PWS.
MOLD REMEDIATION DESCRIPTION - SERVICES
0002Emergencey service call - after business hours1EA$173.84
0003Emergencey service call - during business hours1EA$115.89
0004Hazardous Waste/Mold Cleaning Technician - after hours1HR$86.03
0005Hazardous Waste/Mold - Labor Minimum1EA$143.26
0006Hazardous Waste/Mold Cleaning - Supervisor/Admin - after hours1HR$101.74
0007Hazardous Waste/Mold Cleaning - Supervisor/Admin1HR$67.75
0008Cleaning Remediation Supervisor/Administrative1HR$43.46
0009Cleaning Remediation Technician1HR$41.39
0010Soda Blasting1SF$1.63
0011Soda Blasting - Heavy1SF$1.97
0012Soda Blasting - Extra Heavy1SF$2.33
0013Dry Ice Blasting - Heavy1SF$3.06
0014Dry Ice Blasting - Extra Heavy1SF$3.71
0015Add on confined space blasting1SF$0.43
0016Apply anti-microbial agent1SF$0.17
0017Apply anti-microbial agent - after hours1SF$0.24
0018Apply anti-microbial agent - micromister1CF$0.04
0019Haul debris - per pickup truck load - including dump fees1EA$107.95
0020HEPA Vacuum1HR$60.43
0021Seal/coat {V} - one coats (anti-microbial coating)1SF$0.90
0022Sand exposed framing1SF$1.47
0023Ducting - lay flat - large1LF$0.29
0024Deordorize building - Hot thermal fog1CF$0.04
0025Deordorize chamber - Ozone1CF$0.06
0026Box and liner - used for hazardous waste cleanup - medium1EA$3.93
Content Cleaning
0027Clean and deodorize carpet1SF$0.28
0028Clean floors (all hard floors)1SF$0.41
0029Clean walls and ceiling1SF$0.21
0030Clean ceiling grids1SF$0.18
0031Sofa - Heavy cleaning1LF$26.81
0032Clean chairs1EA$53.90
0033Clean and deodorize mattress or box spring - full1EA$50.31
0034Clean tables - end tables1EA$6.87
0035Clean tables - coffee tables1EA$8.65
0036Clean tables - dining1EA$10.66
0037Clean bookcase contents1LF$5.06
0038Clean bookcase1SF$0.07
0039Clean desk contents1LF$4.95
0040Clean desk1EA$13.75
0041Clean computer printer - small (desk top) wipe down1EA$10.36
0042Clean computer CPU box - exterior wipe down1EA$7.89
0043Clean computer keyboard - exterior wipe down1EA$7.65
0044Clean computer monitor - exterior wipe down1EA$7.89
0045Clean footlockers (chest)1EA$13.37
Content Manipulation
0046Contents- manipulation - hourly charge1HR$23.04
0047Contents- manipulation - after hours hourly charge1HR$34.60
0048Block and pad furniture - hourly charge1HR$43.40
0049General Labor1HR$23.04
0050Inventory, Packing, Boxing, and Moving charge1HR$23.04
0051Move out then reset - large room1EA$45.50
0052Moving Van (17' - 20') and equipment1EA/DA$167.40
0053Off site storage &insurance - per month1SF$0.98
0054Off site storage &insurance - climate controlled - per month1SF$1.37
0055Protect contents - Cover with plastic1SF$0.18
0056Protect contents - Cover with plastic - after hours1SF$0.28
Equipment & Filters
0057Power distribution box1EA/DA$33.98
0058Thermal imaging1HR$43.46
0059Dehumidifier (per 24 hour period) - Xlarge - No monitoring1EA/DA$104.29
0060Dehumidifier (per 24 hour period) - Small - Desiccant - No monitoring1EA/DA$51.16
0061Dehumidifier (per 24 hour period) - Large - Desiccant- No monitoring1EA/DA$73.13
0062Air mover (per 24 hour period) - No monitoring1EA/DA$25.58
0063Air mover axial fan (per 24 hour period) - No monitoring1EA/DA$28.50
0064Vane axial fan 1hp air mover (per 24 hour period) - No monitoring1EA/DA$34.95
0065Wood floor drying-Inj. Type (per 24 hour period) - No monitoring1EA/DA$140.00
0066Hydrodoxal Generator1EA/DA$225.49
0067Neg. air fan/Air scrub-Large (per 24 hour period) - No monitoring1EA/DA$122.22
0068Neg. air fan/Air scrub-XLarge (per 24 hour period) - No monitoring1EA/DA$140.00
0069HEPA filters for neg. air1EA$185.87
0070Add for HEPA filter (for canisters/backpack vacuum)1EA$50.87
0071Equipment Setup/Take Down and Monitoring (Business Hours)1HR$41.39
0072Equipment Setup/Take Down and Monitoring (After Business Hours)1HR$62.15
0073Single axle dump truck - per load - including dumping fees1EA$234.98
0074Dumpster Load - 20 yard1EA$429.00
Heat Drying
0075Artic Cub - ind.fired heater w/ducting - 170 kBtuh1EA/DA$460.00
0076Thermal air mover - electric1DA$180.00
Decontamination
0078Equipment decontamination charge - per piece of equipment1EA$36.03
Extraction
0079Water extraction from floor1SF$0.43
0080Water extraction from floor - Heavy1SF$0.52
0081Water extraction from floor - Category 2 water (Gray water)1SF$0.67
0082Water extraction from floor - Category 3 water (Sewage)1SF$1.07
0083Water extraction from floor - Weight - assisted1SF$0.81
0084Lifted carpet for drying1SF$0.26
00852" Submersible pum with hose (per 24 hour period)1EA/DA$45.77
0086Portable extractor with hoses and flood tool1EA/DA$60.00
Containments
0087Containment Barrier/Airlock/Decon. Chamber1SF$0.55
0088Containment Barrier/Airlock/Decon. Chamber - after hours1SF$0.78
0089Containment Barrier - tension post - per day1EA/DA$3.30
0090Peel & seal zipper1EA$12.06
Perpsonal Protective Equipment
0091Eye protection - plastic goggles- Disposable1EA$6.19
0092Respirator replacement cartridge (per pair)1EA$11.94
0093Respirator1EA$7.61
0094Gloves1EA$0.34
0095Add for personal protective equipment (hazardous cleanup)1EA$8.41
Demo
0096Baseboard - detach1LF$0.75
0097Tear out trim/base1LF$0.61
0098Add-on for tearing out trim/base from tile/grout1LF$0.32
0099Tear out wet drywall, cleanup, bag for disposal - up to 2' tall1LF$2.26
0100Tear out wet non-salvageable carpet, cut & bag for disposal1SF$0.37
0101Tear out wet non-salvageable carpet, cut & bag - Category 3 water1SF$0.52
0102Tear out wet carpet pad and bag for disposal1SF$0.36
0103Tear out wet carpet pad and bag - Category 3 water1SF$0.48
0104Tear out tackless strip and bag for disposal1LF$0.60
0105Tear out non-salvageable vinyle & underlay, cut and bag for disposal1SF$0.84
0106Tear out non-salvageable underlayment & bag for disposal1SF$0.94
0107Tear out non-salvageable Laminate floor and bag for disposal1SF$1.10
0108Tear out non-salvageble Laminate floor and bag - Category 3 water1SF$1.59
0109Tear out and bag wet insulation1SF$0.49
0110Tear out and bag wet insulation in crawl space1SF$0.92
0111Remove unsalvageble pipe insulation1LF$0.61
0112Remove unsalvageable ceiling tiles1SF$0.72
0113Drill holes for wall cavity drying1EA$0.36
0115General Demolition1HR$30.11
Material Only
0116Barricade 6 mil adhesive ply1RL$19.93
0117Fiberlock IAQ 6000 1 gal1EA$70.92
0118Fiberlock IAQ 6000 5 gal1EA$354.63
0119Foam for pressure containment1RL9.46
0120Poly hangers1BX331.25
0121Sticky Mat1RL$80.00
0122Caution Tape1SF$0.06
0123Provide box , packing paper, & tape - medium size1EA$3.17
0124Provide stretch film/wrap1RL$14.99
0125Provide bubble wrap - add on cost for fragile items1LF$0.19
0126Provide furniture lightweight blanket/pad1EA$5.54
0127Plastic Bag - used for disposal of contaminated items1EA$2.80
0128Ceiling tile - 2" X 2"1SF$1.39
HVAC SYSTEM MOLD REMEDIATION DESCRIPTION
0129On-site Evaluation and/or Supervisor/Administrator1HR$43.46
0130Cleaning Remediation Supervisor/Administrative1HR$43.46
0131Cleaning Remediation Technician1HR$41.39
0132HVAC Technicain1HR$97.05
0133Furnace - check, clean replace filters and service1EA$120.37
0134Furnace-check, heavy clean replace filters and service1EA$188.85
0135Clean ductwork - Interior (Per Register)1EA$27.08
0136Clean ductwork - Interior - Heavy clean (Per Register)1EA$35.10
0137Clean ductwork - Exterior1LF$2.42
0138Clean all accesible AHU components & housing1EA$24.89
0139Anti-microbial Agent Application1SF$0.17
0140Deodorizer Application1CF$0.04
0141Clean filters1EA$5.75
0142Replace filters Labor only1EA$2.75
0143Replace Registers1EA$15.59
0144Clean coils, fan motors, and air handling housing1EA$35.08
0145Remove & Replace Fiberglass duct wrap, 1 1/2" thick1SF$0.23
0146Remove & Replace Fiberglass duct wrap, 2" thick1SF$0.23
0147Remove & Replace - flexible - insulated 6" - round1LF$0.46
0148Remove & Replace - flexible - insulated 7" - round1LF$0.46
0149Remove & Replace - flexible - insulated 8" - round1LF$0.46
0150Remove & Replace - flexible - insulated 10" - round1LF$0.46
0151Remove & Replace - flexible - insulated 12" - round1LF$0.46

File details come from the government source that posted it. Updated .