Attachment_8_-_Special_Contract_Requirements.pdf

PDF 78 KB Posted

Attached to
Runway Rubber Removal & Repainting Federal contract opportunity
Solicitation number
FA4608-15-R-0045
Issued by
Department of the Air Force Global Strike Command

About this file

Special Contract Requirements

View the file

Other files for this federal contract opportunity

Other files attached to Runway Rubber Removal & Repainting, newest first.
File Type Posted
Attendance_Sheet.pdf PDF
Attachment_7_-_Wage_Determination.pdf PDF
Attachment_6_-_Contractor_Insurance.pdf PDF
FA4608-15-R-0045_Runway_Rubber_Removal_Solicitation.pdf PDF
Attachment_1_-_Specifications_04-2.pdf PDF
Attachment_5_-_AF66.pdf PDF
Attachment_4_-_Environmental_Req'ts_(Oct_14).pdf PDF
Attachment_3_-_North_ _South_Runway_Diagram.pdf PDF
Attachment_2_-_Specifications_97-17.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA4608-15-R-0045

Attachment 8

Special Contract Requirements

H-001 REQUIRED INSURANCE - Addendum

(IAW FAR 28.306(b) and FAR 52.228-5)

Reference FAR clause entitled "Insurance..." the Contractor shall, at its own expense, procure and thereafter maintain the following kinds of insurance with respect to performance under the contract.

a. Workmen’s Compensation and Employers Liability Insurance as required by law except that if this contract is to be performed in a State which does not require or permit private insurance, then compliance with the statutory or administrative requirements in any such State will be satisfactory. The required Workmen's

Compensation insurance shall extend to cover employer's liability for accidental bodily injury or death and for occupational disease with a minimum liability limit of $100,000.

b. General Liability Insurance. Bodily injury liability insurance, in the minimum limits of $500,000 per occurrence shall be required on the comprehensive form of policy.

c. Automobile Liability Insurance. This insurance shall be required on the comprehensive form of policy and shall provide bodily injury liability and property damage liability covering the operation of all automobiles used in connection with the performance of the contract. At least the minimum limits of $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage shall be required.

H-002 ENVIRONMENTAL MANAGEMENT SYSTEM (EMS) AWARENESS TRAINING

The contractor is required to complete EMS Awareness Training in accordance with Attachment 4, Environmental

Requirements for Contractors Working on Barksdale Air Force Base. The training will be provided in the form of a power point presentation provided by the Contracting Office. The contractor must submit the Certificate of

Completion to the Contracting Officer prior to receiving the Notice to Proceed for this contract.

H-003 BOSSIER CITY -- PARISH SALES AND USE TAX

Bossier City and Bossier Parish levy a use tax defined by state and local sales tax law. As such, these sales are taxable at the point of delivery to the "contractor" (consumer). If the sales or use tax is not collected by the vendor, tax is payable directly to the jurisdiction in which delivery is made. Contractors and subcontractors are each individually liable for sales and use tax on the basis of their individual purchase transactions. This tax may extend to equipment leased or rented to the Government. It may also extend to supplies and equipment purchased elsewhere, but brought into Bossier Parish for final use. All contractors are cautioned to assure themselves of any liability for this tax. The local telephone number for questions concerning this tax is A/C 318 741-8551.

H-004 CONTRACTOR/VENDOR ACCESS TO BARKSDALE AFB

All commercial vehicles are required to enter Barksdale AFB through the East Gate, just off I-20 and Industrial

Drive. This includes construction, food, supply, FedEX, and UPS deliveries, as well as contractors entering with company trucks. Contractors entering in their privately owned vehicles with an approved pass will be allowed entry at any gate. Hours of operation for the East Gate are 0500-2200 Monday through Friday, Saturday 0600-1200.