Attachment_7_Questions_and_Answers_Small_Paving.docx

DOCX document 19 KB Posted

Attached to
Small Paving Projects Federal contract opportunity
Solicitation number
FA4528-17-R-0024
Issued by
Department of the Air Force Global Strike Command

About this file

Q & A

View the file

Other files for this federal contract opportunity

Other files attached to Small Paving Projects, newest first.
File Type Posted
FA4528-17-R-0024_Amendment_2.pdf PDF
Attachment_2_Revised_Project_848_Specs.pdf PDF
Attachment_1_Revised_PA0761_Specs.pdf PDF
Attachment_6_-_PA0761_Maps.pdf PDF
FA4528-17-R-0024_Amendment_0001.pdf PDF
Attachment_4_-_PA0848_Maps.pdf PDF
Attachment_1_-_PA0120_Specs.pdf PDF
FA4528-17-R-0024.pdf PDF
Attachment_2_-_PA0761_Specs.pdf PDF
Attachment_6_-_Financial_Responsibility.docx DOCX document
Attachment_3_-_PA0848_Specs.pdf PDF
Attachment_5_-_Past_Performance_Information_Form.docx DOCX document
Attachment_7_-_Wage_Determination.pdf PDF
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pre-Proposal Offeror Questions and Government Responses Small Paving Questions

FA4528-17-R-0024

3 August 2017

1. Q: Please clarify whether or not bid bonds are required.

A: Bid bonds not required.

2. Q: Please clarify whether or not Past Performance information is required.

A: Evaluation will be made based on price.

3. Q: Please clarify whether or not storm drains and concrete curb & gutter are included in the scope of work.

A: Storm drains and concrete curb and gutter sections are to remain as is. They are not part of the scope of work.

4. Q: Is prime coat required?

A: Prime coat will be the option of the contractor. It is not required.

5. Q: Spec. section 32 11 13 / 3.5.7 - Proof Rolling seems to have a typo regarding the vehicle size to be used. Please clarify.

A: Since it is not an airfield pavement, any size vehicle may be used as long as it can provide the results stated in the specifications.

6. Q: Is pavement marking included in the scope of work?

A: Pavement marking is not included in the scope of work.

7. Q: Please provide a plan and clarify the depth and extent of pavement removal and replacement at Building 761.

A: Asphalt and base course will be removed to a depth of 3 inches below existing grade for the project at Building 761. Asphalt and base course will be removed to a depth of 2 inches below existing grade for the project at building 848.

8. Q: Please clarify scope of work, particularly full depth repair, patching and sealing.

A: Removed asphalt and base course will be replaced with 3 inches of Hot-mix asphalt at building 761. Removed asphalt and base course will be replaced with 2 inches of Hot-Mix asphalt at building 848. Exposed base course will need to be compacted to the requirements of the specifications at both sites.

9. Q: Please clarify the purpose of Attachment 1 - PA0120 Specs.

A: The project for 120 is no longer part of this contract.

10. Q: Please clarify the performance period. The solicitation shows both 90 and 120 days in sections 10 and 11 and also in section F.

A: The performance period shall be 120 days.

11. Q: Will this project require a CPM schedule?

A: Yes this project will require a CPM schedule.