Attachment_7_Questions_and_Answers_Small_Paving.docx
DOCX document 19 KB Posted
- Attached to
- Small Paving Projects Federal contract opportunity
- Solicitation number
- FA4528-17-R-0024
About this file
Q & A
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA4528-17-R-0024_Amendment_2.pdf | ||
| Attachment_2_Revised_Project_848_Specs.pdf | ||
| Attachment_1_Revised_PA0761_Specs.pdf | ||
| Attachment_6_-_PA0761_Maps.pdf | ||
| FA4528-17-R-0024_Amendment_0001.pdf | ||
| Attachment_4_-_PA0848_Maps.pdf | ||
| Attachment_1_-_PA0120_Specs.pdf | ||
| FA4528-17-R-0024.pdf | ||
| Attachment_2_-_PA0761_Specs.pdf | ||
| Attachment_6_-_Financial_Responsibility.docx | DOCX document | |
| Attachment_3_-_PA0848_Specs.pdf | ||
| Attachment_5_-_Past_Performance_Information_Form.docx | DOCX document | |
| Attachment_7_-_Wage_Determination.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pre-Proposal Offeror Questions and Government Responses Small Paving Questions
FA4528-17-R-0024
3 August 2017
1. Q: Please clarify whether or not bid bonds are required.
A: Bid bonds not required.
2. Q: Please clarify whether or not Past Performance information is required.
A: Evaluation will be made based on price.
3. Q: Please clarify whether or not storm drains and concrete curb & gutter are included in the scope of work.
A: Storm drains and concrete curb and gutter sections are to remain as is. They are not part of the scope of work.
4. Q: Is prime coat required?
A: Prime coat will be the option of the contractor. It is not required.
5. Q: Spec. section 32 11 13 / 3.5.7 - Proof Rolling seems to have a typo regarding the vehicle size to be used. Please clarify.
A: Since it is not an airfield pavement, any size vehicle may be used as long as it can provide the results stated in the specifications.
6. Q: Is pavement marking included in the scope of work?
A: Pavement marking is not included in the scope of work.
7. Q: Please provide a plan and clarify the depth and extent of pavement removal and replacement at Building 761.
A: Asphalt and base course will be removed to a depth of 3 inches below existing grade for the project at Building 761. Asphalt and base course will be removed to a depth of 2 inches below existing grade for the project at building 848.
8. Q: Please clarify scope of work, particularly full depth repair, patching and sealing.
A: Removed asphalt and base course will be replaced with 3 inches of Hot-mix asphalt at building 761. Removed asphalt and base course will be replaced with 2 inches of Hot-Mix asphalt at building 848. Exposed base course will need to be compacted to the requirements of the specifications at both sites.
9. Q: Please clarify the purpose of Attachment 1 - PA0120 Specs.
A: The project for 120 is no longer part of this contract.
10. Q: Please clarify the performance period. The solicitation shows both 90 and 120 days in sections 10 and 11 and also in section F.
A: The performance period shall be 120 days.
11. Q: Will this project require a CPM schedule?
A: Yes this project will require a CPM schedule.