Performance Work Statement Revised 16 Dec 14 Hoods and Ducts Cleaning/Inspection Service
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment_3_-_Offeror_Pricing_Schedule_Rev_17_Dec_14.pdf | ||
| Attachment_3_-_Offeror_Pricing_Schedule_Rev_17_Dec_14.pdf | ||
| Questions_ _Answers_Hoods Ducts2.docx | DOCX document | |
| Questions_ _Answers_Hoods Ducts.docx | DOCX document | |
| Revised_Attachment_1_-_PWS.pdf | ||
| Attachment_5_-_Wage_Determination.pdf | ||
| Revised_Attachment_3_-_Offeror_Pricing_Schedule.pdf | ||
| Attachment_4_-_Responsibility_Questionnaire.pdf | ||
| Attachment_1_-_PWS.pdf | ||
| Attachment_3_-_Offeror_Pricing_Schedule.pdf | ||
| Attachment_2_-_QASP.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA4528-15-RFQ-F3C3PC4288AW01
Attachment 1
PERFORMANCE WORK STATEMENT
INSPECT, CLEAN and DEGREASE KITCHEN EQUIPMENT
(EXHAUST HOODS and DUCTS)
1. DESCRIPTION of SERVICES: Furnish all plant, labor, material, and equipment for the inspection, cleaning, and degreasing exhaust hoods, ducts and filters within dampers, exhaust fans, exterior power roof ventilators and roof louvers or vents and to clean all grease that may have accumulated on the roof, penthouse and exterior walls at various locations on Minot AFB and 15 Missile Alert Facilities as stated in this Performance Work Statement (PWS).
1.1 All grease and foreign matter shall be removed from the interior and exterior of hoods, ducts, and roofs, penthouses and exterior walls to a clean, safe, sanitary condition. De-greasing and cleaning agents shall be a biodegradable type, and must be of a non-combustible type recommended for use in food service facilities.
Contractor shall provide sample and manufacturer’s brochure/literature along with Material Safety Data Sheet (MSDS). All work must comply with the most current version of National Fire Protection Association Standard 96.
At the start of the cleaning process, electrical switches that could be activated accidentally shall be locked out. Fire-extinguishing systems shall be permitted to be rendered inoperable during the cleaning process where serviced by properly trained and qualified persons.
1.1.1 The Contractor shall perform all operations in such a manner as to preclude damage to surrounding surfaces and equipment and shall leave surrounding premises in an “as found” condition. Any inoperative or deteriorated fans, louvers, dampers, power roof ventilators, ducts or associated equipment shall be reported the same day in writing to 5CES Fire Emergency Services Flight (COR). If any or all parts of the exhaust system are disassembled or moved during the cleaning operation, they shall be reassembled and replaced in the condition they were found.
Flammable solvents or other flammable cleaning aids shall not be used. Cleaning chemicals shall not be applied on fusible links or other detection devices of the automatic extinguishing system.
1.1.2 Post Cleaning: After the exhaust system is cleaned; it shall not be coated with powder or other substance.
When cleaning procedures are completed, all access panels (doors) and cover plates shall be restored to their normal operational condition. When an access panel is removed, a service company label or tag pre-printed with the name of the company and giving the date of inspection or cleaning shall be affixed near the affected access panels.
Dampers and diffusers shall be positioned for proper airflow.
When cleaning procedures are completed, all electrical switches and system components shall be returned to an operable state. In the event that weather delays cause the exterior portion to be cleaned after the interior, it shall be expected that some residue will be built up at the interior of the hood that will not require added interior cleaning.
1.1.2.1 Prior to completion at each facility, contact the Fire Department COR for an inspection at (701) 723-2461, 723-2462, or 723-2463. The contractor shall remain on site until the Fire Dept. representative has completed the inspection. For MAF’s, a representative will already be on site to inspect.
1.1.2.2 In all locations, cleaning shall be interior and exterior at all times.
1.2 Reports and Documentation: Prior to completion at each facility, contact the 5 CES Fire Emergency Services Flight for an inspection at (701) 723-2461, 723-2462, or 723-2463 to inspect and verify the work conducted. Have the COR sign a verification form documenting the cleaning and the date the work was accomplished. Verification forms will be provided by 5 CES Fire Emergency Services Flight. The contractor must attach the verification forms in the payment system, Wide Area Work Flow (WAWF), before any payment will be made by the Government. A certificate showing the name of the servicing company, the name of the person performing the work, and the date of inspection or cleaning shall be maintained on the premises.
1.2.1 A written report shall be provided to the on-site Facility Manager or government representative that also specifies areas that were inaccessible or not cleaned.
1.3 Inspection and Maintenance of Fire Extinguishing Systems Per NFPA 96 – Key Areas Repeated Below:
1.3.1 Inspection and Maintenance of the fire-extinguishing systems and listed exhaust hoods containing a constant or fire-activated water system that is listed to extinguish a fire in the grease removal devices, hood exhaust plenums, and exhaust ducts shall be made by properly trained, qualified, and certified person(s) acceptable to the authority having jurisdiction at least every 6 months.
1.3.1.1 Certification means by manufacturer(s) of fire-extinguishing systems and extends to actual person(s) who perform inspections and maintenance. More than one manufacturer is listed, so that Ansul, Kidde, and Pyro Chem certifications are all required. Proof of current certification must be provided prior to start of work.
1.3.2 All actuation components, including remote manual pull stations, mechanical or electrical devices, detectors, and actuators, shall be checked for proper operation during the inspection in accordance with the manufacturer’s listed procedures.
1.3.3 The specific inspection and maintenance requirements of the extinguishing system standards as well as the applicable listed installation and maintenance manuals and service bulletins shall be followed.
1.3.4 Fusible links and automatic sprinkler heads shall be replaced at least semi-annually or more frequently if necessary where required by the manufacturer.
1.3.5 The year of manufacture and the date of installation of the fusible links shall be marked on the system inspection tag. The tag shall be signed or initialed by the installer.
1.3.6 Detection devices other than fusible links and automatic sprinklers shall be serviced or replaced in accordance with the manufacturer’s recommendations.
1.3.7 Where automatic bulb-type sprinklers or spray nozzles are used and annual examination shows no buildup of grease or other material on the sprinkler or spray nozzles, annual replacement shall not be required.
1.3.8 Where required, certificates of inspection and maintenance shall be forwarded to the authority having jurisdiction.
1.4 Inspection of Fire Dampers.
1.4.1 Actuation components for fire dampers shall be inspected for proper operation in accordance with the manufacturer's listed procedures.
1.5 Replacement of Fusible Links.
1.5.1 Fusible links on fire damper assemblies shall be replaced at least semiannually or more frequently as necessary. Replacement shall be made by a certified person acceptable to the authority having jurisdiction.
1.6 Documentation Tag.
1.6.1 The year of manufacture and the date of installation of the fusible links shall be documented.
1.6.2 The tag shall be signed or initialed by the installer.
1.7 The cost of the above mentioned replacement parts/assemblies and labor is to be included in the price offered by the contractor and will not be invoiced separately.
2. SERVICES SUMMARY: The contract service requirements are summarized in performance objectives below.
The performance threshold briefly describes the minimally acceptable levels of service required for each performance objective. The Services Summary (SS) provides information on contract requirements, the expected level of Contractor performance, and the expected method of government surveillance and confirmation of services provided. These thresholds are critical to mission success. Procedures as set forth in the FAR 52.212-4 (a), Contract Terms and Conditions - Commercial Items, Inspection/Acceptance, will be used to remedy all deficiencies.
Performance Objective PWS Para
Performance Threshold
Remedy Method of Assessment
SS-1
Clean/de-grease interior and exterior of the following to a clean, safe, sanitary condition
a. Hoods
b. Ducts
c. Roofs
d. Penthouses
e. Exterior Walls
1.1, inclusive
Zero Defects Re-performance within 8 hours of notification
100% Surveillance
SS-2
Inspection and Maintenance of the fire-extinguishing systems and listed exhaust hoods
1.3, inclusive
Zero Defects Re-performance within 8 hours of notification
100% Surveillance
2.1 QUALITY CONTROL: The Contractor shall provide a written description of the quality control system to include identification of the commercial practices and procedures to be used as well as the MSDSs of associated materials proposed for use and a waste disposal plan. Include the inspection system requirements of FAR 52.246-4 in this document. The Contractor shall develop and implement procedures to identify, prevent, and ensure non-performance and continual repeat of defective service does not occur. A written Quality Control Plan shall be submitted to the Contracting Officer and the 5 CES Environmental Management Office for review, feedback, and approval. The plan shall be submitted no later than 10 days after award. The plan shall specifically address the Contractor’s strategy to provide quality workmanship, continual process improvement, and for correcting deficiencies as required.
2.2 QUALITY ASSURANCE: The Government shall inspect and evaluate the Contractor’s performance to ensure services are received in accordance with requirements set forth in this contract. The COR shall inspect by watching actual task performance, physically checking an attribute of the completed task, investigating customer complaints, conferring with facility managers, or otherwise inspecting the task or its results to determine whether or not performance meets the standards contained in this PWS. The COR will record surveillance results. Results of the surveillance then become the official Air Force record of the Contractor’s performance. When a performance threshold has not been met or Contractor performance has not been accomplished, the COR will initiate and provide the Contracting Officer a Contract Discrepancy Report (CDR), for issuance to the Contractor. The
Contractor shall respond to the CDR IAW instructions provided and return it to the Contracting Officer within 10 calendar days of receipt.
2.3 PERFORMANCE ASSESSMENT
2.3.1 Periodic Validations. This method requires the COR to employ a “spot check” style of evaluation based on the Contractor’s schedule. Periodic surveillances will be conducted on a scheduled basis (daily, weekly, monthly, quarterly, semi-annual or annually) and may be adjusted, based on quality trends.
Any unsatisfactory inspection (defect) result shall be recorded, and the Contractor shall re-perform the service within 24 hours after notification by the COR.
Failing to meet the performance threshold as outlined in the SS for any of these performance objectives in any 1-month period shall result in a warning or letter of concern from the Contracting Officer. Failing to meet the performance threshold as outlined in the SS of these performance objectives, in any combination for any two or more consecutive or non-consecutive months during a contract period, shall constitute an immediate Progress Meeting with the Multi-functional Team. All remedies shall be in accordance with the FAR 52.212-4 (a), Contract Terms and Conditions - Commercial Items, Inspection/Acceptance.
2.4 PERIODIC PROGRESS MEETINGS: The CO, COR, COR Supervisor, other Government personnel as appropriate, and the Contractor may meet to discuss the Contractor’s performance if there are on-going issues. A progress meeting will only be held if needed. The following issues may be discussed: opportunities to improve the contract, any modifications required of the contract, unsatisfactory inspections and trends against each performance objective observed, and positive performance and steps taken by the Contractor to prevent unsatisfactory occurrences in the future. The Contractor shall provide a summation of unsatisfactory inspections and customer complaints and provide insight into any identified trends.
The minutes of these meetings will be reduced to writing, signed by the Contracting Officer and any other signatures as deemed appropriate, distributed to the functional area and the Contractor. Should the Contractor not concur with the minutes, the Contractor shall provide a written notification to the Contracting Office identifying areas of non-concurrence for resolution.
3. CONTRACTOR PERSONNEL:
3.1 The Contractor shall provide a Contract Manager who shall be responsible for the performance of the work.
The name of this person, and an alternate or alternates, who shall act for the Contractor when the Manager is absent, shall be designated in writing to the Contracting Officer. The project manager shall be responsible for management and coordination of the work and shall be the point of contact with government representatives. The Contract Manager or alternate shall have full authority to act for the Contractor on all contract matters relating to daily operation of this contract.
3.1.1 The project manager and designated representative(s) must be able to read, write, speak, and understand English.
3.2 Contractor Identification. Contractor Personnel shall present a neat appearance and be easily recognized as Contractor employees. Each contractor employee shall wear an identifying badge, which shall be contractor furnished. The contractor is also responsible for providing employees with any identifiable uniform clothing such as shirts, overalls, hats etc., with the company name identified. Tank tops, cut off shirts, and or shorts are not permissible uniforms.
3.2.1 Control of Contractor Employees. Assignment, transfer, and reassignment of contractor personnel will be the prerogative of the contractor. The contractor shall be responsible for employees in performance of this Work
Statement and shall comply with the general intent and specific policies set forth in regulations of Minot AFB concerning conduct of employees as referenced herein. The government is not responsible for any contract employee misconduct.
3.2.1.1 The Contracting Officer may restrict the employment under the contract of any contractor employee, or prospective contract employee who is identified as a potential threat to the health, safety, security, general wellbeing or operational mission of the installation and its population.
3.3 The Contract Manager or alternate shall be available during normal duty hours (0730-1730) within 60 minutes to meet, on the installation, with Government Personnel (designated by the Contracting Officer) to discuss problem areas. After normal duty hours, the Manager or alternate shall be available within 2 hours.
4. SECURITY:
4.1 CONTRACTOR SECURITY REQUIREMENT for Missile Alert Facilities. The contractor is required to comply with all security regulations and directives as identified herein pertaining to entry and site regulations into the Missile Alert Facilities.
4.1.1 ENTRY AND SITE REGULATIONS: In order to gain entry onto a facility, contractor personnel must be listed on an Entry Authorization List (EAL), authorized by Government representatives.
4.1.1.1 Twenty (20) working days prior to the initial commencement of work, the contractor must submit to the contracting officer a list showing the full name (EXACTLY as it appears on the ID), birth date, Social Security Number (SSN), and a credentialed ID for each employee being utilized for on-site work (must include a photo). The following are acceptable: passport, state issued driver’s license, state issued photo identification, or Base ID. The contractor must include with the EAL submittal a photo copy of both sides of the photo ID to be used. In addition, the following vehicle information is required: make, model, year, primary color, and license plate number (State and number – if no plate equipment, serial number). This list will be used to prepare the EAL referenced above.
Deletions to the EAL may be made without preparing a new list but it must be requested by the contractor in writing. However, a new list must be submitted by the contractor for any addition to the EAL. All requested changes in writing to an approved list submitted between the 1st and 15th of the month inclusive shall be in place by the end of that month. All requested changes in writing to an approved list submitted between the 16th and end of the month inclusive shall be in place by the 15th of the following month.
4.1.1.2 Upon arrival at the MAF, Contractor personnel will contact the Flight Security Controller (FSC) using the gate intercom telephone and inform the FSC of their presence at the security gate. Contractor personnel must remain outside of the MAF security fence and in or near their vehicle until the arrival of the Government Escort Official..
4.1.1.3 Upon arrival, the Government representative will identify and search all Contractor personnel. All Contractor personnel will provide the escort with their ID as listed above stating the employees full name. The ID will be the same as was used to generate the EAL. The contractors’ vehicles will be checked and possibly searched prior to site entry. Contractor vehicles shall be clearly marked identifying each contracting firm.
4.1.1.4 If contractor personnel are not listed on the EAL, or those who are listed cannot provide proper identification, they will not be permitted on the site. Delays caused by lack of proper EAL data or proper ID will be at no cost to the government.
4.1.1.5 The work to be performed is in a restricted area. Therefore the contractor shall conform to all requirements of MAFBI 31-101, Restricted Area Entry and Circulation Control Procedures. The using agency will provide an escort for the contractor. The contractor should expect and prepare for security delays when accessing restricted areas. Contractor will not be reimbursed for security delays.
4.1.1.6 Contract Personnel who violate federal laws or regulation may be barred from the installation at the discretion of the Installation Commander. In such cases, the Contractor is responsible for providing adequate manning at all times, regardless of one or more personnel being barred.
4.2 The Contractor shall:
4.2 Protect all Government property.
4.2.1 Comply with physical security regulations and procedures.
4.2.1.1 While work is in progress, the Contractor may be required to remove his personnel due to Alert status, real or exercise.
4.2.1.2 During all on-site work, the Contractor personnel will be monitored by one (1) Government representative.
Failure to remain within the area being monitored is a serious breach of security and safety regulations. The Contractor will take all necessary action to ensure compliance. The Contracting Officer reserves the right to deny entry to/or take action with any Contractor personnel who refuses to conform to security and/or safety regulations.
Delays resulting from such entry denial shall not result in any cost to the Government or schedule delay.
5. GOVERNMENT-FURNISHED PROPERTY AND SERVICES: Except where restricted in these specifications in other sections for certain tasks, all reasonable quantities of utilities shall be made available to the Contractor. No temporary connections will be permitted, which may be of a semi-permanent nature. All connections shall be made by plugging into existing receptacles while work is in progress for electrical service. All extension cords must be GFI protected. All electrical cords shall be unplugged at the end of each work period.
5.1 Utilities: The Contractor shall adhere to all base level utility conservation practices or requirements. The Contractor shall be responsible for operating under conditions that prevent waste of utilities. The contractor shall conform to the provisions of AFI 31-209, the Resources Protection Program, for safeguarding any government facilities that the contractor will be performing work in.
5.1.1 Equipment and Property Damage. The contractor shall exercise due care to avoid damaging utilities, buildings, or the structures, and government or privately owned vehicles and equipment. The contractor shall report any incidents of theft, vandalism, or damage to contractor, government, or privately owned equipment, vehicles, material, or other property to the security forces and the government representative on the same day of discovery.
Government or private property damaged or destroyed by the contractor shall be repaired or replaced at no expense to the government.
5.2 Security, Fire, and Medical Services: The Government will provide police and fire protection. In the event of a medical emergency, base ambulance service for transporting an injured employee to a local hospital is available on a cost reimbursement basis.
6. ENVIRONMENTAL:
6.1 MSDS. MSDSs, proposed container sizes and rates of use must be submitted to the 5 CES Environmental Management Office (via the COR) for review and approval at least 15 duty days prior to any materials being brought onto any portion of the installation. The Contractor is required to have and maintain Material Safety Data Sheets (MSDSs) on all materials that are used. The contractor is responsible for training his employees to properly use any authorized hazardous materials and properly handle hazardous wastes. A monthly chemical usage report will be submitted to the CES Environmental Management Office (via the COR) that lists the amount of materials (with associated MSDSs) used and locations of usage. After completion of the project, a final total chemical usage report will be submitted to the CES Environmental Management Office (via the COR) that lists the amount of materials (with associated MSDSs) used and locations of usage.
6.2 All contractor-generated wastes will be removed from the installation the same day it is generated and disposed of off base by the contractor. All waste characterization and proper disposal is the responsibility of the contractor.
This shall be done in a manner to conform to the State of North Dakota Health and Sanitation Codes. In no manner will the Government be responsible for disposals.
6.3 Contractor shall be knowledgeable of and comply with all applicable Federal, State and local regulations and requirements regarding environmental protection.
6.4 The Contractor is solely responsible for compliance with OSHA standards for the protection of their employees.
The Contract Manager shall ensure specific safety requirements in Air Force Occupational Safety and Health (AFOSH) standards are complied with by Contractor Personnel when non-compliance would clearly present the potential to harm or damage government resources. The Air Force is not responsible for ensuring that Contractors comply with “personal” safety requirements that do not present the potential to damage government resources.
7.0 PAYMENT: All payments will be based according to the item cost identified in the bid schedule. All payments will be made upon completion of the interior and exterior cleaning required for each facility’s hood or for the completion of the fire safety check for each facility’s hood. See scheduling for interruptions in work.
8.0 SCHEDULING: Cleaning will be accomplished according to the frequency identified in Attachment 2, Offeror Schedule. The contractor shall contact and schedule a specific date & time for Off Base MAFs and all On Base Government and Private Vendor kitchen hood grease cleaning and hood fire extinguisher system inspections with the MAFB fire Inspector 5 CES/CEF (COR) to accomplish the cleaning and the fire safety check.
8.1 The contractor shall Schedule all work at least 15 days in advance and submit the date & time schedule to 5 CES/CEF Asst Fire Chief (COR).
8.1.1 Note: If weather conditions do not permit exterior cleaning, work will be re-scheduled by Contractor with agreement of 5 CES/CEF Fire Emergency Services within 24 hours to a new date no more than 14 days from the original date. Upon completion of the interior and exterior portions of the work and verification by Fire Inspector from 5 CES/CEF (COR), payment as referenced above can be made.
8.2 Hours of Operation: The hours of operation for each facility will be scheduled through the COR.
8.3 Mission Essential: This contract is not considered mission essential and the contractor’s absence during emergencies or contingencies will not hinder the Minot AFB mission.
9.0 RECORDS MANAGEMENT:
All records, files, documents, regardless of media (e.g., paper, electronic, etc.), as described in the PWS, that are the responsibility of the contractor are the property of the Government and shall remain so upon termination or completion of the contract. The contractor shall keep these items current and maintain and dispose of them in accordance with the requirements established in Air Force Instruction (AFI) 33-322, Records Management Program, Air Force Manual (AFMAN) 33-363, paragraph 6.4, Air Force Manual (AFMAN) 33-364, paragraph 2.13, and the Air Force Records Disposition Schedule which can be provided by the COR or CO upon request. Records shall be turned over to the Government upon completion of the contract unless otherwise stated. All records are subject to the Freedom of Information and Privacy Act.
The Minot AFB Records Management Office (5 CS/SCXR), 723-3529/3186, will provide assistance and training to the contractor to ensure compliance with Federal record keeping requirements.
10. CONTRACT MANPOWER REPORTING:
10.1 The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for the hoods & ducts maintenance & inspection services via a secure data collection site. The contractor is required to completely fill in all required data fields at http://www.ecmra.mil.
10.2 Reporting inputs will be for the labor executed during the period of performance for each Government fiscal year (FY), which runs 1 October through 30 September. While inputs may be reported any time during the FY, all data shall be reported no later than 31 October of each calendar year. Contractors may direct questions to the CMRA help desk.
APPENDIX 1
MILEAGE TO 15 INDIVIDUAL MISSILE ALERT FACILITIES
TO FROM MINOT AFB FROM CITY OF
MINOT
A-1 2 miles west of Belfour on 52 57 Miles 46 Miles
B-1 10 miles south of Velva on 41 49 Miles 35 Miles
C-1 7 miles south of Ruso on 41 and 5 miles west on County Rd. 6 69 Miles 58
Miles
D-1 2 miles south of Max on 83 48 Miles 34 Miles
E-1 2 miles north of Emmet on 37 65 Miles 51 Miles
F-1 2 miles north of Ryder on 28 54 Miles 40
Miles
G-1 6 miles north of Plaza on County 3 78 Miles 65 Miles
H-1 4 miles west of Parshall on 23 81 Miles 67 Miles
I-1 9 miles west of Palermo on Hwy 2 65 Miles 51 Miles
J-1 8 miles west of Berthold on Hwy 2 and 6 miles north on 5 54 Miles 45 Miles
K-1 6 miles west of Coulee on State Highway 50 48 Miles 62 Miles
L-1 1 mile south of Bowbells on State Highway 8 72 Miles 86 Miles
M-1 10 miles east of Kenmare on County Rd 2 62 Miles 62 Miles
N-1 5 miles west of Mohall on State Highway 5 41 Miles 55 Miles
O-1 4 miles north of Renville Corner on State Highway 256 32 Miles 46 Miles
Total 866 Miles 803 Miles
Average Trip is 53.5 miles one-way from City of Minot Average trip is 57.7 miles one-way from Minot AFB
APPENDIX 2
DUCT AND EXHAUST HOOD CLEANING VERIFICATION
SAMPLE FOR USE BY CONTRACTOR
This is to certify that all exhaust hoods and ducts were cleaned in:
Building __#270_Burger King_____ on this date and time__23 June, 2010 @2030 hrs__ and that no weather delays occurred requiring rescheduling and if so, that the above date is the date of completion of both interior and exterior portions of each hood and exhaust ducts cleaning work.
Contractor’s Name and Signature:
Fire Inspector 5 CES /CEF Name and Signature: Date:
COMMENTS:
APPENDIX 3
CLEANING & INSPECTION SCHEDULE
See tables below for cleaning and inspection breakout with regards to facility details and frequency.
Cleaning Breakout
Facility Frequency JR Rockers Bldg 292 (1 hood 7’x4’, duct 1.9’x1.9’x6’ and 1.4’x1.4’x6’ 1 hood
24.2’x4’, ducts (3) 1’x1’x8’) Monthly
Burger King Bldg 270 (1 hood, broiler unit; 1 hood, fryer unit and attached duct work)
Quarterly
Bowling Alley Bldg 140 (1 hood 3.33’x1.5’, duct 1’x.83’x7’) Quarterly
Main BX Food Court Bldg 248 (Anthonys’ Pizza) 1 hood 2.25’x5.5’x4’, duct 1’x5’ ;( Charley’s Steakery) 1 hood 2.25’x4’x4’, and duct 1’x 5’; (Taco Bell) 1 hood 8’ x 4’ x 4’; and duct 1’x 5’; (Popeye’s) 1 hood 8’x 3’x4’)
Quarterly
Jimmy Doolittle Center Bldg 174 (1 hood 8’x4’, duct 2’x2.5’x7’ 1 hood 5.2’x3’, duct 1.25’x 1.25’x7’)
Quarterly
Main Dining Facility Bldg 213 (1 hood 40’x12’, twin ducts 1’67’x2.5’x8’, 2 hoods 4.6’x 13.5’, ducts 2’x8’x8’, 2 hoods 4.7’x 3.1’, ducts 2’x8’x8’)
Quarterly
In-Flight Kitchen Bldg 846 (1 hood 19’x8’, plenum 19’x3.6’x2’) Quarterly
Roughrider's Pizza Bldg 202 (1 hood 7’x3’ and attached duct work above pizza oven, no Extinguisher system)
Quarterly
MAF Kitchen Trainer Bldg 695 (1 hood 6’x2’x1’, duct 16”x16”x10’) Semi-Annually
Youth Center Bldg 286 (1 Hood 1’x2’x3.5’ and attached duct work) Semi-Annually
Child Development Center Bldg 166 (5’x.5’x2.7’) Semi-Annually
Chapel #1 Bldg 155 (1 hood 7.5’x3.6’, duct 8’x.8’x16’, no Extinguisher system)
Annually
Chapel #2 Bldg 290 (1 hood 3’x2.5’, duct 1’x1’x25’ (in basement) 1 hood 2’x5’, duct 1’x1’x10’)
Annually
5 CES Kitchen Bldg 445 (1 hood 1’x2’x3.5’, duct 1.5’x2’) Annually
Alert Facility Kitchen Bldg 1085 (1 hood 4’x10.5’, twin duct 1.4’x1.4’x12’ (cooking line), 1 hood 4’x3’, duct 7”x9”x 12’ (serving line), . 1 hood 3’x3’, twin duct 1’x1’x12’ (over clipper)
Annually
Missile Alert Facilities (MAFs) 15
A-1 (1 hood 6’x2’x1’, duct 16”x16”x10’) Semi-Annually
B-1 (1 hood 6’x2’x1’, duct 16”x16”x10’) Semi-Annually
C-1 (1 hood 6’x2’x1’, duct 16”x16”x10’) Semi-Annually
D-1 (1 hood 6’x2’x1’, duct 16”x16”x10’) Semi-Annually
E-1 (1 hood 6’x2’x1’, duct 16”x16”x10’) Semi-Annually
F-1 (1 hood 6’x2’x1’, duct 16”x16”x10’) Semi-Annually
G-1 (1 hood 6’x2’x1’, duct 16”x16”x10’) Semi-Annually
H-1 (1 hood 6’x2’x1’, duct 16”x16”x10’) Semi-Annually
I-1 (1 hood 6’x2’x1’, duct 16”x16”x10’) Semi-Annually
J-1 (1 hood 6’x2’x1’, duct 16”x16”x10’) Semi-Annually
K-1 (1 hood 6’x2’x1’, duct 16”x16”x10’) Semi-Annually
L-1 (1 hood 6’x2’x1’, duct 16”x16”x10’) Semi-Annually
M-1 (1 hood 6’x2’x1’, duct 16”x16”x10’) Semi-Annually
N-1 (1 hood 6’x2’x1’, duct 16”x16”x10’) Semi-Annually
O-1 (1 hood 6’x2’x1’, duct 16”x16”x10’) Semi-Annually
Inspection Breakout
Facility Frequency JR Rockers Bldg 292 (Wet Chem Ansul Model R-102 2 locations in building) Semi-Annually
Burger King Bldg 270 (Wet Chem Ansul Model R-102 2 locations in building) Semi-Annually
Bowling Alley Bldg 140 (Wet Chem Pyro Chem Model PLC-240 1 location in building)
Semi-Annually
Main BX Food Court Bldg 248 (Wet Chem Ansul Model R-102 4 locations in building)
Semi-Annually
Jimmy Doolittle Center Bldg 174 (Dry Chem Kidde Sentinel Model HDR- 25DC 1 location in building)
Semi-Annually
Main Dining Facility Bldg 213 (Dry Chem Kidde Sentinel Model HDR-50DC 6 locations in building)
Semi-Annually
In-Flight Kitchen Bldg 846 (Dry Chem Kidde Sentinel Model HDR-25DC 1 location in building)
Semi-Annually
Youth Center Bldg 286 (Wet Chem Ansul Model R-102 1 location in building) Semi-Annually
Child Development Center Bldg 166 (Wet Chem Ansul Model R-102 1 location in building)
Semi-Annually
Chapel #2 Bldg 290 (Wet Chem Pyro Chem Model PLC-240 1 location in building)
Semi-Annually
5 CES Kitchen Bldg 445 (Wet Chem Ansul Model R-102 1 location in building)
Semi-Annually
Alert Facility Kitchen Bldg 1085 (Wet Chem Ansul Model R-102 1 location in building)
Semi-Annually
Wellness Center Bldg 455 (Wet Chem Ansul Model R-102 1 location in building)
Semi-Annually
Vehicle Maintenance Bldg 426 (Wet Chem Ansul Model R-102 4 locations in building)
Semi-Annually
HazMart Bldg 527 (Dry Chem Pyro Chem Model PC-50 1 location in building)
Semi-Annually
MAF Kitchen Trainer Bldg 695 (Dry Chem Pyro Chem Model PC-15 1 location in building)
Semi-Annually
Missile Alert Facilities (MAFs) 15
A-1 (Dry Chem Pyro Chem Model PC-15 1 location in each building) Semi-Annually
B-1 (Dry Chem Pyro Chem Model PC-15 1 location in each building) Semi-Annually
C-1 (Dry Chem Pyro Chem Model PC-15 1 location in each building) Semi-Annually
D-1 (Dry Chem Pyro Chem Model PC-15 1 location in each building) Semi-Annually
E-1 (Dry Chem Pyro Chem Model PC-15 1 location in each building) Semi-Annually
F-1 (Dry Chem Pyro Chem Model PC-15 1 location in each building) Semi-Annually
G-1 (Wet Chem Pyro Chem Model PCL-350 1 location in building) Semi-Annually
H-1 (Dry Chem Pyro Chem Model PC-15 1 location in each building) Semi-Annually
I-1 (Dry Chem Pyro Chem Model PC-15 1 location in each building) Semi-Annually
J-1 (Dry Chem Pyro Chem Model PC-15 1 location in each building) Semi-Annually
K-1 (Dry Chem Pyro Chem Model PC-15 1 location in each building) Semi-Annually
L-1 (Dry Chem Pyro Chem Model PC-15 1 location in each building) Semi-Annually
M-1 (Dry Chem Pyro Chem Model PC-15 1 location in each building) Semi-Annually
N-1 (Dry Chem Pyro Chem Model PC-15 1 location in each building) Semi-Annually
O-1 (Dry Chem Pyro Chem Model PC-15 1 location in each building) Semi-Annually