C-1_B410_Specs.pdf

PDF 10 MB Posted

Attached to
B410 Construction Federal contract opportunity
Solicitation number
FA448419RA036
Issued by
Department of the Air Force Air Mobility Command

About this file

C-1 B410 Specs

View the file

Other files for this federal contract opportunity

Other files attached to B410 Construction, newest first.
File Type Posted
B410_Construction_Q+A.pdf PDF
Solicitation_Amendment_FA448419RA0360003_SF_30.pdf PDF
B410_Attendance.pdf PDF
Solicitation_Amendment_FA448419RA0360002_SF_30.pdf PDF
FA448419RA0360001.pdf PDF
J-4_JB-MDL_Medical_Statement.pdf PDF
C-3_SID_Package.pdf PDF
J-1_JB-MDL_WD_OC_NJ190039_20190517.pdf PDF
J-2_JB-MDL_SFS_Appendix.PDF PDF
J-5_JB-MDL_Past_Performance_Questionnaire_v2.pdf PDF
C-2 B410 Drawings.pdf PDF
J-3_JB-MDL_AntiterrorismStatement.pdf PDF
Solicitation_-_FA448419RA036.pdf PDF
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

LRP Addition/Alteration of Calibration Lab, Bldg 410

FA890316D0007

Joint Base McGuire-Dix-Lakehurst, Lakehurst, New Jersey

Final Design Submittal – For Construction

SPECIFICATIONS

April 8, 2019 Prepared by STOA Architects

STOA #18024

04/08/2019

Lakehu

04/08/2019

LRP Addition/Alteration of Calibration Lab, Bldg 410 Joint Base McGuire-Dix-Lakehurst, Lakehurst, NJ

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 STATEMENT OF WORK

01 45 35 SPECIAL INSPECTIONS

DIVISION 02 - EXISTING CONDITIONS

02 41 00 DECONSTRUCTION

DIVISION 03 - CONCRETE

03 30 00 CAST-IN-PLACE CONCRETE

DIVISION 04 - MASONRY

04 20 00 UNIT MASONRY

DIVISION 05 - METALS

05 50 13 MISCELLANEOUS METAL FABRICATIONS

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

06 10 00 ROUGH CARPENTRY

06 41 16.00 10 PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS

06 61 16 QUARTZ AGGLOMERATE COUNTERTOPS

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 21 16 MINERAL FIBER BLANKET INSULATION

07 24 00 EXTERIOR INSULATION AND FINISH SYSTEMS

07 27 26 FLUID-APPLIED MEMBRANE AIR BARRIERS

07 27 36 SPRAY FOAM AIR BARRIERS

07 31 13 ASPHALT SHINGLES

07 60 00 FLASHING AND SHEET METAL

07 92 00 JOINT SEALANTS

DIVISION 08 - OPENINGS

08 11 13 STEEL DOORS AND FRAMES

08 14 00 WOOD DOORS

08 33 23 OVERHEAD COILING DOORS

08 51 13 ALUMINUM WINDOWS

08 71 00 DOOR HARDWARE

08 81 00 GLAZING

DIVISION 09 - FINISHES

09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD

09 29 00 GYPSUM BOARD

09 30 10 CERAMIC TILING

09 51 00 ACOUSTICAL CEILINGS

09 65 00 RESILIENT FLOORING

09 90 00 PAINTS AND COATINGS

DIVISION 10 - SPECIALTIES

PROJECT TABLE OF CONTENTS Page 1 Final Design Submittal - For Construction

10 14 00.10 EXTERIOR SIGNAGE

10 14 00.20 INTERIOR SIGNAGE

10 26 00 WALL AND DOOR PROTECTION

10 28 13 TOILET ACCESSORIES

10 44 16 FIRE EXTINGUISHERS

DIVISION 12 - FURNISHINGS

12 21 00 WINDOW BLINDS

DIVISION 21 - FIRE SUPPRESSION

21 13 00.00 40 FIRE-SUPPRESSION SPRINKLER SYSTEMS

21 13 16.00 20 DRY-PIPE FIRE SPRINKLER SYSTEMS

DIVISION 22 - PLUMBING

22 00 00 PLUMBING, GENERAL PURPOSE

22 07 19.00 40 PLUMBING PIPING INSULATION

22 15 14.00 40 GENERAL SERVICE COMPRESSED-AIR SYSTEMS, LOW PRESSURE

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS

23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS

23 05 15 COMMON PIPING FOR HVAC

23 05 48.00 40 VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND

EQUIPMENT

23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC

23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS

23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC

23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC

23 09 23.02 BACNET DIRECT DIGITAL CONTROL FOR HVAC AND OTHER BUILDING

CONTROL SYSTEMS

23 11 25 FACILITY GAS PIPING

23 21 13.00 20 LOW TEMPERATURE WATER (LTW) HEATING SYSTEM

23 21 23 HYDRONIC PUMPS

23 25 00 CHEMICAL TREATMENT OF WATER FOR MECHANICAL SYSTEMS

23 52 43.00 20 LOW PRESSURE WATER HEATING BOILERS (UNDER 800,000 BTU/HR

OUTPUT)

23 64 10 VAPOR COMPRESSION TYPE

DIVISION 26 - ELECTRICAL

26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS

26 20 00 INTERIOR DISTRIBUTION SYSTEM

26 27 13.10 30 ELECTRIC METERS

26 32 33.00 10 UNINTERRUPTIBLE POWER SUPPLY (UPS) SYSTEM ABOVE 15 KVA

CAPACITY

26 35 43 400-HERTZ (HZ) SOLID STATE FREQUENCY CONVERTER

26 35 44.00 20 270 VDC SOLID STATE GROUND POWER UNIT

26 41 00 LIGHTNING PROTECTION SYSTEM

26 51 00 INTERIOR LIGHTING

26 56 00 EXTERIOR LIGHTING

DIVISION 27 - COMMUNICATIONS

27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM

PROJECT TABLE OF CONTENTS Page 2 Final Design Submittal - For Construction

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

28 31 74.00 20 INTERIOR FIRE DETECTION AND ALARM SYSTEM

DIVISION 31 - EARTHWORK

31 00 00 EARTHWORK

31 10 00 CLEARING FOR CIVIL WORKS

31 23 00.00 20 EXCAVATION AND FILL

31 31 16.13 CHEMICAL TERMITE CONTROL

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 01 13.62 ASPHALT SURFACE TREATMENT

32 01 16.71 COLD MILLING ASPHALT PAVING

32 05 33 LANDSCAPE ESTABLISHMENT

32 11 20 SUBBASES FOR FLEXIBLE PAVING

32 11 23 AGGREGATE BASE COURSES

32 11 27 BITUMINOUS-STABILIZED BASE COURSE, SUBBASE, OR SUBGRADE

32 16 19 CONCRETE CURBS, GUTTERS AND SIDEWALKS

32 92 23 SODDING

-- End of Project Table of Contents

PROJECT TABLE OF CONTENTS Page 3 Final Design Submittal - For Construction

APPENDIX

Appendix A

Appendix B

NGEN INSIDE CABLE PLANT (ISP) INSTALLATION STANDARDS

ASBESTOS AND LEAD PAINT INSPECTION REPORT

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 1 OF 54 PAGES

LRP Addtion/Alteration of Calibration Lab, Bldg 410

01 45 35 SD-06 Test Reports

3.1.2Daily Reports

3.1.1Biweekly Reports

SD-07 Certificates

2.1Wood Truss Plant

1.5 G AESpecial Inspector

02 41 00 SD-01 Preconstruction Submittals

1.2.1 GDemolition Plan

GDeconstruction Plan

1.9Existing Conditions

SD-07 Certificates

1.6 GNotification

SD-11 Closeout Submittals

3.3.4Receipts

03 30 00 SD-02 Shop Drawings

1.6.2.1 G AEReinforcing Steel

SD-03 Product Data

2.2.8Joint Sealants

2.2.7Joint Filler

2.2.3.3Recycled Aggregate Materials

2.2.1Cementitious Materials

2.2.6Vapor Barrier

2.1.3Concrete Curing Materials

2.3Reinforcement

2.2.5Admixtures

Local/Regional Materials

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P H

C L A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 2 OF 54 PAGES

03 30 00 SD-05 Design Data

2.1.1 G AEMix Design

SD-06 Test Reports

1.6.1.1 G AEConcrete Mix Design

1.6.4.1Fly Ash

1.6.4.1Pozzolan

1.6.4.2Ground Granulated Blast-Furnace

Slag

2.2.3Aggregates

3.10.2.1Tolerance Report

3.14.2.3 G AECompressive Strength Tests

3.14.2.5Unit Weight of Structural

Concrete

3.14.2.4Air Content

3.14.2.1Slump Tests

2.2.2Water

SD-07 Certificates

2.3.1Reinforcing Bars

04 20 00 SD-02 Shop Drawings

3.3.3.1 G AECut CMU

3.4.1.1 G AEDetail Drawings

SD-03 Product Data

1.5.1 G AECold Weather Procedures

2.2.2.1.1 G AECement

SD-04 Samples

G AEMock-Up Panel

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 3 OF 54 PAGES

04 20 00 2.2.2.1 G AEConcrete Masonry Units (CMU)

2.6.2 G AEAnchors, Ties, and Bar

Positioners

2.6.3 G AEJoint Reinforcement

2.6.6 G AEExpansion-Joint Materials

SD-05 Design Data

G AEPre-Mixed Mortar;

G AEUnit Strength MethodBracing

Calculations

SD-06 Test Reports

Efflorescence Test

Fire-Rated Concrete Masonry

Units

3.6.1.1 G AEField Testing of Grout

G AEPrism Tests

Single-Wythe Masonry Wall

Water Penetration Test

SD-07 Certificates

Masonry Inspector Qualifications

2.2.2.1Concrete Masonry Units (CMU)

Concrete Brick

2.4.1.1Cementitious Materials

2.4.1.3Admixtures for Masonry Mortar

2.4.2.2Admixtures for Grout

2.6.2Anchors, Ties, and Bar

Positioners

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 4 OF 54 PAGES

04 20 00 2.6.3Joint Reinforcement

SD-08 Manufacturer’s Instructions

2.4.1.3Admixtures for Masonry Mortar

2.4.2.2Admixtures for Grout

SD-10 Operation and Maintenance

Data

3.8Take-Back Program

05 50 13 SD-02 Shop Drawings

2.4 GBollards/Pipe Guards

SD-03 Product Data

2.5 GDownspout Terminations

2.1 SRecycled Content

GCertificates of Compliance

06 10 00 SD-02 Shop Drawings

G AETrussed Rafters

2.4.1 G AETrussed Joists

1.8.1 G AEFabricated Structural Members

1.8.2 G AEModifications of Structural

Members

SD-03 Product Data

Underlayment

Fire-retardant Treatment

Structural-use and OSB Panels

2.3Oriented Strand Board

2.4.3Adhesives

SD-05 Design Data

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 5 OF 54 PAGES

06 10 00 1.8.2 G AEModifications of Structural

Members

SD-06 Test Reports

1.4.3Preservative-treated

SD-07 Certificates

1.10.1Certificates of Grade

1.7Preservative Treatment

1.10.2Indoor Air Quality

SD-10 Operation and Maintenance

Data

Plastic

Take-back Program

06 41 16.00 10 SD-02 Shop Drawings

2.10Shop Drawings

3.1Installation

SD-03 Product Data

2.1Wood Materials

Wood Finishes

2.10.7.3Finish Schedule

Certification

SD-04 Samples

2.3Plastic Laminates

2.6Cabinet Hardware

SD-07 Certificates

1.4Quality Assurance

3.1Laminate Clad Casework

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 6 OF 54 PAGES

06 61 16 SD-02 Shop Drawings

G AEDetail Drawings

3.1 G AEInstallation

SD-03 Product Data

G AEQuartz Agglomerate Material

1.4.1 G AEQualifications

2.3 G AEFabrications

G AECertification

G AEVOC Content

SD-04 Samples

2.1 G AEMaterial

SD-10 Operation and Maintenance

Data

3.2 G AEClean-up

07 21 16 SD-03 Product Data

2.2Blanket Insulation

Sill Sealer Insulation

Pressure Sensitive Tape

2.4Accessories

SD-08 Manufacturer’s Instructions

3.2.1Insulation

07 24 00 SD-02 Shop Drawings

3.3 G AEShop Drawings

SD-03 Product Data

Sheathing Board

2.4Thermal Insulation

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 7 OF 54 PAGES

07 24 00 2.3Adhesive

2.5Base Coat

2.6Portland Cement

2.7Reinforcing Fabric

2.8Finish Coat

2.11Joint Sealant

2.9Sealant Primer

2.12Bond Breaker

2.13Backer Rod

1.4.5Insulation Board

1.7Warranty

SD-04 Samples

1.2.3.7 G AESample Boards

SD-06 Test Reports

1.2.3.1Abrasion Resistance

1.2.3.2Accelerated Weathering

1.2.2.3Impact Resistance

1.2.3.3Mildew Resistance

1.2.3.4Salt Spray Resistance

1.2.4Vapor Transmission

1.2.3.6Absorption-Freeze-Thaw

1.2.1.3Wall Fire Test

1.2.1.1Water Penetration

1.2.2.1Surface Burning Characteristics

1.2.2.2Radiant Heat

3.1Substrate

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 8 OF 54 PAGES

07 24 00 1.2.1.2Wind Load

SD-07 Certificates

1.4.1Qualifications of EIFS

Manufacturer

1.4.2Qualification of EIFS Installer

1.4.3Qualification of Sealant Applicator

1.4.4Qualifications of Third Party

Inspector

3.5.1 G AEInspection Check List

SD-08 Manufacturer’s Instructions

3.3Installation

SD-10 Operation and Maintenance

Data

1.7EIFS

07 27 26 SD-01 Preconstruction Submittals

1.5.1Qualifications of Manufacturer

1.5.2Qualifications of Installer

SD-02 Shop Drawings

1.3 G AEFluid-Applied Membrane Air

Barrier

SD-03 Product Data

1.3 G AEFluid-Applied Membrane Air

Barrier

2.6Reinforcement

1.3.2 G AESafety Data Sheets

SD-04 Samples

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 9 OF 54 PAGES

07 27 26 Mockup

SD-06 Test Reports

Capillary Moisture Test

1.3.3Field Peel Adhesion Test

1.3.3 G AEFlame Spread and Smoke

Developed Index Ratings

Site Inspections

SD-07 Certificates

1.3Fluid-Applied Membrane Air

Barrier

1.5.1Qualifications of Manufacturer

1.5.2Qualifications of Installer

SD-08 Manufacturer’s Instructions

1.3Fluid-Applied Membrane Air

Barrier

SD-11 Closeout Submittals

2.1 S AEVolatile Organic Compound

(VOC) Content

07 27 36 SD-01 Preconstruction Submittals

1.8.2Respirator Plan

SD-03 Product Data

2.2.2Closed Cell

2.3Transition Membrane

2.4Primers, Adhesives, and Mastics

2.6Sealants

1.5.1Safety Data Sheets

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 10 OF 54 PAGES

07 27 36 SD-06 Test Reports

1.5.2 GFlame Spread And Smoke

Developed Index Ratings Of SPF

Products

1.5.2Flame Propagation Of Wall

Assemblies

SD-08 Manufacturer’s Instructions

1.6.1SPF Handling, Storage, and

Spray Procedures

2.3Transition Membrane

SD-11 Closeout Submittals

2.1.1Recycled Content

07 31 13 SD-03 Product Data

2.2.1Shingles

SD-04 Samples

2.2.1 G AEShingles

2.2.1 G AEColor Charts

SD-08 Manufacturer’s Instructions

3.3Application

SD-11 Closeout Submittals

2.2.1 SEnergy Star Label for Asphalt

Shingle

1.5.1Manufacturer's Warranty

1.5.2Contractor's Warranty

07 60 00 SD-02 Shop Drawings

2.2.1 G AEExposed Sheet Metal

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 11 OF 54 PAGES

07 60 00 3.1.9 G AEGutters

3.1.10 G AEDownspouts

G AEExpansion Joints

G AEFascia

3.1.5 G AEBase Flashing

3.1.6 G AECounterflashing

3.1.13 G AEFlashing at Roof Penetrations

and Equipment Supports

3.1.8Drip Edges

3.1.11 G AEEave Flashing

SD-04 Samples

1.4.2 G AEFinish Samples

SD-07 Certificates

2.1Certificates of Compliance

SD-08 Manufacturer’s Instructions

1.4.3Instructions for Installation

3.5Quality Control Plan

SD-10 Operation and Maintenance

Data

1.4.3Cleaning and Maintenance

SD-11 Closeout Submittals

2.1Recycled Content

07 92 00 SD-03 Product Data

2.2 G AESealants

2.3 G AEPrimers

2.4 G AEBond Breakers

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 12 OF 54 PAGES

07 92 00 2.5 G AEBackstops

3.1 G AEField Adhesion

SD-11 Closeout Submittals

2.2.1 SIndoor Air Quality For Interior

Sealants

2.2.3 SIndoor Air Quality For Interior

Floor Joint Sealants

2.2.4 SIndoor Air Quality For Interior

Acoustical Sealants

2.6 SIndoor Air Quality For Interior

Caulking

08 11 13 SD-02 Shop Drawings

2.1 G AEDoors

2.1 G AEDoors

2.4 G AEFrames

2.4 G AEFrames

2.2Accessories

2.5Weatherstripping

SD-03 Product Data

2.1 G AEDoors

2.4 G AEFrames

2.2Accessories

2.5Weatherstripping

08 14 00 SD-02 Shop Drawings

2.1 G AEDoors

SD-03 Product Data

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 13 OF 54 PAGES

08 14 00 2.1 G AEDoors

2.2 G AEAccessories

2.3.6 G AEWater-resistant Sealer

1.5 G AEWarranty

2.1.2 G AESound Transmission Class

Rating

SD-04 Samples

2.3.5.2 G AEDoor Finish Colors

SD-06 Test Reports

2.4 G AECycle-Slam

2.4 G AEHinge Loading Resistance

08 33 23 SD-02 Shop Drawings

2.2.1 G AEOverhead Coiling Doors

2.2.3Counterbalancing Mechanism

2.2.4 G AEManual Door Operators

2.2.1.3Bottom Bars

2.1.1.1Guides

2.2.3.1Mounting Brackets

2.2.1.8Overhead Drum

3.3.2Hood

2.1.1.1Installation Drawings

SD-03 Product Data

2.2.1 G AEOverhead Coiling Doors

2.2.2Hardware

2.2.3Counterbalancing Mechanism

2.2.4Manual Door Operators

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 14 OF 54 PAGES

08 33 23 SD-05 Design Data

2.2.1 G AEOverhead Coiling Doors

2.2.2Hardware

2.2.3Counterbalancing Mechanism

2.2.4Manual Door Operators

SD-10 Operation and Maintenance

Data

3.3.2Operation and Maintenance

Manuals

3.3.2Materials

3.3.2Devices

3.3.2Procedures

3.3.2Manufacture's Brochures

3.3.2Parts Lists

SD-11 Closeout Submittals

3.3.1 G AEWarranty

08 51 13 SD-02 Shop Drawings

2.2 G AEWindows

1.10Fabrication Drawings

SD-03 Product Data

2.2 G AEWindows

G AEHardware

2.3.2 G AEFasteners

Thermal-Barrier Windows

2.4Mullions

SD-04 Samples

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 15 OF 54 PAGES

08 51 13 1.4.2.1Finish Sample

SD-05 Design Data

2.2 G AEStructural Calculations for

Deflection

SD-11 Closeout Submittals

2.1.1 SRecycled Content of Aluminum

Windows

08 71 00 SD-02 Shop Drawings

1.3 G AEManufacturer's Detail Drawings

1.5 G AEHardware Schedule

2.3.8 G AEKeying System

SD-03 Product Data

2.3Hardware Items

SD-08 Manufacturer’s Instructions

3.1Installation

SD-10 Operation and Maintenance

Data

1.5Hardware Schedule

SD-11 Closeout Submittals

1.6.1Key Bitting

08 81 00 SD-02 Shop Drawings

Installation

SD-03 Product Data

1.6.1Insulating Glass

1.3Glazing Accessories

SD-04 Samples

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 16 OF 54 PAGES

08 81 00 1.6.1Insulating Glass

SD-07 Certificates

1.6.1Insulating Glass

SD-08 Manufacturer’s Instructions

2.4Setting and Sealing Materials

3.2Glass Setting

09 22 00 SD-02 Shop Drawings

2.1 G AEMetal support systems

09 29 00 SD-03 Product Data

2.2.4Cementitious Backer Units

2.2.2Water-Resistant Gypsum Backing

Board

2.2.3Abuse Resistant Gypsum Board

2.2.7Accessories

1.3Certifications

2.2.1Gypsum Board

SD-07 Certificates

2.2Asbestos Free Materials

1.3.1Indoor Air Quality

SD-08 Manufacturer’s Instructions

2.2Safety Data Sheets

SD-10 Operation and Maintenance

Data

2.2Manufacturer Maintenance

Instructions

09 30 10 SD-03 Product Data

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 17 OF 54 PAGES

09 30 10 2.1.1Porcelain Tile

Quarry Tile

2.1.2Glazed Wall Tile

2.2Setting-Bed

2.4Mortar, Grout, and Adhesive

SD-04 Samples

2.1 G AETile

2.1 G AETransition Strips

2.6 G AETransition Strips

2.4.3 G AEGrout

SD-07 Certificates

1.3.1Indoor Air Quality

SD-08 Manufacturer’s Instructions

3.7Maintenance Instructions

SD-10 Operation and Maintenance

Data

3.2Installation

SD-11 Closeout Submittals

2.1.1 SRecycled Content for Porcelain

Tile

2.1.2 SRecycled Content for Glazed Wall

Tile

2.4 SIndoor Air Quality for Adhesives

2.4.6 SIndoor Air Quality for Sealants

09 51 00 SD-03 Product Data

G DORAcoustical Ceiling Systems

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 18 OF 54 PAGES

09 51 00 1.3Certifications

SD-04 Samples

2.2.1.1 G DORAcoustical Ceiling Tiles

SD-06 Test Reports

2.1.1 G DORCeiling Attenuation Class and

Test

09 65 00 SD-02 Shop Drawings

2.7 G AEResilient Flooring and

Accessories

SD-03 Product Data

2.7 G AEResilient Flooring and

Accessories

2.3Adhesives

2.1Vinyl Composition Tile

2.2Wall Base

SD-04 Samples

2.7 G AEResilient Flooring and

Accessories

SD-06 Test Reports

3.3 G AEMoisture, Alkalinity and Bond

Tests

SD-08 Manufacturer’s Instructions

3.2Surface Preparation

3.1Installation

SD-10 Operation and Maintenance

Data

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 19 OF 54 PAGES

09 65 00 2.7Resilient Flooring and

Accessories

09 90 00 SD-03 Product Data

1.7.1Local/Regional Materials

2.1 G DORCoating

2.1Manufacturer's Technical Data

Sheets

3.2.5Sealant

SD-04 Samples

G DORColor

SD-08 Manufacturer’s Instructions

3.3.1Application instructions

1.5.2Manufacturer's Material Safety

Data Sheets

SD-10 Operation and Maintenance

Data

2.1 G DORCoatings:

10 14 00.10 SD-02 Shop Drawings

3.1 G DORApproved Detail Drawings

SD-03 Product Data

2.1Modular Exterior Signage System

1.2Exterior Signage

SD-04 Samples

1.2 G DORExterior Signage

SD-10 Operation and Maintenance

Data

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 20 OF 54 PAGES

10 14 00.10 3.1.2 GProtection and Cleaning

10 14 00.20 SD-02 Shop Drawings

1.4.2 G DORDetail Drawings

SD-03 Product Data

3.1 G DORInstallation

1.6 G DORWarranty

SD-04 Samples

1.4.1 G DORInterior Signage

Software

SD-10 Operation and Maintenance

Data

3.1.2 G DORProtection and Cleaning

10 26 00 SD-02 Shop Drawings

2.2Corner Guards

SD-03 Product Data

2.2Corner Guards

SD-04 Samples

2.4Finish

SD-06 Test Reports

2.2Corner Guards

SD-07 Certificates

2.2Corner Guards

1.3.1Indoor Air Quality

10 28 13 SD-03 Product Data

2.1.2Finishes

2.2Accessory Items

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 21 OF 54 PAGES

10 28 13 SD-11 Closeout Submittals

2.1 SRecycled content for stainless

steel toilet accessories

10 44 16 SD-01 Preconstruction Submittals

2.1.1 GManufacturer's Data

SD-02 Shop Drawings

2.1.1 G AEFire Extinguishers

1.3.1Accessories

Part 2 G AECabinets

1.3.1 G AEWall Brackets

SD-03 Product Data

2.1.1Fire Extinguishers

1.3.1Accessories

Part 2Cabinets

1.3.1Wall Brackets

3.2.1Replacement Parts List

SD-07 Certificates

2.1.1Fire Extinguishers

2.1.1Manufacturer's Warranty with

Inspection Tag

12 21 00 SD-02 Shop Drawings

3.3Installation

SD-03 Product Data

2.1 G AEWindow Blinds

3.3Installation

Certifications

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 22 OF 54 PAGES

12 21 00 SD-04 Samples

2.1 G AEWindow Blinds

SD-06 Test Reports

2.1Window Blinds

SD-08 Manufacturer’s Instructions

2.1Window Blinds

SD-10 Operation and Maintenance

Data

2.1Window Blinds

21 13 00.00 40 SD-01 Preconstruction Submittals

1.2 GRecord of Existing Conditions

SD-02 Shop Drawings

2.2.3 GSupporting Elements

2.2.4 GFire-Department Connections

2.2.7 GSprinkler Heads

2.2.8 GValves

SD-03 Product Data

2.2.1 GUnderground Piping Materials

2.2.2 GAboveground Piping Materials

2.2.8 GValves

2.2.4 GFire-Department Connections

2.2.5 GRiser Alarm Equipment

2.2.6.1 GAir Compressor

2.2.7 GSprinkler Heads

2.3 GMaterials

2.2.3 GSupporting Elements

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 23 OF 54 PAGES

21 13 00.00 40 2.1 GEquipment and Performance

Data

SD-05 Design Data

Part 2 GDesign Analysis and Calculations

SD-06 Test Reports

3.3.6 GPressure Tests

3.3.3 GSystem Operating Tests

3.3.3 GAir Tests

3.3.3 GValve-Operating Tests

3.3.3 GDrainage Tests

21 13 16.00 20 SD-02 Shop Drawings

1.3.8 GSprinkler heads and piping

system layout

1.3.8 GElectrical wiring diagrams

SD-03 Product Data

2.1 GPiping

2.1.10 GValves

2.1.5 GWater motor alarms

2.1.2 GSprinkler heads

2.1.9 GPipe hangers and supports

2.1.14 GFire department connections

2.1.7 GLow air pressure supervisory

switch

2.1.4 GDry pipe valves

2.1.8 GAir compressor

2.1.1 GMechanical couplings

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 24 OF 54 PAGES

21 13 16.00 20 2.1.10.1 GBackflow Preventers

2.1.6 GPressure Switch

SD-05 Design Data

1.3 GSprinkler system design

SD-06 Test Reports

3.2.1 GPreliminary tests

SD-07 Certificates

1.5.1 GQualifications of installer

SD-10 Operation and Maintenance

Data

2.1.4 GDry pipe valves

2.1.8 GAir compressor

SD-11 Closeout Submittals

1.3.9 GAs-built drawings of each system

22 00 00 SD-02 Shop Drawings

3.8.1 GPlumbing System

SD-03 Product Data

2.5Fixtures

2.5.3Flush Valve Water Closets

2.5.4Wall Hung Lavatories

2.5.5Countertop Lavatories

2.5.6Kitchen Sinks

2.5.7Service Sinks

2.10 GWater Heaters

2.12 GPumps

3.8.1.1 GBackflow Prevention Assemblies

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 25 OF 54 PAGES

22 00 00 1.5.1Welding

3.4 GVibration-Absorbing Features

3.8.1Plumbing System

SD-06 Test Reports

3.8Tests, Flushing and Disinfection

3.8.1.1 GTest of Backflow Prevention

Assemblies

SD-07 Certificates

1.3Materials and Equipment

2.2.1Bolts

SD-10 Operation and Maintenance

Data

3.8.1 GPlumbing System

SD-11 Closeout Submittals

2.1.1 SWater-Efficient Products

2.1.2 SEnergy-Efficient Water Heaters

22 07 19.00 40 SD-02 Shop Drawings

3.1 GInstallation Drawings

SD-03 Product Data

2.3 GAdhesives

2.3 GCoatings

2.3 GInsulating Cement

2.3 GInsulation Materials

2.3 GTape

SD-08 Manufacturer’s Instructions

3.1 GInstallation Manual

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 26 OF 54 PAGES

22 07 19.00 40 SD-11 Closeout Submittals

3.4Record Drawings

2.3 SAdhesives

2.3 SCoatings

2.3 SInsulation Materials

1.3.1 SRecycled Materials

22 15 14.00 40 SD-02 Shop Drawings

2.1 GInstallation Drawings

SD-03 Product Data

2.1.1 GEquipment and Performance

Data

2.3.1 GAboveground Piping Materials

2.2.1 GPiping Specialties

2.4.2 GSupporting Elements

2.2.2 GAir Compressors

2.2.3 GValves

3.1.1.1 GAccessories

2.4.1 GMiscellaneous Materials

SD-05 Design Data

2.1.1 GDesign Analysis and Calculations

SD-06 Test Reports

3.2.1.4Piping System Test Report

SD-07 Certificates

2.3.1Aboveground Piping Materials

2.4.2Supporting Elements

2.2.3Valves

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 27 OF 54 PAGES

22 15 14.00 40 2.4.1Miscellaneous Materials

SD-10 Operation and Maintenance

Data

3.4Operation and Maintenance

Manuals

23 00 00 SD-02 Shop Drawings

1.4.5 GDetail Drawings

SD-03 Product Data

2.10.1.1Metallic Flexible Duct

2.10.1.2Insulated Nonmetallic Flexible

Duct Runouts

2.10.1.2Duct Connectors

2.10.2 GDuct Access Doors

2.10.3Fire Dampers

2.10.10Sound Attenuation Equipment

2.10.10.1Acoustical Duct Liner

2.10.11.1Diffusers

2.10.11.4Registers and Grilles

2.10.12Louvers

2.10.13Air Vents, Penthouses, and

Goosenecks

2.11.1.1Centrifugal Fans

2.11.1.3Centrifugal Type Power Roof

Ventilators

2.12 GAir Handling Units

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 28 OF 54 PAGES

23 00 00 2.13.1.1 GVariable Volume, Single Duct

Terminal Units

2.13.1.3 GReheat Units

1.4.6Test Procedures

1.2.1.2 GDiagrams

SD-06 Test Reports

3.14 GPerformance Tests

3.12 GDamper Acceptance Test

SD-07 Certificates

1.4.7Certification

1.4.3Ozone Depleting Substances

SD-08 Manufacturer’s Instructions

3.3Manufacturer's Installation

Instructions

3.16.2Operation and Maintenance

Training

SD-10 Operation and Maintenance

Data

3.16.1 GOperation and Maintenance

Manuals

2.10.3 GFire Dampers

2.10.4 GManual Balancing Dampers

2.10.5 GManual Balancing Dampers

2.11.1.1 GCentrifugal Fans

2.11.1.2 GIn-Line Centrifugal Fans

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 29 OF 54 PAGES

23 00 00 2.11.1.3 GCentrifugal Type Power Roof

Ventilators

2.12 GAir Handling Units

2.13.1.1 GVariable Volume, Single Duct

Terminal Units

2.13.1.3 GReheat Units

SD-11 Closeout Submittals

2.1.1 SEnergy Efficient Equipment

2.1.2 SReduce Volatile Organic

Compounds (VOC)

3.1 SIndoor Air Quality During

Construction

2.1.3 SOzone Depleting Substances for

Refrigerants

23 03 00.00 20 SD-11 Closeout Submittals

2.1.1 SEnergy Efficient Equipment for

Motors

2.1.2 SReduce Volatile Organic

Compounds (VOC)

23 05 15 SD-01 Preconstruction Submittals

1.2 GMaterial, Equipment, and Fixture

Lists

SD-02 Shop Drawings

1.2 GRecord Drawings

1.2 GConnection Diagrams

1.2 GCoordination Drawings

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 30 OF 54 PAGES

23 05 15 1.2 GFabrication Drawings

3.1 GInstallation Drawings

SD-03 Product Data

2.2 GPipe and Fittings

2.3 GPiping Specialties

2.4 GValves

2.5 GMiscellaneous Materials

2.6 GSupporting Elements

1.2 GEquipment Foundation Data

SD-04 Samples

1.2 GManufacturer's Standard Color

Charts

SD-05 Design Data

2.2 GPipe and Fittings

2.3 GPiping Specialties

2.4 GValves

SD-06 Test Reports

3.1 GHydrostatic Tests

3.1 GAir Tests

3.1 GValve-Operating Tests

3.1 GDrainage Tests

3.1 GPneumatic Tests

3.1 GNon-Destructive Electric Tests

3.1 GSystem Operation Tests

SD-07 Certificates

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 31 OF 54 PAGES

23 05 15 1.4.2 GRecord of Satisfactory Field

Operation

1.4.3 GList of Qualified Permanent

Service Organizations

1.2 GListing of Product Installations

1.2 GRecords of Existing Conditions

3.1 GSurface Resistance

3.1 GShear and Tensile Strengths

3.1 GTemperature Ratings

3.1 GBending Tests

3.1 GFlattening Tests

3.1 GTransverse Guided Weld Bend

Tests

SD-10 Operation and Maintenance

Data

3.12 GOperation and Maintenance

Manuals

23 05 48.00 40 SD-02 Shop Drawings

1.2 GInstallation Drawings

1.2 GOutline Drawings

SD-03 Product Data

1.2 GEquipment and Performance

Data

2.2.9 GIsolators

SD-06 Test Reports

2.4 GType of Isolator

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 32 OF 54 PAGES

23 05 48.00 40 2.4 GType of Base

2.4 GAllowable Deflection

2.4 GMeasured Deflection

23 05 93 SD-01 Preconstruction Submittals

1.3.3 GRecords of Existing Conditions

1.3.3 GRecords of Existing Conditions

1.5.1 GIndependent TAB Agency and

Personnel Qualifications

1.5.4.2 GTAB Design Review Report

1.7.1.1 GTAB Design Review Report

1.5.9.1 GTAB Firm

1.2 GTAB Team Assistants

1.2 GTAB Team Engineer

1.5.9.2 GTAB Specialist

1.2 GTAB Team Field Leader

SD-02 Shop Drawings

1.3.3 GTAB Schematic Drawings and

Report Forms

SD-03 Product Data

1.3 GEquipment and Performance

Data

1.5.1.3 GTAB Related HVAC Submittals

1.5.9.4 GTAB Related HVAC Submittals

1.5.7 GTAB Procedures

1.5.7 GCalibration

1.3.3 GSystems Readiness Check

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 33 OF 54 PAGES

23 05 93 1.5.10 GTAB Execution

1.5.10.3 GTAB Verification

SD-06 Test Reports

3.3.5 GCompleted Pre-Final DALT

Report

3.3.8 GCertified Final DALT Report

1.5.4.3 GPrerequisite HVAC Work

Checkout List

1.5.4.3 GPrerequisite HVAC Work

Checkout List

1.5.4.3 GPrerequisite HVAC Work

Checkout List

3.4.7.1 GProportional Balancing

3.7 GProportional Balancing

3.4.7.2 GSeason 1

3.7 GSeason 1

3.4.7.2 GSeason 2

3.7 GSeason 2

1.5.4.2 GTAB Design Review Report

1.7.1.1 GTAB Design Review Report

1.5.11.2 GTAB Report for Season 1

1.5.11.2 GTAB Report for Season 2

SD-07 Certificates

1.5.1 GIndependent TAB Agency and

Personnel Qualifications

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 34 OF 54 PAGES

23 05 93 1.5.4.2 GDALT and TAB Submittal and

Work Schedule

1.7.1 GDALT and TAB Submittal and

Work Schedule

1.5.4.3 GTAB Pre-Field Engineering

Report

1.7.1.3 GTAB Pre-Field Engineering

Report

1.5.6 GInstrument Calibration

Certificates

3.7 GDALT and TAB Procedures

Summary

3.7 GCompleted Pre-Final DALT Work

Checklist

3.3.2 GAdvance Notice of Pre-Final

DALT Field Work

3.4.7.1 GProportional Balancing

3.7 GProportional Balancing

3.4.7.2 GSeason 1

3.7 GSeason 1

3.4.7.2 GSeason 2

3.7 GSeason 2

1.5.9.1 GTAB Firm

1.3.3 GDesign Review Report

1.7.1.2 GPre-field DALT Preliminary

Notification

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 35 OF 54 PAGES

23 05 93 1.5.4.3 GPrerequisite HVAC Work Check

Out List

23 07 00 SD-02 Shop Drawings

3.2.2.4 GMICA Plates

2.4Pipe Insulation Systems

3.2Pipe Insulation Systems

3.3Duct Insulation Systems

3.4Equipment Insulation Systems

SD-03 Product Data

2.4 GPipe Insulation Systems

3.2 GPipe Insulation Systems

3.3 GDuct Insulation Systems

3.4 GEquipment Insulation Systems

SD-04 Samples

2.3.1.3 GThermal Insulation

3.1.1 GDisplay Samples

SD-08 Manufacturer’s Instructions

2.4 GPipe Insulation Systems

3.2 GPipe Insulation Systems

3.3 GDuct Insulation Systems

3.4 GEquipment Insulation Systems

SD-11 Closeout Submittals

2.1.1 SReduce Volatile Organic

Compounds (VOC)

2.1.2 SRecycled Content

23 09 00 SD-02 Shop Drawings

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 36 OF 54 PAGES

23 09 00 3.3 GDDC Contractor Design Drawings

3.3 GDraft As-Built Drawings

3.3 GFinal As-Built Drawings

SD-03 Product Data

2.2 GManufacturer's Product Data

SD-06 Test Reports

3.1.1Existing Conditions Report

3.5.2 GStart-Up Testing Report

3.6.1 GPVT Procedures

3.6.3 GPVT Report

1.9.1 GPre-Construction Quality Control

(QC) Checklist

1.9.2 GPost-Construction Quality Control

(QC) Checklist

SD-10 Operation and Maintenance

Data

3.7 GOperation and Maintenance

(O&M) Instructions

3.9.1 GTraining Documentation

SD-11 Closeout Submittals

2.5 GEnclosure Keys

3.2.6.1 GPassword Summary Report

1.9.3 GCloseout Quality Control (QC)

Checklist

23 11 25 SD-02 Shop Drawings

1.5.3 GGas Piping System

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 37 OF 54 PAGES

23 11 25 2.2 GGas Piping System

3.3 GGas Piping System

SD-03 Product Data

1.6.1 GPipe and Fittings

1.5.3 GGas Equipment Connectors

1.5.3 GGas Piping System

2.2 GGas Piping System

3.3 GGas Piping System

2.1 GPipe Coating Materials

2.6 GPressure Regulators

2.4 GRisers

2.2.8 GTransition Fittings

2.3 GValves

2.2.4 GWarning and Identification Tape

SD-06 Test Reports

3.18 GTesting

3.18.1 GPressure Tests

3.18.2 GPressure Tests for Liquified

Petroleum Gas

3.18.3 GTest with Gas

SD-07 Certificates

1.5.1 GWelders Procedures and

Qualifications

1.5.1 GAssigned Number, Letter, or

Symbol

SD-08 Manufacturer’s Instructions

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 38 OF 54 PAGES

23 11 25 1.5.2 GPE Pipe and Fittings

2.1 GPipe Coating Materials

SD-10 Operation and Maintenance

Data

1.3.1 GGas Facility System and

Equipment Operation

1.3.2 GGas Facility System Maintenance

1.3.3 GGas Facility Equipment

Maintenance

23 21 13.00 20 SD-02 Shop Drawings

1.3.1Hot water heating system

SD-03 Product Data

2.3.1Pumps

2.3.2Expansion tanks

2.3.5Flow measuring equipment

2.3.4Backflow preventers

2.3.3External air separation tanks

2.1.1Hot water heating pipe

SD-06 Test Reports

3.3.1Hydrostatic test of piping system

3.3.2Auxiliary equipment and accessory tests

SD-07 Certificates

1.5.4Backflow preventer certification

1.5.2.1Report of prior installations

1.5.2.2Welding procedures

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 39 OF 54 PAGES

23 21 13.00 20 1.5.2.3Welder's qualifications

23 21 23 SD-02 Shop Drawings

2.1.2 GSystem Coordination

SD-03 Product Data

2.2.2 GInstructions

2.2.5 GEquipment Data

3.5.2 GTraining Period

SD-06 Test Reports

2.8Factory Tests

3.3Field Quality Control

SD-07 Certificates

1.3.1Manufacturer's Representative

SD-10 Operation and Maintenance

Data

3.5.1 GOperation and Maintenance

Manuals

3.5.2 GTraining

23 25 00 SD-03 Product Data

2.5 GWater Analysis

1.6Spare Parts

3.4Field Instructions

3.5 GTests

3.4 GTraining Course

23 52 43.00 20 SD-02 Shop Drawings

1.3.2.2Fuel Train

1.3.2.2Wiring Diagram

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 40 OF 54 PAGES

23 52 43.00 20 SD-03 Product Data

2.2Boilers

2.4Boiler Trim and Control

Equipment

2.3Burners and Control Equipment

SD-06 Test Reports

3.4.1Operational Tests

1.3.3Water Analysis

SD-07 Certificates

2.2Boilers

2.3Burners and Control Equipment

2.4Boiler Trim and Control

Equipment

SD-08 Manufacturer’s Instructions

2.2Boilers

2.4.7Feedwater Treatment Feeder

SD-10 Operation and Maintenance

Data

2.2Boilers

SD-11 Closeout Submittals

2.1.1 SEnergy Efficient Equipment for

Boilers

2.2boilers

23 64 10 SD-03 Product Data

3.2.3Posted Instructions

1.5.1Verification of Dimensions

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 41 OF 54 PAGES

23 64 10 2.9Factory Tests

3.7System Performance Tests

3.8Demonstrations

3.6.1Water Chiller - Field Acceptance

Test Plan

SD-06 Test Reports

3.6Field Acceptance Testing

3.6.2Field Acceptance Test Report

2.9Factory Tests

3.7System Performance Tests

SD-07 Certificates

3.2.8…

This is the start of the file's text. The full file is on GovTribe.