SOW_Hydro_Form_Press_Attachment_1.docx
DOCX document 16 KB Posted
- Attached to
- Hydro Form Press Federal contract opportunity
- Solicitation number
- FA4460-16-T-0017
About this file
SOW
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Hydro_Form_Press_Q A.docx | DOCX document | |
| Hydro_Form_Press_Q A.docx | DOCX document | |
| Hydro_Form_Press_Specifications_Attachment_2.docx | DOCX document | |
| FA4460-16-T-0017.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 1 FA4460-16-T-0017
STATEMENT OF WORK (SOW)
Bldg. 250 Hydro Form Press Hookup Little Rock Air Force Base, Arkansas
General
1.1 Scope of work:
The Contractor shall provide all ancillary equipment, conduit, wire and labor necessary to complete the installation, including connection to the inside disconnect and other items and services necessary to complete a full disconnect change out in building 250.
1.2 Physical Location:
The place of performance for this contract will be at Bldg 250, Little Rock Air Force Base, AR 72099.
1.3 Work To Be Performed:
1.3.1. Supply and install a new 150 amp circuit breaker.
1.3.2. Extend a conduit and circuit from the MDP panel to the Hydro Form Press.
1.3.3. Supply and install a new service entrance with external service entrance rated fused disconnect and a safety disconnect inside the room for the Hydro Form Press.
1.3.6. All conduit and wire from the transformer to the Hydro Form Press is the responsibility of the general contractor to provide and install. All requirements of the NEC shall be met.
1.4 Acceptance Criteria:
1.4.1 . All components and accessories are new, serviceable, and operate smoothly.
1.4.2. Area of installation is restored to the original condition prior to installation, and free of any debris.
1.4.3. All damages caused by the Contractor, whether to equipment, furniture, roads, landscaping, building components, or any other type of Government property encountered at or near the project site shall be repaired or replaced to match existing conditions to the satisfaction of the Contracting Officer at no additional cost to the Government.
1.4.4. Any damages will be recorded and reported within five (5) business days of completion of installation. If any unacceptable work is found during acceptance inspection, the Contractor shall correct any deficiencies within a reasonable amount of time chosen by the Contracting Officer at no cost to the Government.