D/B Repair/Sustain Roofs B-340/B-970 Federal contract opportunity
Solicitation number
FA4460-16-B-0004
Issued by
Department of the Air Force Air Mobility Command

About this file

Attachment 4 Material Submittal

View the file

Other files for this federal contract opportunity

Other files attached to D/B Repair/Sustain Roofs B-340/B-970, newest first.
File Type Posted
Attachment_10_-_Roof_Survey_B970.pdf PDF
10_May_Site_Visit.pdf PDF
Amendment_2.pdf PDF
4_May_site_visit.pdf PDF
Attachment_8_-_B-340_Floor_Plan.pdf PDF
Attachment_9_-_B-340_Roof_Survey.pdf PDF
Amendment_1.pdf PDF
Attachment_1_-_SOW_NKAK-08-10514-_13-10436.docx DOCX document
Attachment_3_-_C D_Report.doc DOC document
Attachment_5_-_EMIS_Instruction_Guide.doc DOC document
Attachment_2_-_Environmental_MOA.doc DOC document
FA4460-16-B-0004.doc DOC document
Attachment_7_-_LRAFB_Information.pdf PDF
Attachment_6_-_Wage_Determination_AR160132.pdf PDF
Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Material Submittals Schedule SCHEDULE OF MATERIAL SUBMITTALS NKAK 08-105144, NKAK 13-10436 FA4406-16-B-0004 Attch 4

(To be completed by Project Engineer)(To be completed by Contract Administrator)
NUMBER OF COPIES REQUIRED
LINE NUMBERITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTALCERTIFICATION OF COMPLIANCESHOP DRAWINGSSAMPLESCOLOR SELECTIONMANUFACTURER'S RECOMMENDATIONMANUFACTURER'S WARRANTYCATALOG DATAOPERATING INSTRUCTIONSSCHEDULES, LISTINGS, REPORTS, PLANSTECHNICAL DATATEST REPORTSFIELD REPORTSREQUIRED SUBMISSION DATE

fergusog: Enter the due date from the Contractor (MM/DD/YY)

DATE RECEIVED IN CONTRACTING

fergusog: Enter the date received from the Contractor. (MM/DD/YY)

DATE TO CIVIL ENGINEERING

fergusog: Enter the date submittal was given to CE for review. (MM/DD/YY)

RETURN SUSPENSE DATE

fergusog: Enter the date the submittal is due back from CE

(MM/DD/YY)

SUBMITTAL NUMBERS

fergusog: Enter the Submittal Number

DATE CONTRACTOR NOTIFIED CONTRACTOR RESUBMITTAL

fergusog: Enter Resubmittal Number

FINAL APPROVAL

fergusog: Enter the submittal final approval date

(MM/DD/YY)

REMARKS

fergusog: Enter any comments pertaining to the submittal

APPROVED

fergusog: Enter date the Contractor was notified of submittal approval

(MM/DD/YY)

fergusog: Enter Resubmittal Number

DISAPPROVED

fergusog: Enter date the Contractor was notified of submittal disapproval

(MM/DD/YY)

fergusog: Enter the submittal final approval date

(MM/DD/YY)

fergusog: Enter any comments pertaining to the submittal

101 14 19 Coordenation 1.12 Radioactive MaterialXXX
201 45 00 Quality Control 1.05 Cultural Resource ManagementX
301 45 00 1.06 Temporary Erosion Control MeasuresXXX
4DensdeckXX
5AsphaltXX
6sealantsXX
7fastenersXX
8insulationXX
9base sheetxx
10intermediate plysxx
11cap sheetxx
12surface coatingxx
Schedule of Material Submittals Template, Feb 2010 (SAF/AQCP)

File details come from the government source that posted it. Updated .