Attachment_4_-Material_Submittal.xlsx
XLSX spreadsheet 21 KB Posted
- Attached to
- D/B Repair/Sustain Roofs B-340/B-970 Federal contract opportunity
- Solicitation number
- FA4460-16-B-0004
About this file
Attachment 4 Material Submittal
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment_10_-_Roof_Survey_B970.pdf | ||
| 10_May_Site_Visit.pdf | ||
| Amendment_2.pdf | ||
| 4_May_site_visit.pdf | ||
| Attachment_8_-_B-340_Floor_Plan.pdf | ||
| Attachment_9_-_B-340_Roof_Survey.pdf | ||
| Amendment_1.pdf | ||
| Attachment_1_-_SOW_NKAK-08-10514-_13-10436.docx | DOCX document | |
| Attachment_3_-_C D_Report.doc | DOC document | |
| Attachment_5_-_EMIS_Instruction_Guide.doc | DOC document | |
| Attachment_2_-_Environmental_MOA.doc | DOC document | |
| FA4460-16-B-0004.doc | DOC document | |
| Attachment_7_-_LRAFB_Information.pdf | ||
| Attachment_6_-_Wage_Determination_AR160132.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Material Submittals Schedule SCHEDULE OF MATERIAL SUBMITTALS NKAK 08-105144, NKAK 13-10436 FA4406-16-B-0004 Attch 4
| (To be completed by Project Engineer) | (To be completed by Contract Administrator) | ||||||||||||||
| NUMBER OF COPIES REQUIRED | |||||||||||||||
| LINE NUMBER | ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL | CERTIFICATION OF COMPLIANCE | SHOP DRAWINGS | SAMPLES | COLOR SELECTION | MANUFACTURER'S RECOMMENDATION | MANUFACTURER'S WARRANTY | CATALOG DATA | OPERATING INSTRUCTIONS | SCHEDULES, LISTINGS, REPORTS, PLANS | TECHNICAL DATA | TEST REPORTS | FIELD REPORTS | REQUIRED SUBMISSION DATE |
fergusog: Enter the due date from the Contractor (MM/DD/YY)
DATE RECEIVED IN CONTRACTING
fergusog: Enter the date received from the Contractor. (MM/DD/YY)
DATE TO CIVIL ENGINEERING
fergusog: Enter the date submittal was given to CE for review. (MM/DD/YY)
RETURN SUSPENSE DATE
fergusog: Enter the date the submittal is due back from CE
(MM/DD/YY)
SUBMITTAL NUMBERS
fergusog: Enter the Submittal Number
DATE CONTRACTOR NOTIFIED CONTRACTOR RESUBMITTAL
fergusog: Enter Resubmittal Number
FINAL APPROVAL
fergusog: Enter the submittal final approval date
(MM/DD/YY)
REMARKS
fergusog: Enter any comments pertaining to the submittal
APPROVED
fergusog: Enter date the Contractor was notified of submittal approval
(MM/DD/YY)
fergusog: Enter Resubmittal Number
DISAPPROVED
fergusog: Enter date the Contractor was notified of submittal disapproval
(MM/DD/YY)
fergusog: Enter the submittal final approval date
(MM/DD/YY)
fergusog: Enter any comments pertaining to the submittal
| 1 | 01 14 19 Coordenation 1.12 Radioactive Material | X | X | X | ||
| 2 | 01 45 00 Quality Control 1.05 Cultural Resource Management | X | ||||
| 3 | 01 45 00 1.06 Temporary Erosion Control Measures | X | X | X | ||
| 4 | Densdeck | X | X | |||
| 5 | Asphalt | X | X | |||
| 6 | sealants | X | X | |||
| 7 | fasteners | X | X | |||
| 8 | insulation | X | X | |||
| 9 | base sheet | x | x | |||
| 10 | intermediate plys | x | x | |||
| 11 | cap sheet | x | x | |||
| 12 | surface coating | x | x | |||
| Schedule of Material Submittals Template, Feb 2010 (SAF/AQCP) |