Approved Amendment.doc

DOC document 69 KB Posted

Attached to
Paving Indefinite Delivery/Indefinite Quantity (IDIQ), Randolph AFB, TX Federal contract opportunity
Solicitation number
FA3089-12-R-0001
Issued by
Department of the Air Force Air Education and Training Command

About this file

The Following are attached 1) FA3089-12-R-0001 Paving IDIQ Amendment 0002 2) Revised Attachment 9 SAMPLE dated Aug 12 Please Note Clarification on the Coefficient The Coefficient is the number which is applied to the RSMeans bare cost minus the City Cost Index (CCI) to arrive at the contractual cost of the work. For Instance a coefficient of 1.08 means the contractor will perform for an 8 markup. A coefficient of .90 would mean the contractor would perform for a 10 discount. This number is.

View the file

Other files for this federal contract opportunity

Other files attached to Paving Indefinite Delivery/Indefinite Quantity (IDIQ), Randolph AFB, TX, newest first.
File Type Posted
Attachment 9 Revised 28 Aug 12.zip ZIP file
Attachment 9 Revised 28 Aug 12.pdf PDF
Attachment 10 AETC 47 AETC 51.pdf PDF
Amendment 0001.zip ZIP file
RFP FA3089-12-R-0001 Paving IDIQ.zip ZIP file
Atch 2- Specs.zip ZIP file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

The following items are applicable to this modification:

SUMMARY OF CHANGES

1. The purpose of this amendment is to incorporate changes made to Sections H, Section J (replace SOW dated 25 May 2012 with revised SOW dated 15 August 12), and Section L of the RFP.

2. The following items are applicable to this amendment:

A. SECTION H – SPECIAL CONTRACT REQUIREMENTS

FROM:

H-3.1 RS MEANS, COEFFICIENT, AND CITY COST INDEX

a. Bare Cost Total in the current year's e4Clicks Project Estimating Software System (E4CLICKS) and the current year's R.S. Means Facilities Construction Cost Data book Published by R.S. Means, Inc. Bare Costs as referred to in the R.S. Means Facilities Construction Cost Data Book is the installed price.

b. In order to be considered for award, the offeror must submit a coefficient for Contract Line Item Number (CLIN) 0001 and the completion of pricing for unfunded proposal preparation costs based upon projects with a Statement of Work. The coefficient is the price multiplier that the contractor offers. The Government uses this multiplier to apply to the total costs to arrive at the price for an individual Delivery Order. The Government established unit prices listed in the E4CLICKS (material, equipment, and labor without any markups for material, equipment, labor, subcontractor, sales tax, overhead, or profit), multiplied by the average City Cost Index (CCI) percentage for San Antonio, Texas, multiplied times the coefficient to arrive at the actual price for the delivery order. The coefficient shall be represented as net, a decrease from or an increase to the prices listed in the E4CLICKS. An offer of net would be represented as 1.00. An example of a decrease from the prices in the E4CLICKS would be 0.98. An example of an increase above the prices in the E4CLICKS would be 1.06.

c. The offeror's price percentage factor (coefficient) shall contain all costs other than the pre-priced unit prices contained in the current version of RS Mean Cost Data and non-pre-priced items. The coefficient is a numerical factor that represents the contractor's costs. The coefficient must be sufficient to cover all cost including but not limited to items the following items: general & administrative expenses; home office expense and field overhead; as-built drawings; insurance; material delivery expenses; material submittals; computer and software expense; quality contract management and supervision; safety; site security; overhead; profit; project indirect and direct costs; bond premiums; licenses; certifications; basic contract mobilization and basic contract demobilization expense; traffic cones and barricades; gross receipts tax; general conditions (superintendent salaries); all labor burden costs (prime and subcontractor); material waste; consultant fees; subcontractor costs to include but not limited to overhead and profit; on and off site storage; as well as costs associated with compliance of environmental, labor, and tax laws, or these specifications. The offeror's coefficient should consider the above expenses because allowance will NOT be made after contract award for any purpose. The coefficient will not be adjusted for the life of the contract.

(1) Mobilization for rental equipment for each delivery order will only be whatever is allowed and addressed via RS Means Cost Estimating Guide line items for mobilization for the particular equipment to be used.

(2) Any change in the applicable minimum hourly rate of wages (Davis-Bacon Wage Determinations) during the contract period shall not affect the unit price to be paid by the Government for work performed under this contract. (See Section J and FAR Clause 52.222-6)

d. PRICING COEFFICIENTS: The purpose of applying the coefficient to direct pre-priced costs from the E4CLICKS is to compensate the contractor for burden costs and profit for performance. The pricing coefficient is not subject to economic price adjustments and the coefficient shall remain unchanged during the life term of the contract.

e. E4CLICKS Increase/decrease of any cost in the work performed are determined by the applicable current year's e4Clicks Project Estimating Software System and the current year's R.S. Means Master Composite Cost Data book published by R.S. Means, Inc. provided by and required to be used by the contractor.

f. CITY COST INDEX (CCI) QUARTERLY UPDATES: The contractor shall notify the Government of any quarterly changes to the City Cost Index (as a result of quarterly division level updates) and the changed CCI will take effect within 15 calendar days from the date of the notification by RS Means. The purpose of allowing for quarterly updates is to use the most current RS Means pricing information available from which to price out proposals or modifications.

g. Modifications to existing delivery orders: Modifications deleting work will be at the CCI in effect at the time of award of the delivery order or at the CCI in effect when the affected work was added (if added via modification after award of the respective delivery order). Modifications adding work shall be at the CCI in effect at the time of adding the additional work to the delivery order.

TO:

H-3.1 RS MEANS, COEFFICIENT, AND CITY COST INDEX

a. Bare Cost Total in the current year’s e4Clicks Project Estimating Software System (E4CLICKS) and the current year’s R.S. Means Master Composite Cost Data book published by R.S. Means, Inc. Bare Costs as referred to in the R.S. Means Master Composite Cost Data Book is the installed price.

b. In order to be considered for award, the offeror must submit a coefficient for Contract Line Item Number (CLIN) 0001 and the completion of pricing for unfunded proposal preparation costs based upon projects with a Statement of Work. The coefficient is the price multiplier that the contractor offers. The Government uses this multiplier to apply to the total costs to arrive at the price for an individual Delivery Order. The

Government established unit prices listed in the E4CLICKS (material, equipment, and labor without any markups for material, equipment, labor, subcontractor, sales tax, overhead, or profit), multiplied by the division level City Cost Index (CCI) percentage for San Antonio, Texas, multiplied times the coefficient to arrive at the actual price for the delivery order. The coefficient shall be represented as net, a decrease from or an increase to the prices listed in the E4CLICKS. An offer of net would be represented as 1.00. An example of a decrease from the prices in the E4CLICKS would be 0.98. An example of an increase above the prices in the E4CLICKS would be 1.06.

c. The offeror’s price percentage factor (coefficient) shall contain all costs other than the pre-priced unit prices contained in the current version of RS Mean Cost Data and non-pre-priced items. The coefficient is a numerical factor that represents the contractor’s costs. The coefficient must be sufficient to cover all cost including but not limited to items the following items: general & administrative expenses; home office expense and field overhead; as-built drawings; insurance; material delivery expenses; material submittals; computer and software expense; quality contract management and supervision; safety; site security; overhead; profit; project indirect and direct costs; bond premiums; licenses; certifications; basic contract mobilization and basic contract demobilization expense; traffic cones and barricades; gross receipts tax; general conditions (superintendent salaries); all labor burden costs (prime and subcontractor); material waste; consultant fees; subcontractor costs to include but not limited to overhead and profit; on and off site storage; as well as costs associated with compliance of environmental, labor, and tax laws, or these specifications. The offeror’s coefficient should consider the above expenses because allowance will NOT be made after contract award for any purpose. The coefficient will not be adjusted for the life of the contract.

(L) Mobilization for rental equipment for each delivery order will only be whatever is allowed and addressed via RS Means Cost Estimating Guide line items for mobilization for the particular equipment to be used.

(2) Any change in the applicable minimum hourly rate of wages (Davis-Bacon Wage Determinations) during the contract period shall not affect the unit price to be paid by the Government for work performed under this contract. (See Section J and FAR Clause 52.222-6)

d. PRICING COEFFICIENTS: The purpose of applying the coefficient to direct pre-priced costs from the E4CLICKS is to compensate the contractor for burden costs and profit for performance. The pricing coefficient is not subject to economic price adjustments and the coefficient shall remain unchanged during the life term of the contract.

e. Increase/decrease of any cost in the work performed are determined by the applicable current year’s e4Clicks Project Estimating Software System and the current year’s R.S. Means Master Composite Cost Data book published by R.S. Means, Inc. provided by and required to be used by the contractor.

f. CITY COST INDEX (CCI) QUARTERLY UPDATES: The contractor shall notify the Government of any quarterly changes to the City Cost Index (as a result of quarterly division level updates) and the changed CCI will take effect within 15 calendar days from the date of the notification by RS Means. The purpose of allowing for quarterly updates is to use the most current RS Means pricing information available from which to price out proposals or modifications.

g. Modifications to existing delivery orders: Modifications deleting work will be at the CCI in effect at the time of award of the delivery order or at the CCI in effect when the affected work was added (if added via modification after award of the respective delivery order). Modifications adding work shall be at the CCI in effect at the time of adding the additional work to the delivery order.

B. Section J- List of Documents, Exhibits and Other Attachments

Delete and Replace Section J, Attachment 1 (Statement of Work) with the revised Statement of Work dated 15 August 2012:

ATTACHMENTS, DOC & EXHIBITS

LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

DOCUMENT TYPE

DESCRIPTION

PAGES

DATE

Attachment 1

Statement of Work (Revised)

15 Aug 12 C. Section L- Instructions to Offerors

FROM:

L-2.3.

PART I – PRICE PROPOSAL – Submit 2 copies (original and one copy) and 1 electronic copy (CD). Data on the CD must conform to Windows 7 and Microsoft Office 2010, Word and Excel. Limit the price proposal to the following:

(a) Complete blocks 14 through 20c of the RFP Section A, SF 1442. In doing so, the offeror accedes to the contract terms and conditions as written in the RFP Sections A through K. These sections constitute the model contract.

(b) Provide your Price Proposal for your coefficient formatted as shown by Section J, attachment 9.

(c) Complete the fill-ins and certifications in Sections I through K. Section K shall be returned in its entirety. For Sections C through I, the offeror shall submit only those pages requiring a fill-in.

(d) Reserved.

(e) Bonding: Provide a letter from your Surety that the Prime Contractor has the ability to obtain annually $3.0M in performance and payment bonds that is supported with an A.M. Best company rating of “A”.

PART II – TECHNICAL PROPOSAL - Submit 2 copies (original and one copy) and 1 electronic copy (CD). Data on the CD must conform to Windows 7 and Microsoft Office 2010, Word and Excel. The technical proposal should be specific and complete and is limited to five (5) pages. Legibility, clarity and coherence are very important.

(a) Subfactor 1: Management of Multiple Projects. The offeror shall submit sufficient documentation to demonstrate they have experience in the successful management and execution of multiple (4 or more) paving projects (i.e. sidewalks, airfields, roads, parking lots, runways, curbs, gutters) during the same period of time within the past 3 years. Provide the project titles, a brief description of the project scope, project location (city and state), and project cost (minimum of $100K). Provide project owner’s contact information (name and telephone number).

PART III – PAST PERFORMANCE INFORMATION - Submit 2 copies (original and one copy) and 1 electronic copy (CD). Data on the CD must conform to Windows 7 and Microsoft Office 2010, Word and Excel. Limit the past performance information to no more than 10 pages in total to include all back up/supporting documentation, except performance questionnaires.

(a) The Offeror shall provide, as a minimum, a list of their past performance data from Federal, State and Local Government and private industry contracts, to include the offeror’s, critical subcontractors, teaming contractors and/or joint venture partners (i.e., each entity’s). All the items identified below shall be addressed in the listing. Elaborate listing and extensive comments are not required or requested.

1. Contract number, type.

2. Whether the offeror performed as the prime or a subcontractor.

3. Name of contracting office and verified name, address, phone/fax number of points of contact.

4. Project Title and/or brief description of construction project.

5. Initial price and final or current price, Contract start date, scheduled completion date, and current or final completion date.

6. Percent complete as of the date of submission of the proposal; and

7. Brief comments, if desired

( b). Provide this data for a minimum of three (3) and a maximum of five (5) relevant and recent contracts. Recent contracts are defined as performance occurring or completed within the last three (3) years through the solicitation release date (Block 3 of the SF 1442). Relevant contracts must be valued over $100K and must demonstrate an ability to handle multiple projects such as new construction, renovation, alteration and repair work, additions/upgrades, and other major trades and previous working relationships between working parties on similar projects.

(c). Should Offerors wish to provide information on problems encountered on the identified contracts and their corrective actions in accordance with FAR 15.305(2), they shall submit such information at the same time references are submitted

L-2.4. Questionnaires: The offeror shall email or fax Past Performance Questionnaires (Section J, Attachment 6) to include the offeror’s, critical subcontractors, teaming contractors and/or joint venture partners (i.e., each entity’s) to those agencies/firms responsible for the solicitation and administration of those identified projects identified above in paragraph (a). The responsibility to send out the Past Performance Questionnaires rests solely with the offeror. Once the Past Performance Questionnaires are completed by your POCs, the information contained therein shall be considered sensitive and shall not be released to you, the offeror. Questionnaires shall be sent directly back to the Government to the address listed in Block 7 of the SF 1442.

L-2.5. Subcontractor Consent: Past performance information pertaining to a subcontractor cannot be disclosed to the prime offeror without the subcontractor’s consent. Provide a subcontractor/Teaming Partner, Joint Venture Consent Form, from all that will perform major or critical aspects of the requirement, consenting to release of their past performance information to the prime contractor.

L-2.6. Documents submitted in response to this RFP must be fully responsive to and consistent with the following:

1. Requirements of the RFP as stated in Section L.

2. Evaluation Factors for Award in Section M of this RFP.

3. Any limitation on the number of proposal pages. Pages exceeding the page limitations set forth in this Section L will not be read or evaluated, and will be removed from the proposal.

4. Format for proposal Parts II and III shall be as follows:

(a) The proposals will be 8 1/2” x 11” paper except for fold-outs used for charts, tables, or diagrams, which may not exceed 11” x 17”.

(b) A page is defined as one face of a sheet of paper containing information.

5. Typing shall not be less than 12 pitch.

6. Elaborate formats, bindings or color presentations are not desired or required.

TO:

L-2.3.

PART I – PRICE PROPOSAL – Submit 2 copies (original and one copy) and 1 electronic copy (CD). Data on the CD must conform to Windows 7 and Microsoft Office 2010, Word and Excel. Limit the price proposal to the following:

(a) Complete blocks 14 through 20c of the RFP Section A, SF 1442. In doing so, the offeror accedes to the contract terms and conditions as written in the RFP Sections A through K. These sections constitute the model contract.

(b) Provide your Price Proposal for your coefficient formatted as shown by Section J, attachment 9.

(c) Complete the fill-ins and certifications in Sections I through K. Section K shall be returned in its entirety. For Sections C through I, the offeror shall submit only those pages requiring a fill-in.

(d) Reserved.

(e) Bonding: Provide a letter from your Surety that the Prime Contractor has the ability to obtain annually $3.0M in performance and payment bonds that is supported with an A.M. Best company rating of “A”.

PART II – TECHNICAL PROPOSAL - Submit 2 copies (original and one copy) and 1 electronic copy (CD). Data on the CD must conform to Windows 7 and Microsoft Office 2010, Word and Excel. Legibility, clarity and coherence are very important.

(a) Subfactor 1: Management of Multiple Projects. The offeror shall submit sufficient documentation to demonstrate they have experience in the successful management and execution of multiple (4 or more) paving projects (i.e. sidewalks, airfields, roads, parking lots, runways, curbs, gutters) during the same period of time within the past 3 years. Provide the project titles, a brief description of the project scope, project location (city and state), and project cost (minimum of $100K). Provide project owner’s contact information (name and telephone number).

PART III – PAST PERFORMANCE INFORMATION - Submit 2 copies (original and one copy) and 1 electronic copy (CD). Data on the CD must conform to Windows 7 and Microsoft Office 2010, Word and Excel.

(a) The Offeror shall provide, as a minimum, a list of their past performance data from Federal, State and Local Government and private industry contracts, to include the offeror’s, critical subcontractors, teaming contractors and/or joint venture partners (i.e., each entity’s). All the items identified below shall be addressed in the listing. Elaborate listing and extensive comments are not required or requested.

1. Contract number, type.

2. Whether the offeror performed as the prime or a subcontractor.

3. Name of contracting office and verified name, address, phone/fax number of points of contact.

4. Project Title and/or brief description of construction project.

5. Initial price and final or current price, Contract start date, scheduled completion date, and current or final completion date.

6. Percent complete as of the date of submission of the proposal; and

7. Brief comments, if desired

( b). Provide this data for a minimum of three (3) and a maximum of five (5) relevant and recent contracts. Recent contracts are defined as performance occurring or completed within the last three (3) years through the solicitation release date (Block 3 of the SF 1442). Relevant contracts must be valued over $100K and must demonstrate an ability to handle multiple projects such as new construction, renovation, alteration and repair work, additions/upgrades, and other major trades and previous working relationships between working parties on similar projects.

(c). Should Offerors wish to provide information on problems encountered on the identified contracts and their corrective actions in accordance with FAR 15.305(2), they shall submit such information at the same time references are submitted

L-2.4. Questionnaires: The offeror shall email or fax Past Performance Questionnaires (Section J, Attachment 6) to include the offeror’s, critical subcontractors, teaming contractors and/or joint venture partners (i.e., each entity’s) to those agencies/firms responsible for the solicitation and administration of those identified projects identified above in paragraph (a). The responsibility to send out the Past Performance Questionnaires rests solely with the offeror. Once the Past Performance Questionnaires are completed by your POCs, the information contained therein shall be considered sensitive and shall not be released to you, the offeror. Questionnaires shall be sent directly back to the Government to the address listed in Block 7 of the SF 1442 and submitted prior to or no later than the proposal due date.

L-2.5. Subcontractor Consent: Past performance information pertaining to a subcontractor cannot be disclosed to the prime offeror without the subcontractor’s consent. Provide a subcontractor/Teaming Partner, Joint Venture Consent Form, from all that will perform major or critical aspects of the requirement, consenting to release of their past performance information to the prime contractor.

L-2.6. Documents submitted in response to this RFP must be fully responsive to and consistent with the following:

1. Requirements of the RFP as stated in Section L.

2. Evaluation Factors for Award in Section M of this RFP.

3 It is preferred proposals be 8 1/2” x 11” paper except for fold-outs used for charts, tables, or diagrams, which may not exceed 11” x 17”.

5. Elaborate formats, bindings or color presentations are not desired or required.

All other provisions, clauses and attachments remain unchanged.

(End of Summary of Changes)