Statement of Work

View the file

Other files for this federal contract opportunity

Other files attached to Bldg 944 Asbestos Abatement, newest first.
File Type Posted
Questions_from_Bldg_944_Asbestos_Abatement_Site_Visit.docx DOCX document
FA3022-15-T-0004-0002.pdf PDF
FA3022-15-T-0004-0001.pdf PDF
FA3022-15-T-0004.pdf PDF
Asbestos_Location_Drawing.pdf PDF
Wage_Determination.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

FOR

ASBESTOS ABATEMEMT – BUILDING 944

EEPZ 15-1004

28 May 2015

I. PROJECT INFORMATION GENERAL SCOPE

A. The Contractor shall provide all plant, labor, equipment, transportation, and tools necessary to perform an asbestos abatement in Building 944 at Columbus Air Force Base. Perform all work according to this Statement of Work (SOW), the Concept Design Drawings, and all related AF requirements and other codes and references.

II. OUTLINE of WORK Provide all design and construction necessary to…

A. Interior

1. HVAC & TSI

a. Remove all Asbestos Duct Mastic.

b. Remove all Thermal Systems Insulation (TSI) and Joints.

B. General Design & Construction Requirements:

1. Basic Items of work are as follows:

a. Remove and Dispose of all Asbestos Containing Duct Mastic at Building 944.

b. Remove and Dispose of all Asbestos Containing Thermal Systems Insulation and Joints.

c. Contractor shall perform this asbestos abatement in accordance with the requirements of the EPA, OSHA and Mississippi Department of Environmental Quality (MDEQ).

d. Housekeeping practices must be maintained including: proper storage, use, and disposal of materials (i.e., petroleum products, paints/solvents, acids, and detergents); sanitary waste management (i.e., portable toilets); and trash/debris containment (i.e, prevent entry into nearby waterways and storm drains).

III. GOVERNMENT FURNISHED EQUIPMENT OR MATERIALS

The Government will not furnish any equipment or materials.

IV. OTHER

1. The Contractor shall immediately notify the Contracting Officer and secure any documents found with classified, “For Official Use Only” (FOUO) or personal information. The Contracting officer will direct disposition of these documents.

Attachment 1

2. A copy of the 10-day notification to proceed work will be provided to the Contacting Office and Environmental Flight.

3. The Contractor and all employees in this abatement must have Mississippi State Certification for Asbestos Abatement, and these certifications must be submitted to the Contracting Office and Environmental Flight before start date of work.

4. The Contractor shall submit an Asbestos Removal Plan within 5 days after award of contract.

5. All Disposal Manifests shall be reviewed and signed by 14CES/CEIE.

6. The Containers used to ship the asbestos containing materials off-base shall be inspected by the Contractor, that all bags have been double bagged, wet and labeled and/or bag wraps have been wrapped with 6 Mil Poly, wet, labeled, and sealed. 14CES/CEIE reserves the right to ensure compliance at any time.

7. The contractor shall be subject to no-notice inspections under the Occupational Safety and Health Act (OSHA) Program by Inspectors of the Department of Labor.

8. The Contractor shall ensure that provisions are taken to prevent asbestos containing material from becoming airborne. These provisions require approval from 14CES/CEIE.

9. The Contractor shall take positive action to prevent work-generated refuse from entering the sewer system.

All contractor generated refuse and waste shall be hauled from the construction site daily to a disposal area located outside the physical boundaries of the installation. This refuse and waste material shall be hauled in trucks with tight-fitting beds and covers to prevent spillage on roadways. The construction site shall be kept neat, orderly, and safe for workmen at all times. Manifests and material shall be reviewed by the Environmental Flight before asbestos material is taken off base.

10. The Contractor shall visit the job site to verify location, conditions, Linear Feet of Duct and TSI, and dimensions prior to starting work.

11. Toilet facilities may not be available for use by Contractor personnel. When not available the Contractor shall provide portable toilet facilities. All facilities shall be left in a clean state after each use.

12. A person from the Contracting Office and Environmental Flight (14th CES/CEIEC) shall be the authorized government representative.

13. The Period of Performance (PoP) shall be 15 days after award of contract.

END OF STATEMENT OF WORK