Solicitation Amendment FA301020R00050001 SF 30.pdf

PDF 510 KB Posted

Attached to
DEMO AAFES Warehouse Federal contract opportunity
Solicitation number
FA301020R0005
Issued by
Department of the Air Force Air Education and Training Command

About this file

This amendment provides questions and answers related to the solicitation for demolition services at Keesler Air Force Base. The solicitation seeks demolition of an AAFES warehouse building and associated paving, backfilling, grading, and sodding. Key details include that the work includes furnishing labor, materials and equipment to demolish building 4503 and return the area to a natural state. The NAICS code is 238910 and size standard is $16.5 million. The estimated value is between $250,000 and $500,000. The performance period is 120 days from notice to proceed. The pre-solicitation was posted on November 27, 2019 with a closing date of December 31, 2019. The agency is the Department of the Air Force Air Education and Training Command.

View the file

Other files for this federal contract opportunity

Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

R

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBE

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Section C - Specification/SOW/SOO/ORD

Miscellaneous text in this section has been modified to:

Questions and Answers for FA301020R00050001 Demo AAFES Warehouse, Keesler AFB, MS

1. Can the fill material underneath the structures be used for re-grading the site or will new fill material be required? New fill will be required.

2. What procedure is required for decommissioning the monitoring wells? There are no monitoring wells at this site.

3. What is the depth of the well? There are no monitoring wells at this site.

4. Monitoring wells are typically used for hazardous waste - please confirm the wells do not contain any hazardous waste. There are no monitoring wells at this site.

5. Will the trees to be protected be identified by the base? There are no protected trees outlined at this site.

6. What procedure is required to protect the trees? There are no protected trees outlined at this site.

7. Is there any medical or chemical hazardous waste on site? No.

8. Can the fill material beneath the AAFES Warehouse be utilized as fill material for the job? No.

9. Is there a base fluorescent bulb program? Yes. Fluorescent bulbs will be dropped off at CE Environmental for recycling every Tuesday.

10. Is there a size limit on the trucks to be transporting equipment and waste across the Base? No.

11. Will alternate gates be available if any events held by the city block or slow the main route?

Contractor trucks and equipment shall enter base through the contractor gate. If route is blocked, alternative gate entry will be arranged by the base.

12. Will there be any weight restrictions on trucks traveling through the Base? Standard urban weight restrictions.

13. Is rail a possibility for transportation of waste? No.

14. Is a formal dust control plan required? Yes. Contractor may use nearby hydrant for dust control but must use backflow preventer and completely shut off valve with each use.

15. Would the contractor or Vectrus/CEV be responsible to write the dust control plan? Contractor

16. Are there any underground tanks within 200 feet of the demolition site perimeter or within the perimeter? No.

17. What are the tree and shrub preservation requirements? There are none required for this project.

18. What volume and pressure of water is available to water the sod with? Keesler water pressure is typically 40 - 70 psi.

19. Is there currently a connection to the water system that can be used? Contractor may use nearby hydrant.

20. Will the 60 day watering period be extendable beyond the performance period? Yes.

21. If it is able to pass the performance period, who will be responsible to mow the new sod during the watering period? Contractor.

22. Was this building or the site used as anything other than an AAFES warehouse in the past? If so, what? No.

23. Were there ever any recordable or known spills of any kind on any part of this demolition site in the past? No.

24. Were hazardous or radioactive materials of any kind ever stored on this site? No.

25. Has plumbing/drain piping been included in any environmental testing? No.

26. Was mercury, and other heavy metals, included in the environmental testing? No.

27. Is there any possibility of contaminates inside plumbing piping? No.

FA301020R00050001

28. Are there original architectural drawings and/or site plans of the building, including any additions or modifications, available? No.

29. Who is responsible for all underground locates of the entire demolition site and surrounding area?

Vectrus and City Light and Power (CLP) will locate utilities before demolition

30. Has a ground penetrating radar analysis been performed, including under the road, on the entire site? If so, are the results available? No.

31. Is the depth of the existing utilities shown on the plans available? No.

32. Will plumbing pipes require sealing of each section as they are removed? No.

33. Will expanding foam installed in the pipes before demolition act as an acceptable seal? Yes.

34. Are complete mechanical and electrical drawings available for the entire building? No.

35. Who is responsible to assure ALL alarms, monitoring systems, surveillance equipment, fiber optic cables, power systems, fuel systems, control systems and communication systems are completely disconnected and inoperable at the time of demolition start-up? Contractor. Fiber and all communication cables will be removed by COMM.

36. If contractor is responsible, will anything outside of the demolition sight be possibly affected or tripped due to anything within the demolition area? No.

37. Are there any special concerns as to protecting greenery not included in the scope of work for removal? No.

38. Will the contractor be responsible for plants dying as a result of roots being damaged that encroach upon the demolition site? No.

39. Is any demolition on the site on railroad property? Will this require additional permitting? No.

40. Does anything left in the building contain radioactive particles and was it tested for radioactivity?

No.

41. Who will be responsible to terminate the fire main prior to demolition? Contractor.

42. Will all waste container contents need to be tested before leaving the Base? If so, how long will the contents be allowed to sit on Base to allow for testing? Who will be responsible for the testing? No waste containers sans asbestos abatement will need testing for this project.

43. Is there backflow prevention on the sewer or will we need to install those before demolition?

Sewer for this building is a gravity main. No backflow prevention is required.

44. Will any operations on the base slow, halt or hinder the demolition and waste removal process besides the Special Olympics? If so, what will the duration of these activities be? Will there possibly be alternate routes to move materials and minimize delays? No. 81 CONS will notify contractor of any unforeseen activity on base that will affect demolition. Any time or material delays will be noted, and alternate route, if needed due to road closures, will be provided at this time.

The Requirements text has been modified to:

MAHG18-1095 Demo AAFES Warehouse WO #81770

FA301020R00050001

IDCode:
Page: 1
Pages: 3
AmendNo: 0001
EffDate: 12/17/2019
ReqNo: F2J31D9301AW02
ProjNo: MAHG18-1095
IssCode: FA3010
AdmCode:
IssuedBy: FA3010 81 CONS CC

CP 228 377 3230

310 M ST BLDG 4605

KEESLER AFB, MS 39534-2701

United States Clayton Petrie, Email: clayton.petrie@us.af.mil Telephone: 228-377-1807

AdminBy:
ContractorNameAdd:
Code:
FacCode:
SolChg: 1
SolNo: FA301020R0005
SolDate: 11/26/2019
AwardChg:
AwardNo:
AwardDate:
Amended: 1
OffrExt:
OffrNoEx: 1
NoCopies: 1
ApprData: See Section G
ChgeOrd:
ChgeOrder:
Modify:
SuppAgre:
SuppAuth:
ModOthr:
OthrSpec:
NoReq: Off
Require:
Copies:
Descript: The purpose of this amendment is to provide questions and answers from the site visit.
ContNameTitle:
CoNameTitle: Katie Fulford

Email: katie.fulford.1@us.af.mil Telephone: 228-377-5504

ContDate:
CODate: