Attachment_1_MAHG151012_Specs.pdf
PDF 3 MB Posted
- Attached to
- Repair HVAC System, Base Supply Bldg 4002 Federal contract opportunity
- Solicitation number
- FA3010-16-R-0009
About this file
Specifications
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Site_Visit_Sign_In.pdf | ||
| Attachment_5_Past_Performance_Reference_List.rtf | RTF text file | |
| Attachment_4_Performance_Questionnaire.doc | DOC document | |
| Attachment_2_MAHG151012_Drawings.pdf | ||
| FA3010-16-R-0009_Solicitation_HVAC_Base_Supply.pdf | ||
| Attachment_3_WD_MS160119.doc | DOC document | |
| Attachment_7_Notice_of_Compliance.doc | DOC document | |
| Attachment_6_SF_1444.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT:
4002 REPAIR HVAC TAYLOR LOGISTICS
PROJECT NUMBER:
MAHG-151012
100% Submittal
KEESLER AIR FORCE BASE
BILOXI, MISSISSIPPI
STEPHENS MECHANICAL ENGINEERING
925 TOMMY MUNRO DR., STE B June 13, 2015
BILOXI, MS 39532
228 207 3322
MAHG 15-102
Repair HVAC Taylor Logistics
Biloxi, Mississippi
Addendum-1
March 21, 2016
Specifications:
1. Section 01000 Keesler Paragraph 2.1-A: Omit Paragraph and insert:
“A. The warehouse areas of the building will remain functional and operational; the office areas in the south end of the building shall be vacated for this project. Rm 128 and adjacent office shall be occupied with PAE supplying temporary air. The room shall be prepared immediately in project.
The existing ceiling and lights shall be removed, insulation disposed of, any devices temporarily wired out of way, and the existing plywood deck above removed. The existing fencing above shall be rolled back as contractor deems necessary to perform work. The attached condensate drain will be rerouted or lowered to allow access. With chillers down the unit served by the drain will be inactive. Currently the room has steel bar joists four foot on center with 2x4 stringers bolted on top with the plywood (rotted) attached to stringers.
Remove the split system unit associated with the space in its entirety.
Contact HVAC shop to retrieve refrigerant prior to demolition. Replace all plywood with new ¾” CDX screwed to new stringers on 16” centers. Deck shall completely cover the offices below. The deck will serve as a work platform and allow work above occupants for safety. However, schedule removal of return fan at a time when occupants are not there as this is a heavy unit. Upon completion of deck return inside and install new lights, grid, 6” batt insulation on ceiling tile, and do not install grilles at this time. Once the new main ductwork above is ready for operation with new air handler and chill water system operational, then return to Rm 128 and adjacent office to install the VAV boxes, supporting ductwork, grilles, and the controls. It will be necessary to cut holes in deck for grilles. Minimize hole sizes and number of holes where possible. The fencing above with condensate drain will be restored. PAE will then remove temporary cooling.”
2. Section 01000 Keesler Paragraph 3.1-A: Omit Paragraph and insert:
A. “It is the intent of this project to completely renovate the HVAC system serving the office areas of the building. The existing chill water system and the chillers shall be completely demolished with subsequent replacement. The entire airside side shall also be demolished and replaced with a new VAV system.
The heating system shall remain less the small heating water pump currently serving the offices. A new pump with accessories and connecting piping shall be installed. Exterior work shall occur to re-pipe the chillers with a reverse return system. All asphalt shall be replaced as currently shown by plans. All unused penetrations into the warehouse shall be sealed for 2 hour fire ratings.
All ductwork penetrating wall shall be fire protected with a damper per UL standards. There are several penetrations that will be enlarged using a concrete saw. The office areas will be vacated for this project. Additional offices occur in the warehouse area along south wall that currently has ductwork and piping to be removed over and in it and will be included in work.
The main ductwork and hot/chill water piping will be extended through the warehouse south end over those existing offices. A new plywood deck will be installed over Rm 128 and the pickup/delivery office. This work shall occur first as this office will immediately be used as an occupant rotation space. Provide tarps over weapons storage and storage that may remain to insure accidental flooding does not occur. The contractor shall coordinate work in those areas for access. The security fencing above the warehouse offices, in way of work, shall be removed and restored to allow access to existing ductwork and piping as well as installation of new. Also, a future chill water loop will be added through the warehouse area. That area will be occupied and all work must be coordinated for access as this is a secure area. “
2.3. Section 19500 Paragraph 2.3-A: Omit requirement for a personal computer and peripheral hardware.
Drawings:
1. Sheet M101:
A. Security Notes: Omit sentence: “Some phasing may occur to allow access only to the west side of the office, then when complete, the east side will be turned over for work”. Office areas will be vacated for duration of work.
B. Add Note: Fencing above offices in way of work within warehouse area will be removed and restored with work complete.
2. Sheet M102:
A. Security Notes: Omit sentence: “Some phasing may occur to allow access only to the west side of the office, then when complete, the east side will be turned over for work”. Office areas will be vacated for duration of work.
B. Add Note: Fencing above offices in way of work within warehouse area will be removed and restored with work complete.
C. Add Note: Remove existing split system HVAC equipment in its entirety for Rooms 112 and 115A. Existing controls, fan coils, condensing units, refrigerant piping, grilles (less return grille as a large hole would be left), ductwork, equipment pads, and condensate systems shall be removed. Patch holes in walls with grout to match wall color, repair sheet rock finishes and paint to match where thermostats and grilles occurred, seal roof penetrations where occurring, replace any damaged ceiling tiles from this work, and leave closet as is. Contact HVAC shop to pull refrigerant prior to work and dispose of decommissioned units.
3. Sheet M103:
A. Provide temporary portable roll around cooling unit (1.25 ton minimum) for Rm 126.
B. Provide and install protection for server rack in Rm 123, install plastic tent loosely around it with roll around 1 ton HVAC unit blowing into plastic tent.
C. Above ductwork leaving AHU room (36x32 and 42x24) and in ahu room are two rows of sprinkler heads, engage a sprinkler contractor to evaluate the installation of the ductwork and provide/ relocate heads with offsets to drop down below bottom face of ductwork for correct coverage.
D. Install the following for the AHU double door after rerouting electrical conduit above doorway.
1. Saw cut mortar joint above new opening 16" past each side of cut. Insert a 4x4x3/8" steel angle as a lintel. Prime and paint before inserting.
2. Saw cut block 8" past required opening and below new lintel.
3. Remove block and clean edges and slab.
4. Insert new frame and new 8x8" block each side. Tie to existing wall and provide ties for new frame. Grout solid.
5. Prime and paint to match existing.
6. Co-ordinate with the HVAC CEOM to have the lockset properly keyed for a KAFB mechanical room.
2. Siemens has installed a new duct smoke detectors. Contact Siemens to remove units when demolishing existing and then contact them to reinstall to new units.
4. Sheet M104:
A. Provide temporary portable roll around cooling unit (1.25 ton minimum) for Rm
129. This room number not on drawing bit is IT room located on that sheet served by VAV 49.
B. Provide temporary de-humidifier for the Weapons Vault before shutting down climate control unit or central chilled water system. Unit should be capable of removing a minimum capacity of 1 pint/hr.
C. Remove sheet rock ceilings in rms 115,116,117,119 including vestibules.
Remove grilles, lights, and other appurtenances. Reinstall ceiling once HVAC ducting is complete with new moisture resistant ceiling tile, grid (aluminum for corrosion resistance), new grilles (use new cube core exhaust grilles to match existing size), and lights per electrical addenda.
D. Above ductwork leaving AHU room (50x35 and 42x20) and in ahu room are two rows of sprinkler heads, engage a sprinkler contractor to evaluate the installation of the ductwork and provide/ relocate heads with offsets to drop down below bottom face of ductwork for correct coverage.
E. Siemens currently installing new duct smoke detectors. Contact Siemens to remove units when demolishing existing and then contact them to reinstall to new units.
5. Sheet 103:
There are match line discrepancies, omit match line designations and replace with corresponding designations per below:
WAS IS
301 104
6. Sheet 104:
with corresponding designations per below:
301 103
7. Sheet 105:
with corresponding designations per below:
601 106
8. Sheet 106 with corresponding designations per below:
501 105
9. Sheet 107:
with corresponding designations per below:
WAS IS
501 105
801 108
901 109
10. Sheet 108:
with corresponding designations per below:
501 106
901 109
1001 110
11. Sheet 109 with corresponding designations per below:
WAS IS
701 107
1001 110
12. Sheet 113
Change the second “Cooling Coil” in the “Air Handling Unit Schedule” to “Heating Coil”
13. Sheet 114
Add Pre-Heat Coil and automatic control valve to drawing 1/114, AHU – 1, 2 Control Sequence.
14. Sheet E000 – Luminaire Schedule
A. Add Luminaire Type “W4” to the schedule. Fixture shall be:
Equal to DAY-O-LITE VL-1644-DI-2-T8-WM-4-CC-UNV with (2) F32T8-4100 lamps.
15. Sheet E101 – Electrical Demolition Notes
A. Change Note 3 to read: INSTALLATION OF NEW LIGHTING FIXTURES
SHALL BE CONNECTED TO EXISTING CIRCUITS SALVAGED FROM
DEMOLITION IN EACH RESPECTIVE AREA. NEW CONDUIT AND WIRING
SHALL BE INSTALLED IN EACH ROOM AS INDICATED. SEE NEW LIGHTING
PLAN FOR COORDINATION.
B. Change Note 4 to read: ALL EXISTING LIGHTING CIRCUITS SHALL REMAIN
FOR RECONNECTION TO NEW LIGHT FIXTURES. EXISTING SWITCHES IN
EACH AREA SHALL REMAIN AND SHALL OVERRIDE NEW OCCUPANCY
SENSORS FOR MANUAL CONTROL. SEE NEW LIGHTING PLAN FOR
COORDINATION.
16. Sheet E102 – Electrical Demolition Notes
A. Change Note 3 to read: INSTALLATION OF NEW LIGHTING FIXTURES
SHALL BE CONNECTED TO EXISTING CIRCUITS SALVAGED FROM
DEMOLITION IN EACH RESPECTIVE AREA. NEW CONDUIT AND WIRING
SHALL BE INSTALLED IN EACH ROOM AS INDICATED. SEE NEW LIGHTING
PLAN FOR COORDINATION.
B. Change Note 4 to read: ALL EXISTING LIGHTING CIRCUITS SHALL REMAIN
FOR RECONNECTION TO NEW LIGHT FIXTURES. EXISTING SWITCHES IN
EACH AREA SHALL REMAIN AND SHALL OVERRIDE NEW OCCUPANCY
SENSORS FOR MANUAL CONTROL. SEE NEW LIGHTING PLAN FOR
COORDINATION.
C. Add the partial plan 1/E102R shown on the attached for demolition work in the existing bathrooms.
17. Sheet E201 – Lighting Notes
A. Change Note 2 to read: INSTALLATION OF NEW LIGHTING FIXTURES MAY
REQUIRE ADDITIONAL CONDUITS, WIRING, AND FLEX CONDUITS FOR
FIXTURE WHIPS TO LOCATE FIXTURES IN NEW LOCATIONS. FIXTURES
SHALL BE CONNECTED TO EXISTING SWITCHED CIRCUIT FOR MANUAL
CONTROL OF LIGHTS. OCCUPANCY SENSOR SWITCHES SHALL BE
INSTALLED IN EACH ROOM AND/OR AREA FOR AUTOMATIC CONTROL OF
LIGHTS.
18. Sheet E201 – Specific Lighting Notes
A. Change Note 1 to read: INSTALL NEW 2-#12, 1-#12G IN 1/2" EMT AS
REQUIRED FOR NEW LIGHTING FIXTURES. CONNECT NEW LIGHTING
CIRCUIT TO EXISTING SWITCHED CIRCUIT SALVAGED DURING
DEMOLITION. NEW LIGHTING SHALL BE CONTROLLED BY OCCUPANCY
SENSORS AS SHOWN IN EACH AREA WITH OVERRIDE BY EXISTING
MANUAL TOGGLE SWITCHES. EMERGENCY BALLASTS SHALL BE
CONNECTED TO UNSWITCHED CIRCUIT IN THE SAME ROOM.
19. Sheet E202 – Lighting Notes
A. Change Note 2 to read: INSTALLATION OF NEW LIGHTING FIXTURES MAY
REQUIRE ADDITIONAL CONDUITS, WIRING, AND FLEX CONDUITS FOR
FIXTURE WHIPS TO LOCATE FIXTURES IN NEW LOCATIONS. FIXTURES
SHALL BE CONNECTED TO EXISTING SWITCHED CIRCUIT FOR MANUAL
CONTROL OF LIGHTS. OCCUPANCY SENSOR SWITCHES SHALL BE
INSTALLED IN EACH ROOM AND/OR AREA FOR AUTOMATIC CONTROL OF
LIGHTS.
20. Sheet E202 – Specific Lighting Notes
A. Change Note 1 to read: INSTALL NEW 2-#12, 1-#12G IN 1/2" EMT AS
REQUIRED FOR NEW LIGHTING FIXTURES. CONNECT NEW LIGHTING
CIRCUIT TO EXISTING SWITCHED CIRCUIT SALVAGED DURING
DEMOLITION. NEW LIGHTING SHALL BE CONTROLLED BY OCCUPANCY
SENSORS AS SHOWN IN EACH AREA WITH OVERRIDE BY EXISTING
MANUAL TOGGLE SWITCHES. EMERGENCY BALLASTS SHALL BE
CONNECTED TO UNSWITCHED CIRCUIT IN THE SAME ROOM.
B. Add the partial plan 1/E202R shown on the attached for new lighting and ceiling work in the existing bathrooms.
3.4. Section 19500 Paragraph 2.3-A: Omit requirement for a personal computer and peripheral hardware
Domestic Water Metering
Add the following:
Provide and install Disc Type Water Meter with Pulse Adapter:
1. Description:
a. Standard: AWWA C700.
b. Pressure Rating: 150-psig working pressure.
c. Body Design: Nutating disc; totalization meter.
d. Registration: In gallons.
e. Case: Bronze.
f. End Connections: Threaded.
Meter:
Size: 3” Meter: Neptune Tru/Flo or equal.
Pulse Adapter: RIO Tronics or equal.
Backflow Preventer: Watts LF957-NRS with Strainer and flanged connections or equal.
F2
F2
F2E
F2
F2E
W4
W4
W4
F2E
F2
F2E
F2
F2
W4
W4
W4
W4
PROJECT SPECIFICATION INDEX
Description Pages
1. Section 001020 Drawing List 1- 1
2. Section 001030 Summary of Project Work 1- 2
3. Section 010000 General Requirements with Keesler Supplements 1- 4
4. Section 010010 HVAC Coordination, Commissioning, and Close Out 1- 4
5. Section 011400 Work Restrictions 1- 2
6. Section 011500 Quality Requirements 1- 2
7. Section 013300 Submittal Procedure 1- 4
8. Section 013300 Project Schedule 1- 4
9. Section 013550 Environmental Protection 1- 6
10. Section 015000 Temporary Construction 1- 4
11. Section 017320 Selective Demolition 1- 3
12. Section 017700 Closeout Procedures 1- 2
13. Section 017800 Closeout Submittals 1- 5
14. Section 017825 Operation and Maintenance 1- 3
15. Section 020000 General Demolition 1- 6
16. Section 095100 Acoustical Ceilings 1- 6
17. Section 150000 Mechanical General Requirements 1- 7
18. Section 150500 Temporary Rental Equipment 1-5
19. Section 15100 Basic Materials and Methods 1- 9
20. Section 15200 Insulation od Mechanical Systems 1- 8
21. Section 15600 Heating, Ventilating and Air Conditioning Equipment 1- 8
22. Section 15700 Heating and Air Conditioning Piping 1- 3
23. Section 15800 Air Distribution 1-6
24. Section 15900 Controls 1- 4
25. Section 15950 Building Energy Management 1- 50
26. Section 16010 Basic Electrical Requirements 1- 6
27. Section 16050 Basic Electrical Materials and Methods 1- 4
28. Section 16060 Grounding and Bonding 1- 2
29. Section 16120 Low Voltage Conductors 1- 3
30. Section 16130 Raceways 1- 5
31. Section 16445 Panelboards, Safety Switches, Cabinets 1-4
32. Section 16500 Lighting 1-4
SECTION 00102
LIST OF DRAWINGS
SECTION 00102
PART 1 GENERAL
1.1 SUMMARY
This document lists the drawings for the project pursuant to contract clause "DFARS 252.236- 7001, Contract Drawings, Maps and Specifications."
1.2 CONTRACT DRAWINGS
Contract drawings are as follows:
DRAWING TITLE
NO.
Title Sheet, Vicinity Map, Location map, Index of Drawings
M101 HVAC DUCT, PIPING, CEILING DEMOLITION – SECTION A
M102 HVAC DUCT, PIPING, CEILING DEMOLITION – SECTION B
M103 HVAC PLAN - SECTION A
M104 HVAC PLAN – SECTION B
M105 HVAC PIPING PLAN – SECTION A
M106 HVAC PIPING PLAN – SECTION B
M107 HVAC PIPING PLAN – SECTION C
M108 HVAC PIPING PLAN – SECTION D
M109 HVAC PIPING PLAN – SECTION E
M110 HVAC PIPING PLAN – SECTION F
M111 ENLARGED MECHANICAL ROOMS AND DETAILS
M112 ENLARGED MECHANICAL ROOMS, DETAILS, AND SCHEDULES
M113 SCHEDULES AND DETAIL
M114 CONTROL SCHEMATICS AND SEQUENCES
M115 CONTROL SCHEMATICS AND SEQUENCE
M116 CONTROL SCHEMATICS AND SEQUENCE
A101 NEW CEILING WORK
A102 NEW CEILING WORK
E000 ELECT LEGEND AND SCHEDULES
E101 ELECTRICAL DEMOLITION PLAN-PART A
E102 ELECTRICAL DEMOLITION PLAN-PART B
E201 LIGHTING PLAN – PART A
E202 LIGHTING PLAN – PART B
E203 MECHANICAL SYSTEMS PLAN – PART A
E204 MECHANICAL SYSTEMS PLAN – PART B
-- End of Document --
SECTION 001030
SECTION 00 10 30
SUMMARY
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Description The project consists of the renovation and addition of the control systems for the Taylor Logistics building 4002. Work shall remove all exist ceilings, mechanical equipment, lights, selective electrical, ductwork, controls, piping, chiller, pumps and devices for the office area. The project shall replace all those mentioned with new ceilings, lights, hvac equipment, controls, and those items shown on plans. A new chill water loop will be extended through the warehouse section. All work shall comply with Base Standards to include National Electric Code, ASHRAE, SMACNA, and UL codes, standards, and listings. Fire protection, egress, and life safety will be maintained throughout project.
B. Location The project is located on Keesler Air Force Base, Biloxi, Mississippi. Building 4002.
C. In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
1. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remains.
2. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.
1.2 LOCATION OF UNDERGROUND FACILITIES
A. Obtain digging permits prior to start of excavation by contacting the Contracting Officer 15 calendar days in advance. Scan the construction site with electromagnetic or sonic equipment, and mark the surface of the ground paved surface where existing underground utilities or utilities encased in pier structures are discovered. Verify the elevations of existing piping, utilities, and any type of underground or encased obstruction not indicated to be specified or removed but indicated or discovered during scanning in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
1.3 NOTIFICATION PRIOR TO EXCAVATION
SECTION 001030
A. Notify the Contracting Officer at least 15 days prior to starting excavation work.
Contact Miss Utility 48 hours prior to excavating. Contractor is responsible for marking all utilities not marked by Miss Utility or base utilities shop.
PART 2 PRODUCTS
N O T U S E D
PART 3 EXECUTION
NOT USED
END OF SECTION
SECTION 01 00 00
KEESLER
PART 1 GENERAL
1.0 SUMMARY OF WORK
The project consists of the renovation and addition of the control systems for the Taylor Logistics building 4002. Work shall remove all exist ceilings, mechanical equipment, lights, selective electrical, ductwork, controls, piping, chiller, pumps and devices for the office area. The project shall replace all those mentioned with new ceilings, lights, hvac equipment, controls, and those items shown on plans. A new chill water loop will be extended through the warehouse section. All work shall comply with Base Standards to include National Electric Code, ASHRAE, SMACNA, and UL codes, standards, and listings. Fire protection, egress, and life safety will be maintained throughout project.
INCLUDE ALL WORK AS INDICATED ON DRAWINGS AND IN STRICT ACCORDANCE WITH THESE
SPECIFICATIONS AND APPLICABLE DRAWINGS AND SUBJECT TO TERMS AND CONDITIONS OF THE
CONTRACT.
A. All work shall be done in a neat and workmanlike manner and in keeping with generally accepted standards for similar work.
B. Contractor is responsible for field verifying all measurements and evaluating existing conditions.
1.1 WORKING CONDITIONS
The Contractor shall take all necessary and prudent safety precautions to ensure the safety of the workforce and other exposed personnel.
A. Underground Utilities: Protect all active utilities. Any damage to existing utility lines caused by the Contractor will be the Contractors responsibility.
B. Hazardous Electrical Exposure: Provide Safety protection and precautions for any electrical exposure.
C. Permits: Contractors will be required to obtain permits as required by Keesler in the performance of their work. Contractors shall post or have readily available all permits before work is commenced The following permits must be obtained anytime referenced work is required.
Dig Permit - PAE Customer Service Burn Permit - Keesler AFB Fire Department Confined Entry Permit, Certified Personnel - obtain permit from PAE project management personnel, or PAE safety office. Notification to fire department of actual day and time work is accomplished.
1.2 MATERIAL DELIVERY AND STORAGE
A. Delivery: The Contractor shall have all materials for his work delivered during normal working hours or shall have a representative present to receive shipments. The contractor should be particularly aware that all delivery vehicles must have sufficient information to locate project site. This includes name and address of the project site and name of prime contractor and a point of contact for delivery.
B. Storage: The Contractor shall be responsible for the storage of all material and equipment. All items shall be properly stored to maintain their original condition until actually installed.
1.3 REPAIR OF GOVERNMENT - OWNED FACILITIES
In order to complete the work on this job, certain GOVERNMENT-owned facilities may have to be removed or altered in some way and others may be inadvertently damaged. It is the responsibility of the Contractor to return these facilities to a condition acceptable to the
GOVERNMENT.
1.4 UTILITIES
A. All reasonable amounts of electricity and water required for the completion of this project will be furnished to the Contractor without charge from existing Government facilities where feasible.
1. INTERRUPTION OF UTILITY SERVICE: Interruptions to utility services shall be minimized. Necessary outages shall be coordinated with the GOVERNMENT a minimum of 21 days in advance of the planned outage.
2. TEMPORARY SANITARY FACILITIES: Portable sanitation units for this project shall be supplied by the contractor. This includes maintenance, transportation to and from job site, secure placement of unit as not to obstruct normal public activity, and unit clean-out as needed. The type units provided and the placement location(s) shall be approved by the GOVERNMENT.
3. STORM DAMAGE: Should warnings of winds of gale force or stronger be issued, the Contractor shall take every practical precaution to minimize danger to persons and damage to property. These precautions shall be coordinated through the GOVERNMENT, [government technical monitor] and shall include closing all openings; removing all loose materials, tools, and equipment from exposed locations; as well as removing or securing scaffolding and other temporary work. Contractor will follow Keesler requirements for Hurricane Conditions in force.
4. SAFETY: The Contractor shall observe all Safety, Security, Traffic and Fire regulations presently enforced at Keesler Air Force Base. And comply with latest issue of OSHA requirements.
1.5 CONSTRUCTION
A. Material: All material furnished by the Contractor for this job shall be new, unused material of high quality. All equipment and materials shall comply with the buy American act. Contractor shall notify Government if a deviation is required.
B. Cleaning: The Contractor shall maintain the premises, including any staging area or storage areas, free from accumulations of waste, debris, and rubbish caused by the Contractor’s work and shall minimize the spread of dust and flying particles. As work is completed, or at the end of each day, the site shall be cleaned and all waste material shall be properly disposed of.
1.6 JOBSITE MAINTENANCE AND STORAGE AREAS
A. The contractor shall maintain the jobsite and staging areas in conformance with Keesler standards.
B. Lay down/staging areas shall be kept neat and free of loose debris at all times. Grass shall be cut and maintained regularly. Height and maintenance shall be consistent with normal Base standards and consistent with the immediate area.
C. Jobsites and lay down/staging areas shall be enclosed with a 6’ chain link fence with brown fabric screening. Materials and equipment may be stored inside storage units.
Items stored in the lay down area shall be arranged neatly.
D. All temporary storage trailers and storage containers shall present a neat and clean appearance and shall be in a state of good repair and shall be located within the fenced area described in paragraph above.
E. If allowed by the contract and if approved by the GOVERNMENT, an office mobile unit may be located outside of a fenced area. At a minimum, this unit shall be in a paved area and shall present a neat, professional appearance. Unit shall be of Keesler standard colors, shall have presentable skirting and access stairs. Ancillary items, such as porches and canopies, shall be neat and painted Keesler brown. Contractor shall submit a picture of the proposed unit for approval and before unit is moved to Base.
F. Execution of work may require excavation or other type of work both at and away from primary work area. These areas shall be secured and work times shall be kept to a minimum. Open excavations shall be directly in progress or shall be covered directly after work complete. Open excavations requiring extended period of inactivity shall be temporarily backfilled. In no case shall an excavation be open for more than 72 hours.
Barricades, fences and other warning devices shall be maintained neatly at all times.
1.7 INTERUPTION OF MECHANICAL, ELECTRICAL, PLUMBING SERVICE
A. Interruptions to any mechanical, electrical or plumbing services shall be minimized.
Necessary outages shall be coordinated with the GOVERNMENT a minimum of 21 days in advance of the planned outage. The Contractor shall fill out a “Utility Service Outage Request Form” and submit it to the GOVERNMENT. The GOVERNMENT may require the contractor to attend a coordination meeting to access the purpose, intent, and impact of the outage request with the facility and any or all operations departments. Contractors shall not shut-down or start-up any mechanical, electrical or plumbing system without the coordination and/or permission of the GOVERNMENT.
1.8 Environmental Protection
A. Contractor personnel shall, at all times, perform all work and take such steps required to prevent any interference or disturbances to the ecological balance of the environment.
All work must be performed in accordance with applicable Federal, State, Local, and Air Force environmental regulations. Use good management practices to protect air, water, land and wildlife and to prevent noise, solid waste, radiant energy, dust and radioactive pollutants. In the event of a chemical or hazardous material spill, the contractor must immediately notify the Keesler Fire Department at 228-377-1839 and the GOVERNMENT representative at 228-377-8255.
B. Required Asbestos Abatement and Management Procedures:
1. These steps are in accordance with Air Force Instruction, EPA, and MDEQ.
OSHA governs all worker safety and must be complied with by contractors and subcontractors. These requirements are summarized in the Keesler Air Force Base Asbestos Operations and Management Plan. Please reference the Plan.
These steps are required by all personnel or contractors doing work on Keesler Air Force Base.
2. If the personnel or contractor encounters what they think may be asbestos, they are required to stop and call the KAFB Asbestos Point of Contact which is the Keesler Environmental Section. They can be reached at 228-377- 1262 or 228-377-3004 during duty hours and 228-348-0864 during off hours. Once it is determined by the Asbestos POC that asbestos is present, the following actions are required (Only the APOC and Bioenvironmental are certified to make that determination).
1.9 Security Requirements
A. The Contractor is responsible for obtaining passes to enter the installation. The contractor shall coordinate with GOVERNMENT to obtain approval and documentation for application of passes/ID.
2.1 BUILDING OCCUPANCY
A. Building(s) will remain operational and may be occupied during construction. Contractor shall perform all work during normal working hours except as otherwise approved to accommodate agreed upon “shut-downs” and other required “after hours” work.
3.1 SCHEDULE OF WORK
A. The Contractor shall be responsible for establishing a schedule to meet construction time.
B. For this contract the Contractor shall have 365 calendar days to complete the work.
C. The Contractor shall develop, and submit for approval a Critical Path Method (CPM) schedule indicating all work activities including required interruptions of utilities, facilities activities, traffic flow, etc.
3.2 PHASING OF WORK
A. It is the intent of this project to renovate the Facility in groups of rooms / Common Area at a time. No work shall begin in an occupied area until the previous Work area is released to the Contracting Officer. Two week notice shall be given to the Contracting Officer in order to move occupants of the next Work Area before construction.
B. Contract phasing shall be fully developed by the Contractor with the User and the Government Technical Manager (GOVERNMENT) and shall insure that the Contractor’s Phasing Plan fully allows the facility services to remain open and that there are no interferences with the facility’s ability to meet its scheduled obligations.
3.3 GENERAL
A. The contractor shall coordinate his work with the Government Technical Manager (GOVERNMENT) to avoid interference with necessary activities within and adjacent to the construction site. The Contractor shall coordinate the work of all trades to prevent any conflicts. The Contractor before proceeding with the construction shall resolve any conflicts of components.
B. Normal Work Hours:
The Contractor will perform all work during work hours between 7:00 A. M. and 5:00 P.M. but work after these normal business hour shall be required if necessary to complete the work as scheduled and as required by phasing requirements. The Contractor will not normally be permitted to work on weekends or on the following legal holidays (or the day the federal government observes these holidays) unless he has coordinated such work with the GOVERNMENT at least 72 hours in advance:
1. New Year’s Day
2. Martin Luther King, Jr’s Birthday - Third Monday in January
3. President’s Day - Third Monday in February
4. Special Olympics- Thursday through Sunday of First NON-Training weekend in
May
5. Memorial Day - Last Monday in May
6. Independence Day
7. Labor Day - First Monday in September
8. Columbus Day - Second Monday in October
9. Veteran’s Day
10. Thanksgiving Day
11. Christmas Day
4.1 SITE VISIT
A. Bidder is responsible for site investigation in accordance with contract clause entitled "Site Investigation and Conditions Affecting the Work" (FAR 52.236-3).
5.1 CONTRACT DRAWINGS AND SPECIFICATIONS
A. The Contractor must comply with the contract clause entitled "Specifications and Drawings for Construction" (FAR 52.236-21). See paragraph 19.01 entitled "INTENT
OF DRAWINGS".
6.2 MATERIAL AND EQUIPMENT SUBMITTALS
A. SUBMITTAL REGISTER
1. Within fourteen calendar days after receipt of "Notice of award," of the contract, the Contractor shall furnish the Contracting Officer a Submittal Register to indicate the Contractor's scheduled submittal dates.
2. The Register shall contain all items (shop drawings, manufacturer's literature, certificates of compliance, material samples, guarantees, etc.) that the Contractor shall submit for review and approval action during the life of the contract
B. The Contractor will submit four (4) copies of all required submittals unless otherwise specifically indicated.
6.3 DESCRIPTIVE DATA
A. The Contractor shall submit three copies of AF Form 3000, Material Submittal Approval, to the GOVERNMENT for approval. Included shall be manufacturer's descriptive data for materials, fixtures, and equipment the Contractor proposes to incorporate in the work. The submittal shall include catalog numbers, diagrams, drawings, and such additional descriptive data and samples required to properly evaluate all items. When specifications require materials to conform to Federal, Military, Commercial, AGTM, etc., specifications and standards, the Contractor shall submit supplier's or manufacturer's Certification of Conformance in addition to other descriptive data.
Catalog numbers and trade names specified indicate examples of a standard product.
Other manufacturers' products may be substituted contingent upon approval. Approval of all items must be obtained prior to fabrication or purchase. Payment for work incorporating these materials will not be made if required material submittals have not been approved. Approval of materials, fixtures, and equipment will be based on manufacturer's published ratings and conformance with specifications.
B. The Material Descriptive Data Submittal shall include, but shall not be limited to, the information indicated in the appropriate specification section.
C. The Shop Drawing Submittal shall include, but shall not be limited to, the information indicated in the appropriate specification section.
D. The Samples Submittal shall include, but shall not be limited to, the information indicated in the appropriate specification section.
6.4 CONTRACTOR DEVIATION
A. When data is submitted for approval, the Government's approval of such data shall not relieve the Contractor from responsibility for errors or deviation from contract drawings and specifications. In the case of a deviation, the Contractor shall inform the GOVERNMENT in writing of the request f o r deviation with all the specific data related to the change.
7.1 REFERENCED PUBLICATIONS
A. Any publication referenced in this specification, but not shown in each part under paragraph entitled "APPLICABLE PUBLICATIONS", also form a part of these specifications to the extent referenced.
8.1 TEMPORARY CONSTRUCTION FENCING [not required on this project]
A. Provide and install six-foot (6’) high chain link fence, including gates as indicated, in accordance with commercial (not residential) industry standards.
B. Zinc coated steel fabric or wire not less than (9) gauge.
C. Hot-dipped galvanized steel fence supports, framing and fittings of commercial grade sizes and weights.
D. Provide Keesler standard brown vision screen.
9.1 REMOVAL PROCEDURES
A. No removed items will be reused in this contract unless specifically listed in these specifications and/or on the drawings. All removed equipment becomes the property of the Contractor unless noted otherwise. The Contractor will be required to furnish lifting equipment as necessary to remove the equipment, and shall provide all equipment to transport the removed items off base. All unused material or debris will be removed from Government-controlled property. Use of Government-contracted dumpsters is prohibited. Unused materials, debris and rubbish shall be disposed of off base in a permitted landfill. The Contractor shall comply with Mississippi Department of Environmental Management Regulations.
10.1 GROUND FAULT CIRCUIT INTERRUPTERS
A. Whenever the Contractor uses portable electrical tools or equipment in an outside location or in an interior wet location where floor is conductive such as concrete, the Contractor shall provide and use a portable ground fault circuit interrupter (GFCI). This shall apply wherever electric power is supplied through Government-controlled facilities.
The Contractor shall be responsible for maintaining the GFCI in operating condition and testing it before each use.
11.1 IRE REGULATIONS
A. The Contractor shall comply with all aspects of the National Fire Protection Association (NFPA) publication 241, "Safeguarding Building Construction and Demolition Operations," dated 1980 and Unified Facilities Criteria (UFC)3-600-01 with Change 3 dated 1 March 2013.
12.1 ASBESTOS
A. No friable asbestos containing materials will be installed as a part of this contract. Spray application of asbestos or asbestos-containing materials to exposed walls, ceilings, ducts, columns, etc. is prohibited. In the event friable asbestos containing materials are encountered during "rip out" and demolition operations, the Contractor shall notify the Government Project Manager and will take appropriate abatement action.
13.1 INTENT OF DRAWINGS
A. All drawings are diagrammatic and are intended to qualify the materials specified and indicate their intended relationship to each other. The drawings are not to be scaled, rather field conditions should dictate placement. The various scales used on the drawings may not allow the indications of all fittings, offsets, and accessories that may be required. The Contractor is to carefully investigate the conditions that would affect the work to be performed and shall arrange such work accordingly.
14.1 AS-BUILT DRAWINGS [see specifications]
A. The Contractor shall provide to the Government marked drawings commonly referred to as "as- builts" indicating conditions that differ from that shown on the contract plans The Contractor will review with the GOVERNMENT the "as-builts" on a weekly basis to ensure an accurate up-to- date set of documents is being kept. Changes are to be noted as the work progresses. The Contractor will utilize a Government-furnished copy of the contract drawings with the changes neatly indicated in red using the drafting standards and legends indicated in the contract d r a w i n g s . One copy is required and will be submitted to the GOVERNMENT at the final inspection. If there are no changes, a title sheet (from the contract drawings) will only be required with the note "NO CHANGES" marked appropriately.
15.1 TRAFFIC CONTROL
A. The Contractor shall be responsible for the orderly handling of traffic through the work at all times during the life of the construction contract. This shall be accomplished in conformity with all state, local, federal, and military Authorities Having Jurisdiction.
16.1 CONTRACTOR MAINTENANCE
A. At the end of each working day the Contractor shall clean up the work site which includes the construction area(s), construction office area(s), material storage area(s), parking and eating area(s), and any other area(s) affected by the construction process.
Stacked material shall not be within 8m (25-feet) of an active roadway. Tracking of soil, mud or other construction debris or substance on any Base street, parking area, sidewalk, patio, driveway, turf, or other area shall not be permitted. The Contractor shall keep all turfed areas clean within the construction limits, and shrubs and other elements in the landscape shall be maintained.
17.1 ENVIRONMENTAL PROTECTION
A. The work includes demolition or removal of all construction indicated or specified. All material and debris resulting from this project shall become property of the Contractor and shall be hauled and disposed of off base at the Contractor's expense. Organic waste from ground clearing operations may be disposed of at the Base compost facility, but check with the GOVERNMENT for final clearance. All solid wastes including but not limited to wood, sheetrock, metal, wire, paint, painted brick, painted concrete, painted rock, painted anything, and etc. shall be disposed of in an approved state certified landfill at the Contractor's expense.
B. Clean concrete, brick, rock, and dirt do not require disposal in a certified landfill. This material shall be disposed of off base in any legal manner that will not result in liability to the United States Air Force. Payment for services to the Contractor shall not be released until Contractor has provided copies of all landfill receipts to the GOVERNMENT. The Contractor shall comply with all state, local, federal, and military Authorities Having Jurisdiction (AHJ).
18.1 ENVIRONMENTAL RELEASE REPORTING
A. An environmental release report shall be completed for all environmental releases that are c a u s e d by an Air Force activity or which occur on an Air Force installation or facility. Examples of environmental releases are listed as follows but not limited to: oil releases to navigable waters, hazardous substance release above the reportable quantity, vinyl chloride releases, excessive emissions over amount allowed in permits, hazardous material incidents occurring during transportation, underground storage tank spills and releases, and any emergency incidents of environmental contamination. The Contractor shall immediately notify the GOVERNMENT in the event of any environmental release. The following information shall be documented; the time, type, amount, and cause of release.
19.1 PROTECTION OF EXISTING LANDSCAPE DURING CONSTRUCTION: n/a
20.1 STAGING AREA
A. The Contractor will be provided space as indicated for an office trailer and staging of materials in support of this project and must provide protection and security for it in that area. If not identified on contract drawings the location will be mutually agreed upon and within a reasonable distance to the construction area. Contractor will be required to provide temporary fencing with Keesler AFB standard brown screening around all trailer and staging areas. Contractor will be responsible for job site security as required.
21.1 TESTING
A. Where specific tests are required by this contract, the Contractor shall notify the GOVERNMENT at least 24 hours prior to testing. The Contractor shall turn in a test report, if required, to the GOVERNMENT as soon as possible. The Contractor shall not proceed with any work that would cover up the work being tested until the GOVERNMENT has approved the work being tested.
Section 01000
22.1 CONDUCT OF WORK
A. The Contractor shall conduct his work so the Government property and personnel, other personnel, and work areas shall be protected at all times from inconvenience, damage of any nature, or injury caused by this work until completion of the contract.
23.1 REPAIR OR REPLACEMENT OF DAMAGED PROPERTY
A. In the event of damages of any nature caused by this work (including maintenance and warranty operations) due to improper protection, precaution, or safety measures, such damages shall be repaired or such property shall be replaced by the Contractor at no expense, cost, or charge to the Government.
B. In the event the Contractor does not satisfactorily repair or replace such damage caused by the work of the contract, the Government reserves the right to make the necessary corrections and deduct from the contract price the cost to the Government for inconveniences, labor material, etc. involved.
24.1 BARRICADES
A. The Contractor shall furnish, place and maintain all required barricades as directed by the Safety Office and the Government Project Manager, and access driveways and doors will remain clear at all times.
25.1 CLEANING SCHEDULE
A. Clean sites of all construction related and project related debris on a regular basis or as required by the GOVERNMENT.
B. Remove waste and surplus materials, rubbish, and construction facilities from the work areas and the site. All base roads are to be cleaned of dirt/debris as directed.
C. Execute final cleaning prior to the final inspection.
26.1 CLOSEOUT PROCEDURES
A. Closeout procedures will be conducted for each construction area/building as if it were a separate project. When the Contractor is ready for final inspection, the Contractor shall notify the GOVERNMENT (in writing) within two (2) working days of the desired inspection date. During the inspection, the Contractor and the GOVERNMENT shall document all deficiencies on a "punch list." The GOVERNMENT will provide a formal copy of the punch list to the Contractor. The Contractor shall be responsible for correcting all punch list items prior to the end of the contract completion date and notify the GOVERNMENT (in writing) when the contractor is ready for re-inspection.
27.1 CONTROLLED/RESTRICTED AREAS.
Section 01000
A. The Contractor shall implement local Base procedures for entries to Air Force control/restricted areas where Contractor personnel will work.
28.1 WEAPONS, FIREARMS, AND AMMUNITION
A. Contractor employees are prohibited from possessing weapons, firearms, or ammunition on themselves or within Contractor-owned or privately owned vehicles while on Keesler AFB.
29.1 TRAFFIC LAWS
A. All Contractor personnel shall comply with Base traffic regulations.
SECTION 010010
SECTION 01001
HVAC COORDINATION COMMISSIONING AND CLOSE-OUT
1.0 HVAC PROJECT COORDINATION MEETINGS:
The General and/or Prime Contractor shall send his Mechanical Foreman to all Tuesday morning project coordination meetings. These meetings shall be held in the Civil Engineering Building (B.4705) every Tuesday morning at 7:30 am unless notified otherwise. The contractors’ representative shall be the point of contact for the project and the most familiar with the project progress and details. The purpose of these meetings shall be for project update and coordination purposes.
2.0 PROJECT CLOSE-OUT SEQUENCE:
The General Contractor and Mechanical Contractor are required to coordinate the following sequence with the PAE STM, Designer/Engineer and CSC CEOM shop supervisor one month prior to the beginning of the Certified Factory Start-Up for all equipment. All coordination requests must be submitted in writing or e- mail to the STM. The Contractor shall submit proof of Factory Technician Start-Up Certification and Factory Start-Up Report for approval in the submittal process. All of the following procedures are sequential and must therefore be coordinated and executed in sequential order. The Contractor will be allowed to proceed to each sequential item based on successful completion of each item as approved and directed by the
STM.
1. Controls Commissioning with Commissioning Reports for all Devices: The Contractor shall not proceed to item #2 until all controls commissioning reports for all devices are submitted to the STM and approved. Controls commissioning reports shall be submitted upon the immediate completion of controls commissioning so as not to delay the project. The Contractor shall begin delivery of all Close-Out materials at this point (see item #7).
2. Operational Test: After completion of installation, all mechanical systems shall be started and operated to prove proper functioning of each item of equipment. All operating test shall be scheduled with the STM and performed to the satisfaction of the STM. The contractor shall coordinate the controls contractor to be present.
Should any element or individual piece of equipment not perform properly, the Contractor shall make all required corrections and repeat the operational test for the equipment in question and/or any other related equipment that must operate in unison to the satisfaction of the STM before proceeding to item #3.
3. Certified Factory Start-up with Certified Factory Start-up Report: After equipment installation and operational test are completed; the Contractor shall provide the services of a manufacturer certified field representative for starting the unit and training for the PAE CEOM operator(s) and or technician(s) at no additional costs.
Training can occur sequential to Certified Factory Start-Up if successful and the STM is provided the Certified Factory Start-Up Report immediately upon completion, approved, and Certified Factory Training has been previously coordinated.
Uncertified vendor field representatives are not allowed. Factory certified vendor field representatives are only allowed if they are approved during the submittal process.
The contractor shall coordinate the controls contractor to be present. The Contractor shall present PAE STM with all required copies of the O&M manuals upon completion of Factory Start-Up and prior to Training.
4. Test and Balance: The contractor shall provide complete Test & Balance service as dictated by the specifications. Any deviations from the Test & Balance specification shall be requested in writing to the PAE STM and approved by the designer/Engineer.
The Contractor shall request in writing all pertinent information required for Test & Balance if additional or any information is needed. The Test & Balance Report shall be presented to the Designer/Engineer within 48 Hours for approval by the designer/Engineer. The Designer/Engineer shall have 1 week to review upon receipt thereof. Additional details of the Test & Balance requirements are presented specifically in the Test & Balance section of the specifications.
5. Training for newly installed Mechanical Systems and Devices:
a. Scheduling: Typically, training is only scheduled on Tuesday, Wednesday, or Thursday each week; but exceptions may be permitted on request. Requests for Rescheduling training must be presented in writing or e-mail and may be contingent to a 7-day advance notice. All systems and devices must be fully tested and functioning prior to beginning scheduled training. It is the installers responsibility to ensure that the equipment works BEFORE PAE CEOM staff arrive for training.
b. Start-up and/or Operational Reports: All equipment reports shall be completed in full and delivered to PAE STM prior to beginning the training.
c. Training: Shall be provided by Certified Factory Technician(s) and must include demonstrated performance of all designed system and device functions. Any failures identified during the training which are not immediately (less than 15 minutes) repairable will result in training stoppage until corrected and ALL system component operations re-verified prior to resuming the training.
d. Rescheduling of Training: If any failure is identified prior to or during training which requires rescheduling of the training; The contractor shall notify the PAE STM in writing or email, who in turn, will notify PAE CEOM Supervisors and coordinate. The reschedule date will not require a 7 day notice but will be accommodated at the earliest time based on PAE STM/PAE/CEOM work load and manning.
6. Pre-Final Inspection: When requested by the STM and/or the Contractor and deemed necessary by the STM a courtesy Pre-Final Inspection shall be provided to the contractor. Written comments shall be offered to the Contractor and the Contractor shall address all issues before requesting Final Inspection.
7. Final Inspection (95% complete): The Contractor shall request a date/time/place for Final Inspection in writing or e-mail to the PAE STM when…