About this file

This project is intended to repair cracks and spalls replace ladders and then epoxy coat the floors and walls in the two upper lift station wet wells per contractor report in accordance with all applicable National Air Force State and local building codes and regulations.

View the file

Other files for this federal contract opportunity

Other files attached to Repair Sewer Wet Wells, newest first.
File Type Posted
FA2835-16-R-0018_Questions_(002).pdf PDF
sewer_wet_wells_(pictures).pdf PDF
David_Bacon_Wage_Determination.pdf PDF
FA2835-16-R-0018_Sol..pdf PDF
WO___65747_Drawings.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Repair Sewer Wet Wells

Location Building: 1306

By: Lenore Gerossie

WORK ORDER NUMBER: 65747

DATED: 4 February 2016

Revised 7/21/16

1. GENERAL INFORMATION:

This project is intended to repair cracks and spalls, replace ladders and then epoxy coat the floors and walls in the two upper lift station wet wells per contractor report in accordance with all applicable National, Air Force, State and local building codes and regulations. This work will consist of supplying/furnishing all labor, materials, tools, equipment, shop drawings, expenses necessary to accomplish the work described below in compliance with the Commonwealth of Massachusetts Building Code and Massachusetts General Law requirements, state and federal codes, base standards and manufacturer’s instructions. Where there is a conflict between nationally recognized codes and local codes, the most stringent shall apply.

2. SCOPE: Make repairs to Upper Lift Station Tanks (See attached drawings for tank location)

Tank#2 Auxiliary Wall North:

There is a multitude of cracks by the ladder (attachment 1&2)

Replace ladders with material made of non-corrosive material

The concrete is spalling and needs repair

Tank#2 Auxiliary Wall East :

Horizontal crack by ladder with extensive staining and weeping water all repairs to be made by epoxy grout injections (attachment 3)

Tank#2 Auxiliary Wall South:

Vertical crack has weeping water material and moderate staining. (attachment 4)

Tank#2 Auxiliary Wall West:

Vertical and horizontal cracking with running water and major staining material coming through the cracks (attachment 5)

Tank#1 Main Wall North:

Replace Wall ladders to be made of non-corrosive material (attachment 6)

All repairs to be made with Hilti injection or equivalent epoxy grout injections

3. GENERAL REQUIREMENTS:

Work includes, but is not limited to the following:

a. Provide resolutions of any technical problems that arise during the construction.

b. Should any change in scope be required, it must be coordinated with the Contracting Officer and approved as a change order prior to performing the change in work.

c. Provide a full work schedule to Project POC upon approval of contract. Any construction issues, changes to schedule, or schedule slippages with justification must be reported at the periodic updates.

d. The Contractor is solely responsible for compliance with the Occupational Safety and

Health Act of 1974 (OSHA) and the protection of their employees and all sub-contractor employees. In performing work under this contract on a Government installation, the contractor shall report any accidents involving Air Force property/equipment damage, or contractor personnel injuries occurring on the job or an accident resulting in death, injury, occupational disease, or adverse environmental impact to the contracting officer within five days.

e. Provide three (3) copies of O & M manuals and warranty letter

f. Period of Performance 120 days

g. Complete the “builder data inventory and assessment sheet” for newly installed assets, ensuring the bar code number is attached to the new equipment. Transfer bar codes from any removed equipment to the builder assessment ½ sheet form.

4. ADMINISTRATION:

Points of Contact (POC):

Lead: Lenore Gerossie Phone Number. (781) 225-2960

Alternate POC: William Neice Phone Number. (781) 225-6157