Solicitation Questions and Answers.pdf

PDF 71 KB Posted

Attached to
Eglin Mobile Lab Lift-gate Federal contract opportunity
Solicitation number
FA282320Q9033
Issued by
Department of the Air Force Materiel Command Test Center

View the file

Other files for this federal contract opportunity

Other files attached to Eglin Mobile Lab Lift-gate, newest first.
File Type Posted
TRD.pdf PDF
Aug 2020_Fillable Rep.pdf PDF
Clauses and Provisions.pdf PDF
Combo Small SVC_S.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation Questions and Answers

f. Must have both internal and external controls

Question: Is a hand held remote required?

Answer: The external controls do not have to be hand held just able to be operated while off the platform from the ground.

g. Must have platform safety rails

Question: Will cart stops work

Answer: Cart stops will not be sufficient. Rails must be in accordance with AFMAN91-203 -

AIR FORCE OCCUPATIONAL SAFETY, FIRE, AND HEALTH STANDARDS

Which states: 7.1.5.3. All open-sided floors, platforms and runways four (4) feet or more above the ground or floor shall be guarded by a standard railing on all open sides, except at ramp entrance to a ramp, stairway or fixed ladder. (T-0) Collapsible or removable railings may be installed on a runway, but shall only be removed when a special task (such as oiling, shafting or filling tank cars) is being performed and other protective measures, approved by the installation Occupational Safety office, are used. (T-0) Railings shall be reinstalled when the task is complete. (T-0)

7.1.5.5. Guard railings shall consist of securely mounted top rails, intermediate rails and posts.

(T-0) The vertical height shall be 42 inches, plus or minus 3 inches, from the upper surface of the top rail to the floor, platform, runway or ramp level. (T-0) Exception: Guard railings in place prior to 26 October 2016 shall consist of a top rail, intermediate rail and posts, or equivalent, and shall have a minimum vertical height of 36 to 44 inches from the upper surface of the top rail to the floor, platform, runway or ramp level. (T-0) Heights greater than 45 inches are permissible, provided the guard rail system meets all criteria of 29 CFR 1910.29(b)

A site that sells safety rails that would be compliant is: (https://www.uline.com/BL_791/Safety- Railings). The railing will need to protect the 3 open sides of the lift while it is in operation and be removable in order to stow the lift gate when not in use. 42 inches is the standard height of safety rail and would be sufficient for our needs.