STATEMENT OF WORK (SOW)
Project Title: Storage Rack System install, building 1623, Cape Canaveral Air Force Station
A. Introduction/Background
The 45th Logistics Readiness Squadron owns and operates a warehouse located in building 1623 on Cape Canaveral Air Force Station, Florida. This is an approximately 26,000 square foot warehouse with wall heights of approximately 19 ft. from floor to ceiling. It is used to store United States Air Force assets which are used to support the mission of the 45th Space Wing. Currently, the interior of building 1623 is in the planning stages to be refurbished with new shelving systems to replace the current dilapidated shelving for future storage capabilities. .
B. Objectives
Using FY15 End-of-Year funds, create a safe, efficient, and practical storage rack system for critical spares stored in building 1623 CCAFS. Doing so will create better utilization of the usable cubic footage and provide the load handling capability for critical spare assets. Safety will be ensured by providing adequate storage racks configured in an efficient manner.
C. Scope of Work
Deliver and install 14 rows consisting of 560- 144” beams, 84-42”x192” uprights, and 840- 42”D wire decks.10 rows consisting of 400- 144” beams, 60-48”x192” uprights, and 600- 42”D wire decks. Racks will be positioned as determined by the Asset Manager. Racks will be bolted together and uprights will be anchored to the floor with anchors adequate to handle the rating and function of the shelving. The selected contractor will be responsible for all planning, execution, implementation, and completion of project to include site clean-up. The selected contractor will provide feedback on project progress to all parties involved on a regular or as requested basis. The selected contractor is responsible for all resources necessary to complete the project. The selected contractor will ensure all unused materials at the project site are removed and the area cleaned prior to use by 45th Logistics Readiness Squadron personnel.