Posting_Cost_Estimate.xlsx

XLSX spreadsheet 15 KB Posted

Attached to
Retrograde Landscape Federal contract opportunity
Solicitation number
F2A3E26197A001A
Issued by
Department of the Air Force Air Mobility Command

About this file

Cost Estimate Worksheet

View the file

Other files for this federal contract opportunity

Other files attached to Retrograde Landscape, newest first.
File Type Posted
JFSDA56004_Grass_Seeding_Specification.pdf PDF
JFSD201535_RETROGRADE_LANDSCAPE_SITE_VARIOUS_AREAS_14Sepl2016.pdf PDF
SOW_Sep16_revised.pdf PDF
Posting_Cost_Estimate_15_Sep.xlsx XLSX spreadsheet
Combo_-_Landscaping.pdf PDF
SOW_July2016_revised.pdf PDF
JFSD201535_RETROGRADE_LANDSCAPE_SITE_VARIOUS_AREAS_26Jul2016.pdf PDF
Wage_Determination.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Building/LocationDescriptionUnitQuantityPriceTotal
Bldg. 242DemolitionSquare Feet2117
InstallationSquare Feet2117
Bldg.339DemolitionSquare Feet11866
InstallationSquare Feet11866
Karl FoersterEach32
JunipersEach14
Install EdgingLinear Feet180
Bldg. 233DemolitionSquare Feet1123
InstallationSquare Feet1123
Stella D'Oro LillyEach10
J Street & TuskegeeDemolitionSquare Feet842
InstallationSquare Feet842
Bldg. 308DemolitionSquare Feet6000
InstallationSquare Feet6000
Bldg. 315DemolitionSquare Feet1684
InstallationSquare Feet1684
Bldg. 316DemolitionSquare Feet2975
InstallationSquare Feet2975
Demo TreeEach24
Eielson/7th StreetDemolitionSquare Feet1055
InstallationSquare Feet1055
Bldg. 231/232DemolitionSquare Feet600
InstallationSquare Feet600
Bldg. 117DemolitionSquare Feet396
InstallationSquare Feet396
Bldg. 208DemolitionSquare Feet3741
InstallationSquare Feet3741
Demo ShrubEach3
Bldg. 109DemolitionSquare Feet2154
InstallationSquare Feet2154
Install EdgingLinear Feet250
Demo TreeEach1
Bldg. 319DemolitionSquare Feet1449
InstallationSquare Feet1449
Bldg. 410DemolitionSquare Feet208
InstallationSquare Feet208
Bldg. 418DemolitionSquare Feet462
InstallationSquare Feet462
Demo TreeEach1
Bldg. 320DemolitionSquare Feet566
InstallationSquare Feet566
Demo TreeEach2
Bldg. 203DemolitionSquare Feet2230
InstallationSquare Feet2230
Demo ShrubEach2
Bldg. 202DemolitionSquare Feet873
InstallationSquare Feet873
Bldg. 201DemolitionSquare Feet888
InstallationSquare Feet888
Demo SlabsEach4
Bldg. 124DemolitionSquare Feet1476
InstallationSquare Feet1476
Demo ShrubEach1
Bldg. 629DemolitionSquare Feet8785
InstallationSquare Feet8785
629 Demo TreeEach3
Bldg. 631DemolitionSquare Feet10831
InstallationSquare Feet10831
631 Demo TreeEach6
Bldg. 607DemolitionSquare Feet13308
InstallationSquare Feet13308
Bldg. 699DemolitionSquare Feet2197
InstallationSquare Feet2197
Bldg 121Demo TreeEach4
InstallationSquare Feet200
Bldg 459DemolitionSquare Feet480
InstallationSquare Feet480
Main Gate (bldg 126)DemolitionSquare Feet1227
InstallationSquare Feet1227

TOTAL