MAGURREWOCK DAM EMERGENCY SPILLWAY Federal contract opportunity
Solicitation number
F15PS00244
Issued by
Department of the Interior Fish and Wildlife Service Region 9 Headquarters

About this file

Technical Specifications

View the file

Other files for this federal contract opportunity

Other files attached to MAGURREWOCK DAM EMERGENCY SPILLWAY, newest first.
File Type Posted
Sol_F15PS00244_Amd_000003.pdf PDF
Sol_F15PS00244_Amd_000002.pdf PDF
RFI's_for_Emergency_Spillway_at_Moosehorn.docx DOCX document
Sol_F15PS00244_Amd_000001.pdf PDF
Bid_Schedule.pdf PDF
ME16.pdf PDF
Sol_F15PS00244.pdf PDF
F15PS00244_PPQ-FWS_.docx DOCX document
F15PS00244_Project_Experience_Questionnaire.docx DOCX document
100__Drawing_MAGURREWOCK_ISB_FULL.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1 0 0 % F I N A L

TECHNICAL SPECIFICATIONS

REPAIR OF UPPER MAGURREWOCK

DAM

WASHINGTON COUNTY, MAINE

Prepared for U.S. Fish and Wildlife Service Region 5 – Division of Engineering

July 2014

Prepared By:

URS Group, Inc.

8181 East Tufts Avenue Denver, Colorado 80237

Project No. 22243739 i

Repair of Upper Magurrewock Dam

100% FINAL TECHNICAL SPECIFICATIONS

TABLE OF CONTENTS

DIVISION 1 - GENERAL REQUIREMENTS

01110 Summary of Work 01120 Contractor Work Plan 01145 Health and Safety 01200 Price and Payment Procedures 01310 Project Coordination and Meetings 01320 Construction Progress Schedules 01330 Submittals 01350 Environmental Protection 01410 Regulatory Requirements 01450 Quality Control 01500 Construction Facilities and Temporary Controls 01515 Reservoir Control 01550 Construction Access Roads and Parking Areas 01555 Staging and Stockpile Areas 01570 Sediment and Erosion Control 01575 Disposal of Waste Materials 01720 Layout of Work and Surveying 01770 Contract Closeout

DIVISION 2 - SITE WORK

02210 Geotechnical Investigation 02220 Selective Demolition 02230 Clearing and Grubbing 02235 Stripping and Stockpiling Topsoil 02240 Dewatering 02265 Cofferdams and Stream Diversion 02315 Excavation 02330 Earthwork 02375 Riprap 02665 Geotextile 02920 Reclamation ii

DIVISION 3 - CONCRETE

03100 Concrete Formwork 03150 Concrete Joints and Waterstops 03200 Concrete Reinforcement 03300 Cast-In-Place Concrete 03900 Articulated Concrete Block Mats

DIVISION 5 - METALS

05500 Metal Fabrications

DIVISION 6 - WOOD AND PLASTICS

06155 Composite Wood Decking

APPENDIX A

Service Spillway Design Drawings by Ducks Unlimited, Inc.

APPENDIX B

Geotechnical Data

APPENDIX C

Permits

DIVISION 1 – GENERAL REQUIREMENTS

Summary of Work 01110-1

N:\Projects\22243739_Upper_Magurrewock\Sub_00\11.0_Specifications\100% Specifications\Div 1\01110 Summary of Work.doc 9/27/10

SECTION 01110

SUMMARY OF WORK

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Project description, work summary, and Owner description.

1.2 BACKGROUND

A. Upper Magurrewock Dam is located in northeastern Maine at Moosehorn National Wildlife Refuge (NWR) near Baring, Maine. The dam is constructed across Magurrewock Stream, a tributary to the St. Croix River. The dam and reservoir are owned and operated by the U.S. Fish and Wildlife Service (USFWS).

B. The dam is classified as a low hazard structure. The existing dam is an earthen structure with a structural height of approximately 7 ft. Appurtenant structures include a service spillway located near the middle of the dam. The service spillway consists of a stoplog and gate-controlled concrete intake structure through the embankment.

1.3 PROJECT DESCRIPTION

A. The dam currently does not pass the Inflow Design Flood (IDF). The Repair of Upper Magurrewock Dam Project includes modifications to allow the dam to safely pass the IDF. The modifications include a new emergency spillway, modifications to the existing service spillway, and embankment dam raise.

B. Major work items associated with the Repair of Upper Magurrewock Dam Project include:

1. Mobilization and preparatory work;

2. Erosion and sediment controls;

3. Clearing and grubbing;

4. Dewatering, cofferdams and reservoir control;

5. Stripping and stockpiling topsoil and salvaging existing riprap;

6. Constructing a new emergency spillway, including excavating the spillway channel and installing articulated concrete block mats;

7. Modifying the existing service spillway to raise the concrete walls, including salvaging and replacing the existing handrail, demolishing the existing grate, and designing and installing a new deck;

8. Segregating, processing and stockpiling excavated materials from the spillway areas for fill;

9. Raising the embankment dam crest elevation;

10. Placing imported and salvaged riprap, and imported riprap bedding;

11. Placing aggregate base course dam road surfacing;

12. Spoiling excess and unsuitable excavated materials in the disposal area;

13. Topsoil placement, seeding and reclamation; and

14. Demobilization.

Summary of Work 01110-2

N:\Projects\22243739_Upper_Magurrewock\Sub_00\11.0_Specifications\100% Specifications\Div 1\01110 Summary of Work.doc 9/27/10

1.4 OWNER DESCRIPTION

A. The term Owner as used in these Specifications shall mean the Government.

B. The Owner will occupy the premises full time during the period of construction to conduct normal operations.

C. Cooperate with Owner to minimize conflicts, and to facilitate Owner’s operations.

PART 2 PRODUCTS

NOT USED.

PART 3 EXECUTION

NOT USED.

END OF SECTION

Contractor Work Plan 01120-1

N:\Projects\22243739_Upper_Magurrewock\Sub_00\11.0_Specifications\100% Specifications\Div 1\01120 Contractor Work Plan.doc 9/27/10

SECTION 01120

CONTRACTOR WORK PLAN

PART 1 GENERAL

1.1 SUMMARY

A. This section covers the Contractor Work Plan.

1.2 SUBMITTALS

A. Submit in accordance with Section 01330: Submittals.

B. Prepare and submit a project-specific Work Plan to the Engineer for approval within 14 days after Award. Include the following topics in the Work Plan:

1. Construction implementation plan to include work approach, equipment to be used for each item of construction, methods, and management.

2. Key personnel names and qualifications, list of subcontractors, including an organizational chart and project directory with contact information.

3. Health and Safety Plan. See Section 01145: Health and Safety.

4. Environmental Protection. See Section 01350: Environmental Protection.

5. Waste Handling and Disposal Procedures. See Section 01575: Disposal of Waste

Materials.

6. Spill prevention and control procedures. See Section 01350: Environmental

Protection.

7. Fire prevention and protection. See Section 01350: Environmental Protection.

8. Dust control. See Section 01350: Environmental Protection. (BMPs to be used).

9. Construction sequence and schedule. See Section 01320: Construction Progress

Schedules.

10. Construction Quality Control Plan (CQCP). See Section 01450: Quality Control.

11. Other applicable items to describe work approach.

1.3 WORK PLAN REQUIREMENTS

A. The Work Plan shall be carefully thought out, prepared in accordance with all applicable Federal, state, and local laws and regulations, these specifications, and good engineering and construction practices. The Work Plan shall include a complete discussion of conformance with applicable laws, regulations, guidelines, and other applicable procedures, and shall be approved by the Engineer before beginning field activities.

B. A statement in the Work Plan that “all applicable laws will be followed” is not sufficient detail for the Work Plan submittal. Repetition of specification wording and requirements shall only be used to present the elements of the work plan, not as a substitute for the detail that is expected to present the Contractor’s work approach.

C. The Work Plan shall be developed in accordance with the requirement of the individual specifications indicated and other requirements in this specification.

Contractor Work Plan 01120-2

N:\Projects\22243739_Upper_Magurrewock\Sub_00\11.0_Specifications\100% Specifications\Div 1\01120 Contractor Work Plan.doc 9/27/10

PART 2 PRODUCTS

NOT USED.

PART 3 EXECUTION

Health and Safety 01145-1

N:\Projects\22243739_Upper_Magurrewock\Sub_00\11.0_Specifications\100% Specifications\Div 1\01145 Health and Safety.doc 9/27/10

SECTION 01145

HEALTH AND SAFETY

PART 1 GENERAL

1.1 REFERENCES

A. Williams - Steiger Occupation Safety and Health Act of 1970 (OSHA).

B. All other applicable Federal, State, and Local Safety and Health requirements.

1.2 CONTRACTOR'S RESPONSIBILITY

A. Provide and implement a Health and Safety Plan (HSP) that conforms to all applicable regulations.

B. The HSP shall include the possibility of encountering hazardous or controlled waste at the site, worker protection, actions to be taken, and responsible parties for managing such waste streams.

1.3 OWNER AND ENGINEER'S RESPONSIBILITY

A. Owner and Engineer will have no responsibility for enforcing the Contractor's Health and Safety program.

1.4 SUBMITTALS

A. Submit in accordance with Section 01330: Submittals.

B. Prepare and submit the Contractor's Project Health and Safety Plan in accordance with the General Conditions. The plan is for informational purposes only.

PART 2 PRODUCTS

NOT USED.

PART 3 EXECUTION

Price and Payment Procedures 01200-1

SECTION 01200

PRICE AND PAYMENT PROCEDURES

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Measurement and payment criteria applicable to work performed under a unit price payment method.

B. Measurement and payment criteria applicable to work performed under a lump sum payment method.

C. List of unit price and lump sum pay items.

D. Schedule of value requirements for lump sum pay items.

E. Defect assessment and non-payment for rejected work.

1.2 AUTHORITY

A. Measurement methods delineated in the individual Specification Sections are intended to complement the criteria of this Section. In the event of conflict, the requirements of the individual Specification Section shall govern.

B. Take all measurements and compute quantities for unit price pay items. The Engineer will verify measurements and quantities of work performed by the Contractor for payment purposes.

C. Assist the Engineer in the taking of measurements by providing necessary equipment, workers, and survey personnel as required.

1.3 QUANTITIES OF UNIT PRICE ITEMS

A. Quantities indicated in the Bid Form are for bidding and contract purposes only. Actual quantities and measurements supplied or placed in the work and verified by the Engineer shall determine payment.

1.4 MEASUREMENT OF QUANTITIES FOR UNIT PRICE ITEMS

A. Measurement Devices:

1. Weigh scales: inspected, tested, and certified by the appropriate Maine Weights and Measures Division within the past year.

2. Platform scales: of sufficient size and capacity to accommodate the conveying vehicle.

3. Metering devices: inspected, tested, and certified by the appropriate New Mexico Weights and Measures Division within the past year.

B. Measurement by volume: Measured by cubic dimension using mean length, width, and height or thickness.

C. Excavation quantities will be based on the calculated volume between the baseline survey, as defined in Section 01720: Layout of Work and Surveying and the excavation limits shown on the Drawings or described in these Specifications, or to the most

01200-2 practicable lines, grades and dimensions as prescribed by the Engineer, and will include only material that is actually removed within the prescribed pay lines.

D. Fill quantities will be based on the calculated volume between the approved excavation limits or the approved base surface and the fill limits shown on the Drawings or described in these Specifications, or to the most practicable lines, grades and dimensions as prescribed by the Engineer, and will include only material that is actually placed within the described pay lines.

E. Compute excavation and fill quantities in accordance with the requirements of Section 01720: Layout of Work and Surveying.

F. Where concrete for structures is to be placed directly upon or against the excavations and the character of the material cut into is such that the material cannot be trimmed efficiently to accurate dimensions by ordinary excavation finishing methods, as determined by the Engineer, measurement for payment thereof will be made to the prescribed average dimension lines. The prescribed average dimension lines shall be considered as 6 inches outside the neat lines of the concrete for the purposes of measurement for payment.

G. Measurement for payment of excavations upon or against which concrete is not required to be placed will be limited to the neat lines shown on the Drawings, to the most practicable lines, grades, and dimensions as established by the Engineer.

H. Measurement by area: Measured by square dimension using mean length and width or radius. Items which are measured by the acre, such as revegetation, shall be measured horizontally.

I. Linear measurement: Measured by linear dimension, at the item centerline or mean chord. Items which are measured by the lineal foot, such as pipes, culverts, underdrains, fence, etc., shall be measured parallel to the base or foundations upon which the items are placed, unless otherwise specified or shown on the Drawings.

J. Stipulated sum/price measurement: Items measured by weight, volume, area, or linear means or combination, as appropriate, as completed items or units of the Work.

K. Lump sum items will not be measured for payment. However, measurements may be made to monitor work progress.

1.5 PAYMENT

A. Payment includes: Full compensation for furnishing all required labor, materials, products, tools, equipment, plant, transportation, services, incidentals; erection, application or installation of an item of the work, and all other costs of whatsoever nature for the items of work complete, will be included in the various bid items; overhead and profit.

B. Contractor shall submit a Schedule of Values for all lump sum bid items listed in the Bid Schedule within 30 days of the Notice to Proceed. The Schedule of Values will be used to help assess the intermediate value of work completed for the purpose of making progress payments.

01200-3

C. Payment for unit price items will be made on the basis of the actual measurements and quantities accepted by the Engineer multiplied by the Contract unit prices in the Bid Form.

D. Payment for lump sum price items will be made on the basis of the contract lump sum prices in the Bid Form. If the Contractor requests progress payments for lump sum items, such progress payments will be made in accordance with a detailed program of payment apportioning in the schedule of values, prepared by the Contractor and submitted to the Engineer for approval.

1.6 DEFINITION OF BID ITEMS

A. Bid Items:

1. Mobilization, Preparatory Work, and Demobilization (Lump Sum Item)

a. This item includes the mobilization of personnel, equipment and temporary construction facilities to the project site and their subsequent removal; providing temporary utilities; safety fence; traffic control signage and barricades; and other miscellaneous items required to begin construction and closeout the Contract. The cost of all work specified in Division 1 - General Requirements, unless specifically covered in other bid items, will not be paid separately, but shall be included in the lump sum price bid in the Schedule for Mobilization, Preparatory Work and Demobilization.

b. Measurement: This item will not be measured for payment.

c. Payment will be made for Mobilization, Preparatory Work and

Demobilization as follows, subject to acceptable construction progress:

1) Thirty percent of the bid price for this Bid Item with the first monthly progress payment.

2) Twenty-five percent of the bid price for this Bid Item with the second monthly progress payment provided, in the Owner’s assessment, the work is progressing reasonably towards scheduled completion.

3) The remainder shall be equally prorated over each remaining payment request for the balance of the construction schedule.

d. Mobilization, Preparatory Work and Demobilization is limited to maximum of ten percent (10%) of the total Bid Price.

2. Erosion and Sediment Control (Lump Sum Item)

a. Erosion and Sediment Control includes installation, maintenance, and removal of all sediment control devices required for the Work, including hay bales, silt fence, sedimentation ponds, and associated compliance work required by Federal, State, and County permits.

b. Measurement: Measurement for payment shall be based on the approved Schedule of Values.

c. Payment: Payment will be made at the Contract Lump Sum Price.

3. Clearing and Grubbing (Unit Price Item)

01200-4

a. This item includes clearing and grubbing within the limits of site disturbance for required excavations, staging and stockpile areas, disposal areas and borrow areas. Includes disposal, cutting brush and trees, grubbing roots and stumps, and mowing grass and weeds.

b. Measurement: Measurement for payment shall be based on the acres cleared and grubbed within the limits of site disturbance.

c. Payment will be made at the Contract Unit Price per acre to the nearest

0.01 acre.

4. Stripping and Stockpiling Topsoil (Unit Price Item)

a. This item includes stripping all topsoil as defined in the Specifications to the depths approved by the Engineer and within the limits of the disturbed areas approved by the Engineer. Item includes hauling the stripped topsoil to the stockpile area and stockpiling the topsoil. Re-location of the stockpiled topsoil to a new stockpile location is considered incidental and will not be paid for separately.

b. Measurement: Measurement for payment shall be in cubic yards of topsoil in the stockpile.

c. Payment will be made at the Contract Unit Price per cubic yard.

5. Dewatering (Lump Sum Item)

a. This item includes dewatering all construction areas including installing, maintaining and removing all pumps, piping, drains, well points, wells, and other facilities required to effectively control, collect, and dispose of groundwater or surface water to permit safe and proper construction of all contract work in the dry. This item also includes removing the dewatering facilities at the end of construction.

b. Measurement: Measurement for payment shall be based on the approved Schedule of Values.

c. Payment: Payment will be made at the Contract Lump Sum Price.

6. Cofferdams and Stream Diversion (Lump Sum Item)

a. This item includes all work associated with diverting and controlling upstream flows around the work, including cofferdams, installation and maintenance for temporary pipelines, pumps, ditches, and other facilities required to effectively divert and control upstream water around the work at the site. This item also includes removing cofferdam and diversion facilities at the end of construction.

b. Measurement: Measurement for payment shall be based on the approved Schedule of Values.

c. Payment: Payment will be made at the Contract Lump Sum Price.

7. Unclassified Excavation (Unit Price Item)

a. This item includes excavation of unclassified materials as defined in Section 02315: Excavation required for construction in the areas shown on the Drawings and hauling the material to stockpiles, directly to placement areas, or to spoil areas, including spoil or unsuitable material to the Government Provided Waste Disposal Facility.

01200-5

b. Measurement: Measurement for payment shall be by volume (cubic yards) of unclassified excavation, measured in-place from the existing ground surface after topsoil stripping to the neat excavation lines and grades shown on the Drawings.

c. Payment: Payment will be made at the Contract Unit Price per cubic yard.

8. Rock Excavation (Unit Price Item)

a. This item includes excavation of rock materials as defined in Section 02315: Excavation, required for construction in the areas shown on the Drawings. Test holes cannot determine with certainty the quantity of rock that may be encountered. Therefore, the quantity for this item has been estimated for the purposes of establishing a unit cost if rock is encountered and needs to be removed for construction to the lines and grades shown on the Drawings.

b. Measurement: Measurement for payment shall be by volume (cubic yards) of rock removed measured in-place to the neat excavation lines and grades shown on the Drawings using survey or other acceptable measurement methods approved by the Engineer.

c. Payment: Payment will be made at the Contract Unit Price per cubic yard.

9. Excavate and Stockpile Type I On-Site Riprap (Unit Price Item)

a. This item includes excavating, screening, processing, and stockpiling onsite riprap from the locations shown on the Drawings to produce Type I riprap gradations meeting the specifications. Re-location of stockpiled riprap to a new stockpile location is considered incidental and will not be paid for separately.

b. Measurement: Measurement for payment shall be by volume (cubic yards) of acceptable Type I riprap in the stockpile.

c. Payment will be made at the Contract Unit Price per cubic yard.

10. Excavate and Stockpile Type II On-Site Riprap (Unit Price Item)

a. This item includes excavating, screening, processing, and stockpiling onsite riprap from the locations shown on the Drawings to produce Type II riprap gradations meeting the specifications. Re-location of stockpiled riprap to a new stockpile location is considered incidental and will not be paid for separately.

b. Measurement: Measurement for payment shall be by volume (cubic yards) of acceptable Type II riprap in the stockpile.

c. Payment will be made at the Contract Unit Price per cubic yard.

11. Embankment Fill (Unit Price Item)

a. This item includes processing materials obtained from onsite excavation areas to meet embankment fill requirements, and transporting, placing, spreading, grading, moisture conditioning, and compacting fill in accordance with Section 02330: Earthwork, at the locations shown on the Drawings.

01200-6

b. Measurement: Measurement for payment shall be by volume (cubic yards) of embankment fill measured in-place from the excavated surface to the neat lines and grades shown on the Drawings.

c. Payment: Payment will be made at the Contract Unit Price per cubic yard.

12. Riprap Bedding (Unit Price Item)

a. This item includes material procurement from offsite sources, transporting, placing, spreading, moisture conditioning, and grading Type I and Type II riprap bedding materials to the lines and grades shown on the Drawings.

b. Measurement: Measurement for payment shall be by volume (cubic yards) of riprap bedding material measured in-place from the subgrade surface to the neat lines and grades shown on the Drawings for bedding placed below riprap.

c. Payment: Payment will be made at the Contract Unit Price per cubic yard.

13. Furnish and Place Type I Riprap (Unit Price Item)

a. This item includes procurement from offsite sources, transporting, placing, and spreading Type I riprap to the lines and grades shown on the Drawings.

b. Measurement: Measurement for payment will be made by volume (cubic yards) of Type I riprap measured in-place from the subgrade surface of the riprap bedding to the neat lines and grades shown on the Drawings.

c. Payment: Payment will be made at the Contract Unit Price per cubic yard.

14. Furnish and Place Type II Riprap (Unit Price Item)

a. This item includes procurement from offsite sources, transporting, placing, and spreading Type II riprap to the lines and grades shown on the Drawings.

b. Measurement: Measurement for payment will be made by volume (cubic yards) of Type II riprap measured in-place from the subgrade surface of the riprap bedding to the neat lines and grades shown on the Drawings.

c. Payment: Payment will be made at the Contract Unit Price per cubic yard.

15. Place Onsite Type I Riprap (Unit Price Item)

a. This item includes all work required to haul and place Type I riprap, screened and processed from on-site sources to meet the specified riprap requirements, to the lines and grades shown on the Drawings.

b. Measurement: Measurement for payment will be made by volume (cubic yards) of Type I riprap measured in-place from the subgrade surface of the riprap bedding to the neat lines and grades shown on the Drawings.

c. Payment: Payment will be made at the Contract Unit Price per cubic yard.

16. Place Onsite Type II Riprap (Unit Price Item)

01200-7

a. This item includes all work required to haul and place Type II riprap, screened and processed from on-site sources to meet the specified riprap requirements, to the lines and grades shown on the Drawings.

b. Measurement: Measurement for payment will be made by volume (cubic yards) of Type II riprap measured in-place from the subgrade surface of the riprap bedding to the neat lines and grades shown on the Drawings.

c. Payment: Payment will be made at the Contract Unit Price per cubic yard.

17. Aggregate Base Course (Unit Price Item)

a. This item includes material procurement from offsite sources, and placing, spreading, grading, moisture conditioning, and compacting aggregate base course at the locations shown on the Drawings, excluding aggregate base course under the articulated concrete blocks. Aggregate base course under the articulated concrete blocks are included in the item for Articulated Concrete Block Mats.

b. Measurement: Measurement for payment will be made by volume (cubic yards) of aggregate base course measured in-place from the subgrade surface to the neat lines and grades shown on the Drawings.

c. Payment: Payment will be made at the Contract Unit Price per cubic yard.

18. Service Spillway Modifications (Lump Sum Item)

a. This item includes procuring, batching, transporting, forming, placing, vibrating, finishing, and curing reinforced structural concrete for the raised service spillway concrete wall including procuring transporting, and installing reinforcing steel, dowels, accessories, and joint preparation. Also includes removing, salvaging, and reinstalling the hand rail on the top of the raised service spillway walls; procuring and installing new handrails, steps and steel chain; demolishing the existing grating; designing, furnishing, and installing new decking on the raised structure, and related adjustments, modifications and additions to existing structural elements as shown or specified.

b. Measurement: Measurement for payment shall be based on the approved Schedule of Values.

c. Payment: Payment will be made at the Contract Lump Sum Price.

19. Articulated Concrete Block Mats (Unit Price Item)

a. This item includes procuring, transporting, and installing the articulated concrete block mat (ACB) system to the lines and grades shown on the Drawings. Also includes subgrade preparation and procuring, transporting, and installing associated ACB system components including aggregate base course for ACB substrate and ACB infill, and woven and non-woven geotextile geotextile above and below the aggregate base course substrate.

b. Measurement: Measurement for payment will be made per square foot of articulated concrete blocks installed to the lines and grades shown on the Drawings. Grading, subgrade preparation, aggregate base course and

01200-8 geotextiles used for the ACB system are considered incidental to this item and will not be measured separately for payment.

c. Payment: Payment will be made at the Contract Unit Price per square foot.

20. Erosion Control Mat (Unit Price Item)

a. This item includes furnishing and installing erosion control mat at the locations shown on the Drawings.

b. Measurement: Measurement for payment will be made by surface area coverage (square yards) of erosion control mat installed to the neat lines and grades shown on the Drawings excluding overlaps or anchorage.

Portions of the erosion control mat below ground and buried for anchorage, and other earthwork associated with anchorage are considered incidental to the installation and will not be measured for payment.

c. Payment: Payment will be made at the Contract Unit Price per square yard.

21. Placing Topsoil (Unit Price Item)

a. This item includes loading and hauling topsoil from stockpiles, spreading, and grading topsoil evenly over the areas to be reclaimed.

b. Measurement: Measurement shall be by volume (cubic yards) of topsoil placed as measured in the stockpiles after stripping.

c. Payment: Payment will be made at the Contract Unit Price per cubic yard.

22. Reclamation (Unit Price Item)

a. This item includes procuring, transporting, and placing materials required for reclamation in disturbed areas, seeding, and hydraulically applied tackified mulch where shown on the Drawings or as specified.

b. Measurement: Measurement for payment shall be by area (acres) of areas seeded, measured to the nearest hundredth of an acre.

c. Payment: Payment shall be made at the Contract Unit Price per acre.

1.7 OPTIONAL PAYMENT ITEMS

A. Payment Items identified as optional shall be considered fully removable without compensation to the Contractor. Price estimates for optional and removable items shall include all elements necessary to complete the optional work including, but not limited to, personnel, equipment, mobilization, demobilization and overhead.

B. The Owner may elect to retain or remove optional Items in the Owner’s best interest. Bid pricing shall consider the total cost as well as the specific cost of optional Items and impact to other Items.

C. The following are optional bid items:

1. Bid Option 1: Upstream Slope Riprap Bedding Geotextile Underlayment (Unit Price Item)

01200-9

a. This item includes procuring, transporting, and installing non-woven geotextile under the riprap bedding on the upstream slope of the embankment.

b. Measurement: Measurement for payment will be made by surface area coverage (square yards) of geotextile installed excluding overlaps and anchorages.

c. Payment: Payment will be made at the Contract Unit Price per square yard.

1.8 SCHEDULE OF VALUES

A. Submit Schedule of Values for lump sum items listed in this Section within 15 days after date of Notice to Proceed.

B. The Schedule of Values will be used to assess the intermediate value of Work for pay applications, and is subject to Engineer’s acceptance. Revise and resubmit the Schedule of Values to the Engineer until it is acceptably detailed to make intermediate payments by in the opinion of the Engineer.

1.9 DEFECT ASSESSMENT

A. Replace the work, or portions of the work, not conforming to the Drawings or the Specifications.

B. If, in the opinion of the Engineer, it is not practical to remove and replace the work that does not conform to the Drawings or the Specifications, the Owner will direct one of the following remedies:

1. The defective work will remain, but the corresponding unit or lump sum price of the work will be adjusted to a new unit or lump sum price at the discretion of the Owner.

2. The defective Work will be partially repaired at the instruction of the Owner, and the corresponding unit or lump sum price of the work will be adjusted to a new unit or lump sum price at the discretion of the Owner.

3. The individual Specification Sections may modify the options specified in this Section or may identify a specific formula or percentage unit or lump sum price reduction. In the event of conflict, the requirements of the individual Specification Section shall govern.

4. The authority of the Owner to assess the defect and identify payment adjustment is final.

1.10 NON-PAYMENT FOR REJECTED PRODUCTS

A. Payment shall not be made for any of the following:

1. Products wasted or disposed of in a manner that is not acceptable.

2. Products determined as unacceptable before or after placement.

3. Products not completely unloaded from the transporting vehicle.

4. Products placed beyond the lines and grades of the required Work.

5. Products remaining on hand of the Contractor after completion of the Work.

6. Loading, hauling, and disposing of rejected products.

7. Rejected materials including, but not limited to, overly wet or frozen earth material.

01200-10

8. Excavation or fill made for the convenience of the Contractor for any purpose or reason.

9. Overexcavation and replacement materials.

PART 2 PRODUCTS

NOT USED

PART 3 EXECUTION

NOT USED

Project Coordination And Meetings 01310-1

SECTION 01310

PROJECT COORDINATION AND MEETINGS

PART 1 GENERAL

1.1 WORK INCLUDED IN THIS SECTION

A. The work of this section includes, but is not limited to: coordination; preconstruction meeting; progress meetings; and task start-up meetings.

1.2 COORDINATION

A. Coordinate scheduling, submittals, and work of the various sections of the Specifications to assure efficient and orderly sequence of installation of interdependent construction elements.

B. Coordinate all work with progress meetings to explain unique features of the work to the work forces. The Engineer will attend such meetings. Meet daily with the Engineer to explain work progress, quality control, and any issues affecting successful completion of the work.

C. Coordinate completion and clean up of work of separate sections in preparation for Substantial Completion.

D. After the Owner occupancy of premises, coordinate access to site for correction of defective work and the work not in accordance with Contract Documents, to minimize disruption of Owner's activities.

1.3 PRECONSTRUCTION MEETING

A. Pre-construction meeting shall include a conference call with USFWS Contracting and General Service Division. Schedules shall be sent to Contracting Officer prior to meeting. Main purpose of meeting is to review Contractor requirements and responsibilities. CGS will send out pre-construction contract requirements prior to the meeting.

B. Within ten days after Notice to Proceed and prior to starting the Work except mobilization, the Contractor, accompanied by a representative from each principal subcontractor, shall meet with the Owner and the Engineer for an on-site Preconstruction Meeting. The Preconstruction Meeting will be scheduled by the Owner. The principal features of work will be reviewed and any questions regarding the Contract and work site will be addressed.

C. Attendance Required: the Owner, the Engineer, and the Contractor's Superintendent, the Contractor's Safety and Health Officer, principal subcontractors, and other key personnel as requested by the Contractor or Owner.

D. Unless previously submitted to the Owner, the Contractor shall bring to the conference a schedule for each of the following:

1. Preliminary Progress Schedule.

2. Procurement schedule.

3. Shop Drawings and other submittals schedule.

4. Schedule of Values

01310-2

E. The purpose of the conference is to designate responsible personnel and establish a working relationship. Matters requiring coordination will be discussed and procedures for handling such matters established. The agenda may include:

1. Distribution of Contract Documents, including Contractor’s executed bond, certificate of insurance, and Contract.

2. Submission of list of Subcontractors, list of Products, schedule of values, and preliminary progress schedule.

3. Designation of personnel representing the parties in the Contract, and the Engineer.

4. Procedures and processing of field decisions, submittals, substitutions, applications for payments, proposal request, Change Orders, and Contract closeout procedures.

5. Contractor's schedules.

6. Critical Work sequencing.

7. Processing Applications for Payment.

8. Field decisions and Change Orders.

9. Use of premises by the Owner, the Engineer and the Contractor.

10. Owner's requirements.

11. Construction facilities and controls provided by the Owner.

12. Use of premises, office and storage areas, security, housekeeping, and Owner's needs.

13. Survey and layout.

14. Security and housekeeping procedures.

15. Contractor's assignments for safety and first aid.

16. Quality Control and Inspection Program.

17. Procedures for maintaining record documents.

18. Major equipment deliveries and priorities.

19. Requirements for start-up of equipment.

20. Inspection and acceptance of equipment put into service during construction period.

21. Record drawings.

F. The Engineer will preside at the conference and will arrange for keeping the minutes and distributing the minutes to all persons in attendance.

1.4 PROGRESS MEETINGS

A. The Engineer will schedule and hold regular progress meetings at least weekly and at other times as requested by the Owner or required by progress of the Work. The purpose of the meetings will be to review the progress of the Work, maintain coordination of efforts, discuss changes in scheduling, and resolve other problems which may develop.

B. Additional meetings may be called by the Owner, the Engineer, or the Contractor during any stage of the project when it is deemed necessary to raise any significant questions, establish new guidelines, introduce a new aspect to the project, or any other items that will affect the progress of work.

C. Meetings may take place at the project site or some other location that is satisfactory to the Owner, the Engineer and the Contractor.

D. The Engineer will make arrangements for meetings, prepare agenda with copies for participants, preside at meetings.

01310-3

E. Attendance Required: The Contractor and all Subcontractors active on the site shall be represented. The Contractor may at its discretion request attendance by representatives of its Suppliers, manufacturers, and other Subcontractors.

F. All expenses associated with attending the meetings that are incurred by other than the Owner and the Engineer shall be born by the Contractor.

G. Proposed Agenda:

1. Review and approval of minutes of previous meetings.

2. Review of Work progress of minutes of previous meeting.

3. Field observations, problems, conflicts, and decisions.

4. Identification of problems which impede the schedule and proposed corrective actions.

5. Review of submittals schedule and status of submittals; expedite as required.

6. Requests for information status.

7. Review of off-site fabrication and delivery schedules.

8. Revisions to project schedule.

9. Maintenance of progress schedule.

10. Corrective measures and procedures to regain projected schedules.

11. Planned progress during succeeding Work period.

12. Coordination of project schedules and projected progress. Review of three week look-ahead schedule provided by Contractor to ensure proper coordination with Owner, Engineer, and subcontractors.

13. Maintenance of quality, and Safety and Work standards.

14. Pending changes and substitutions.

15. Effect of proposed changes on progress schedule and coordination, and effect on other contracts of the project.

16. Other business relating to Work.

H. The Engineer shall record minutes; include significant proceedings and decisions and distribute copies after meeting to participants and those affected by decisions made.

1.5 TASK START-UP MEETING

A. Before the start of any significant site activity, as determined by the Engineer, conduct a start-up meeting to discuss procedures, quality control, inspections, and related activities.

Attendance at the meeting should include the Contractor project manager, site supervisor, representatives of key Subcontractors, and the Engineer and his designated representatives. Notify Engineer at least 72 hours in advance of meeting to allow the Engineer to invite necessary offsite personnel.

PART 2 PRODUCTS

NOT USED

PART 3 EXECUTION

Construction Progress Schedules 01320-1

SECTION 01320

CONSTRUCTION PROGRESS SCHEDULES

PART 1 GENERAL

1.1 SUMMARY

A. Construction Progress Schedules developed in accordance with this Section and the General Conditions.

1.2 SUBMITTALS

A. Submit in accordance with Section 01330: Submittals.

B. With each Progress Schedule submission provide the following:

1. Contractor certification that progress schedule submission is the actual schedule being utilized for execution of the Work and certification by all Subcontractors with 10 percent or more of Work that they concur with Contractor progress schedule submission.

2. Five legible copies of the progress schedule.

C. Preliminary Progress Schedule:

1. Within 10 days following the effective date of the Agreement, the Contractor shall prepare and submit a preliminary Critical Path Method (CPM) Bar Chart progress schedule covering all Work to be done on the Project. The schedule shall include the major construction activities and their durations and start/finish dates.

2. The Bar Chart schedule and subsequent revisions shall be submitted to the Owner and shall reflect the actual progress of the Project to within 5 days prior to submittal.

3. If the schedule or any subsequent revision is not acceptable to Owner, the schedule shall be revised and resubmitted as many times as necessary until the schedule is acceptable. Acceptance of the schedule will not be unreasonably withheld.

4. The initial progress schedule, when accepted by the Owner, will be the project baseline schedule.

D. Shop Drawings and Engineering Data Schedule.

1. At the time the preliminary Bar Chart progress schedule is submitted, a schedule shall be submitted of the items of materials, equipment, qualifications, plans, and data for which Shop Drawings and/or engineering data are required by the Specifications. For each required submittal item, the date shall be given for intended submission of the item to Engineer for review and the date required for its return to avoid delay in any activity beyond the scheduled start date.

Sufficient time shall be allowed for initial review, correction and resubmission, and final review of all submittals.

01320-2

E. Bi-weekly Progress Reports:

1. At the end of each two week period, the activities that have been completed, with their actual start and completion dates, and a list of the activities on which Work is currently in progress and the number of working days required to complete each, shall be submitted to Owner.

F. Submit adjusted schedule or confirm validity of current schedule with each monthly Application for Payment in accordance with this Section and the General Conditions, and at such other times as necessary to reflect the following:

1. Progress of Work to within 5 days prior to submission.

2. Changes in Work scope and activities modified since submission.

3. Delays in Submittals or resubmittals, deliveries, or Work.

4. Adjusted or modified sequences of Work.

5. Other identifiable changes.

6. Revised projections of progress and completion.

G. Narrative Progress Report: Submit with each monthly submission of progress schedule.

1.3 PROGRESS OF THE WORK

A. If Contractor fails to complete activity by its latest scheduled completion date and this failure may extend Contract Times (and/or Milestones), Contractor shall, within 7 days of such failure, submit a written statement as to how Contractor intends to correct nonperformance and return to the acceptable current progress schedule. Actions by Contractor to complete Work within Contract Times (or Milestones) will not be justification for adjustment to Contract Price or Contract Times.

B. Engineer may request a schedule recovery or mitigation plan if Contractor fails to:

(i) complete a critical scheduled activity by its latest Milestone completion date, or

(ii) satisfactorily execute Work as necessary to prevent delay to the overall completion of the Work.

C. Owner may require Contractor, at Contractor's expense, to add to its plant, equipment, or construction forces, as well as increase the working hours, if operations fall behind schedule.

1.4 PRELIMINARY PROGRESS SCHEDULE

A. As a minimum, submit two CPM schedules as follows:

1. The Bar schedule shall be sufficiently detailed to indicate such activities as shop drawing submittal and review, equipment manufacture and delivery, installation of equipment, earthwork, demolition activities, concrete placements, and subcontractor’s items of work. Construction activities of less than 1 day's duration or more than 5 days' duration shall be kept to a minimum. Each activity on the diagram shall be labeled with the following information: description, duration, start date, and finish date.

B. Planned durations and start dates shall be indicated for each Work item subdivision.

Work item durations for any activity shall not exceed thirty (30) working days. Each

01320-3 major component and subdivision component shall be accurately plotted on time scale sheets 11 inches by 17 inches or 24 inches by 36 inches in size. Not more than four sheets shall be employed to represent this overview information.

1.5 PROGRESS SCHEDULE

A. General:

1. Schedule(s) shall reflect Work logic sequences, restraints, delivery windows, review times, Contract Times, and Milestones set forth in the Agreement, and shall begin with the date of Notice to Proceed and conclude with the date of Final Completion.

2. The schedule requirement herein is the minimum required. Contractor may prepare a more sophisticated schedule if such will aid Contractor in execution and timely completion of Work.

3. Submit assumptions for base schedule describing work week duration, numbers of shifts, hours per shift, holidays, assumed weather days, assumed productivity, crew size, etc.

4. Adjust or confirm schedules in accordance with this Section and the General Conditions on a monthly basis.

5. The update of the Project Schedule shall be an integral part of the estimate upon which progress payments will be made. If, in the judgment of the Owner, the Contractor fails or refuses to provide information required to accomplish a complete Project Schedule Update or revision as specified hereafter, the Contractor shall be deemed to have not provided the required estimate upon which progress payments may be made, and shall not be entitled to progress payments until it has furnished the information necessary for a complete schedule update to the satisfaction of the Owner.

6. Float time is a Project resource available to both parties to meet contract Milestones and Contract Times.

7. Use of float suppression techniques such as preferential sequencing or logic, special lead/lag logic restraints, and extended activity times are prohibited, and use of float time disclosed or implied by use of alternate float-suppression techniques shall be shared to proportionate benefit of Owner and Contractor.

8. Pursuant to above float-sharing requirement, no time extensions will be granted nor delay damages paid until a delay occurs which (i) impacts Project's critical path, (ii) consumes available float or contingency time, and (iii) extends Work beyond contract completion date.

9. If the Contractor provides an accepted schedule with an early completion date, the Owner reserves the right to reduce Contract Times to match the early completion date by issuing a deductive Change Order at no change in Contract Price.

B. Format:

1. Baseline schedule, on maximum 11-inch by 17-inch or 24-inch by 36-inch sheet size to include at least:

a. Identification and listing in chronological order of those activities reasonably required to complete Work, including, but not limited to, subcontract work, fabrication, and delivery dates including required lead

01320-4 times, move-in and other preliminary activities, Project closeout and cleanup, and specified Work sequences, constraints, and Milestones, including Substantial Completion date(s). Listings to be identified by Specification section number.

b. Identify: (i) horizontal time frame by year, month, and week,

(ii) duration, early-start, and completion for each activity and subactivity, and (iii) critical activities and Project float, (iv) assumed weather allowances, (v) planned holidays, (vi) production rates and (vii) assumed work hours per day and number of work days per week.

c. Subschedules to further define critical portions of the Work.

d. Monthly Schedule Submissions: Show overall percent complete, projected and actual, and completion progress by listed activity and subactivity.

1.6 NARRATIVE PROGRESS REPORT

A. Include, as a minimum:

1. Summary of Work completed during the past period between Narrative Progress Reports.

2. Work planned during the next period.

3. Explanation of differences between summary of Work completed and Work planned in previously submitted Narrative Progress Report.

4. Current and anticipated delaying factors and their estimated impact on other activities and completion Milestones.

5. Corrective action taken or proposed.

1.7 CLAIMS FOR ADJUSTMENT OF CONTRACT TIMES

A. Reference the General Conditions.

B. Where Engineer and Owner has not yet rendered formal decision on Contractor claim for adjustment of Contract Times, and parties are unable to agree as to amount of adjustment to be reflected in progress schedule, Contractor shall reflect that amount of time adjustment in progress schedule as Engineer and Owner may accept as appropriate for the interim. It is understood and agreed that such interim acceptance by Engineer and Owner will not be binding and will be made only for purpose of continuing to schedule Work, until such time as formal decision as to an adjustment, if any, of the Contract Times acceptable to the Engineer and Owner has been rendered. Contractor shall revise progress schedule prepared thereafter in accordance with Engineer and Owner formal decision.

01320-5

PART 2 PRODUCTS

PART 3 EXECUTION

Submittals 01330-1

SECTION 01330

SUBMITTALS

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Submittal requirements. Submittals shall be in accordance with this Section and the General Conditions.

B. Make submittals concurrently to the Contracting Officer, Contracting Officer’s Representative and Engineer.

1.2 DEFINITIONS

A. Work-related submittals of this Section are categorized for convenience as follows:

1. Product Data: Product Data includes standard printed information on materials, products and systems not specifically prepared for the Work, other than designation of selections from among available choices printed therein.

2. Shop Drawings: Shop Drawings include specially prepared technical data for the Work, including drawings, diagrams, performance curves, data sheets, schedules, templates, patterns, reports, calculations, instructions, measurements and similar information not in standard printed form for general application to other contracts.

3. Samples: Samples include both fabricated and unfabricated physical examples of materials, products and units of Work; both as complete units and as smaller portions of units of Work; either for limited visual inspection or (where indicated) for more detailed testing and analysis.

4. Miscellaneous Submittals: Miscellaneous Submittals related directly to the Work (non-administrative) include construction permits, Stormwater Pollution Prevention Plan (SWPPP) requirements, Spill Prevention Control and Countermeasures Plan (SPCC), Work Plan, Health and Safety Plan, warranties, maintenance agreements, workmanship bonds, project photographs, survey data and reports, physical Work records, quality testing and certifying reports, copies of industry standards, records, drawings, field measurement data, operation and maintenance materials, overrun stock; and similar information, devices and materials applicable to the Work and not processed as Product Data, Shop Drawings or Samples.

1.3 QUALITY…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .