This document provides specifications for a liquid penetrant inspection station required under the federal contract opportunity SPMYM223Q1648. The station must include six components: two 15-gallon dip tanks with dwell shelves 10 inches from the bottom and drains for expired chemicals; one 15-gallon emulsifier station with similar configuration; a 20x30x18 inch wash station with water connections and gauges; a 13x24x18 inch dryer with temperature display and shelves; and a 13x30x18 inch developer dust chamber with viewing window. The components must divide into three segments no more than 114 inches long for transport, with a 36 inch working height. The station must operate from 120V AC power and pass NRTL safety certification.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SPMYMQ1648 DYE PENETRANT STATION AMENDMENT.pdf | ||
| SPMYM2231648 DYE PENETRANT STATION.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Liquid Penetrant Inspection Station Salients (JML 31456934)
Six station Liquid Penetrant Inspection Station as described below:
Material – welded steel frames with stainless steel tanks, powder coated finish
(2) Dip Tanks with dwell – Both 15 gal capacity, each dip tank should be 13” wide x 30” long x 18” deep
(1) Emulsifier Station with dwell – 15 gal, dimensions should be 13” wide x 30” long x 18” deep
(1) Wash Station – 20” W x 30” L x 18” D, water supply and drain connections, calibrated pressure and temperature gauges, quick connect hose
(1) Dryer with circulating fan– 13” W x 24” L x 18” D, temperature indicator, shelves at 6” and 12” from the bottom
(1) Developer Dust Chamber - 13” W x 30” L x 18” D, viewing window on lid
Station should be divided into three separate segments for ease of transport (i.e. 1. dip tanks and emulsifier station, 2. wash station, and 3. dryer/developer chamber)
Dip Tanks and Emulsifier stations should have dwell (draining) shelves at about 10” from bottom of tanks. They should also have drains to empty expired chemicals.
Soft closing hinged lids with handles and lock open mechanism for dip on emulsifier and developer stations
Length of stations segments end to end NTE 114”. Height should be approximately 36” to working surface.
Be able to operate on 120 VAC plug in power source and 120 PSI
NRTL Certified (i.e. CSA, UL, etc.), CSE certification not acceptable
File details come from the government source that posted it. Updated .