IFBSheetpilingWallRepair.docx

DOCX document 136 KB Posted

Attached to
Sheetpiling Wall Repair Federal contract opportunity
Solicitation number
DTSL55-11-B-C0924
Issued by
Department of Transportation Saint Lawrence Seaway Development Corporation

About this file

Sheetpiling Wall Repair Solicitation

View the file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

IFB #DTSL55-11-B-C0924

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

DTSL55-11-B-C0924

2. TYPE OF SOLICITATION

|_| SEALED BID (IFB)

|_| NEGOTIATED (RFP)

3. DATE ISSUED

August 19, 2011

PAGE OF PAGES

IMPORTANT – The “offer” section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

5. REQUISITION/PURCHASE REQUEST NO.

11-N-C0924

6. PROJECT NO.

7. ISSUED BY CODE

8. ADDRESS OFFER TO

U.S. Department of Transportation Saint Lawrence Seaway Development Corporation Attn: Contracting Office PO Box 520, 180 Andrews Street Massena, New York 13662

U.S. Department of Transportation Saint Lawrence Seaway Development Corporation Contracting Office PO Box 520, 180 Andrews Street Massena, New York 13662

9. FOR INFORMATION

CALL:

►
A. NAME

Teresa Helm, Contract Specialist Patricia L. White, Contracting Officer

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS) 315-764-3252, e-mail - teresa.helm@dot.gov, or 315-764-3236, e-mail - patricia.white@dot.gov

SOLICITATION

NOTE: In sealed bid solicitations “offer and “offeror” mean “bid” and “offeror”.

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):

Furnish all plant, labor, equipment, and materials except for Corporation-furnished timber fenders and perform all work to repair approximately 50 feet of damaged anchored sheet piling bulkhead (North Wharf Wall) located at the Corporation’s Spare Gate Storage Facility on Fregoe Road, Massena, New York in accordance with these specifications and drawings.

This procurement is a total small business set-aside

NOTE: PROSPECTIVE CONTRACTORS ARE REQUIRED TO REGISTER IN THE CENTRAL CONTRACTOR REGISTRATION (CCR) DATABASE PRIOR TO AWARD OF A CONTRACT AT www.ccr.gov. CONTRACTORS ARE ALSO REQUIRED TO COMPLETE ELECTRONIC ANNUAL REPRESENTATIONS AND CERTIFICATIONS AT http://orca.bpn.gov.

11. The Contractor shall begin performance within 10 calendar days after receiving the notice to proceed and complete by December 15, 2011.

This performance period is |X| mandatory, |_| negotiable. (See Section F, Page 16 of 40.)

12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If “YES,” indicate within how many calendar days after award in Item 12B.)

|X| YES |_| NO

12B. CALENDAR DAYS

10 Days

13. ADDITIONAL SOLICITATION REQUIREMENTS::

A. Sealed offers in original and 2 copies to perform the work required are due at the place specified in Item 8 by 3:00 p.m. (hour) local time, Monday, September 19, 2011 (date). If this is a sealed bid solicitation, offers will be publicly opened at that time.

Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee |X| is, |_| is not required.

C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than 30 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

STANDARD FORM 1442

OFFER (Must be fully completed by offeror)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14)

CODE FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS ►

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation – give number and date of each)

AMENDMENT NO.
DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER

(Type or print)

20B. SIGNATURE
20C. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) ( ) 41 U.S.C. 253(c) ( )

26. ADMINISTERED BY CODE

27. PAYMENT WILL BE MADE BY

U.S. Department of Transportation Saint Lawrence Seaway Development Corporation Finance Office PO Box 520

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return _________ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

29. AWARD ( Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO

SIGN (Type or print) 31A. NAME OF CONTRACTING OFFICER (Type or print)

30B. SIGNATURE
30c. DATE
31B. UNITED STATES OF AMERICA

BY

31C. DATE

STANDARD FORM 1442 BACK

PART I

SECTION A

TABLE OF CONTENTS

SECTION DESCRIPTION PAGES

PART I – THE SCHEDULE

A
SOLICITATION/CONTRACT FORM – TABLE OF CONTENTS
1 – 3
B
SUPPLIES OR SERVICES AND PRICES/COSTS
4
C
DESCRIPTION/SPECS/WORK STATEMENT
5 – 13
D
PACKAGING AND MARKING
14
E
INSPECTION AND ACCEPTANCE
15
F
DELIVERIES OR PERFORMANCE
16
G
CONTRACT ADMINISTRATION DATA
17 – 20
H
SPECIAL CONTRACT REQUIREMENTS
21 – 22

PART II – CONTRACT CLAUSES

I
CONTRACT CLAUSES
23 – 25

PART III – LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

J
LIST OF ATTACHMENTS
26 – 27

PART IV – REPRESENTATIONS AND INSTRUCTIONS

K
REPRESENTATIONS, CERTIFICATIONS AND OTHER
28 – 36

STATEMENTS OF OFFERORS

L
INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS
37 – 39
M
EVALUATION OFFERS FOR AWARD
40

END OF SECTION A

SECTION B

SUPPLIES OR SERVICES AND PRICES/COSTS

ITEMUNIT
NO. DESCRIPTIONQUANTITY UNITPRICE TOTAL

BASIC REQUIREMENT ITEM NO. 1

1a.

Mobilization and Demobilization to include bonds; developing/designing a work plan, shoring/stabilization for the spare gate storage pad foundations, temporary cofferdam or other mechanism(s) for providing dewatered access; delivery and placement of plant and equipment; and following completion of the repairs and restoration of the site, removal of temporary facilities and debris, cleanup and demobilization.

Repair connections within the work area delineated on Contract Drawings Nos. SLS-340-73/1 and 2 and describe within these specifications. This work includes stabilizing existing spare gate storage pad foundations as necessary, installing facilities for establishing access to the wall for repairs, excavating fill behind wall for repair access, shifting displaced wall back to original alignment, rebuilding the sheetpiling-to-waler connections, removal of any temporary walers or other fixtures and replacement of the crushed stone fill behind the wall.

FOR

THE JOB L.S.

1b.

FOR

THE JOB L.S.

SUBTOTAL Basic Requirement Items Nos. 1a and 1b

OPTIONAL REQUIREMENT ITEM NO. 2 (Discretionary, prior COTR approval required)

2a.

Repair additional waler-to-sheetpiling connections, if required.

Est. 2

Each $_____________

2b.

Labor and equipment for a crew of two (2) to perform additional repairs that are as yet undetermined but may become evident as the work progresses to include cutting, welding, bolting, etc. This covers items not specifically addressed in Items Nos. 1b and 2a above. Materials for this work will be paid for based on submitted receipts.

Est. 50

Hour $____________

TOTAL Basic Requirement Item Nos. 1a and 1b and Optional Requirement Item Nos. 2a and 2b

The estimated price range of this project is between $250,000 and $500,000.

Signature _________________________________________________ Date ____________________________________

END OF SECTION B

SECTION C

DESCRIPTION/SPECS./WORK STATEMENT

SPECIAL PROVISIONS

C.1. DESCRIPTION OF WORK.

The work covered by these specifications consists of furnishing all plant, labor, equipment and materials except for Corporation-furnished timber fenders and performing all work to repair approximately 50 feet of PZ-27 sheet piling anchored wall, known as the “North Wharf Wall” at the Spare Gate Storage Facility. A section of this wall that is approximately 40 feet long was displaced outward up to approximately 12 inches, when the bolted sheetpiling-to-waler connections pulled out through corroded sheetpiling material at certain locations. Behind the anchored wall, the granular fill has subsided. The work will require the Contractor to provide dry and stable access to both sides of the compromised sections of the wall. The repairs require the Contractor to clean, cut to sound steel, patch the steel sheets, move the wall back to its original alignment, make new waler connections to the repositioned wall and replace the granular fill behind the wall.

C.2. CONTRACT DRAWING AND SPECIFICATIONS.

The List of Attachments together with these specifications detail the project requirements.

(See list of drawings under Part III, Section J, List of Attachments, Pages 26 through 27.)

C.3. WORK SITE REQUIREMENTS.

a. General. The Contractor acknowledges that he/she has satisfied himself/herself as to the nature and location of the work, the general and local conditions, including but not restricted to those bearing upon transportation, disposal, handling, and storage of materials, availability of labor, water, electric power, roads, uncertainties of weather or similar physical conditions at the site, the conformation and conditions of the ground and structures, and the character of equipment and facilities needed preliminary to and during prosecution of the work. The Contractor further acknowledges that he/she has satisfied himself/herself as to the character, quality and quantity of surface and subsurface materials or interference from existing structures or related facilities to be encountered insofar as this information is reasonably ascertainable from an inspection of the site, review and consideration of the Report “Underwater Investigation of SLSDC Marine Base Spare Gate Storage Facility…” dated 09/23/2010 by Collins Engineers, Inc., as well as from information presented within the contract and reference drawings and these specifications. If the Contractor fails to properly acquaint himself/herself with the available information and existing work site conditions, he/she will not be relieved from responsibility for properly estimating the cost of successfully performing the work. The Contractor shall be responsible for performing all work in strict accordance with applicable Occupational Safety and Health Administration (OSHA) Regulations.

b. Utilities. The Contractor shall provide any power required at his/her own expense.

c. Potable Water. The Contractor shall provide all required potable water at his/her own expense.

d. Sanitation. The Contractor shall provide chemical toilets within his/her work area which shall comply fully with the New York State Department of Health Standards. The capacity of the toilet facilities shall be sufficient to provide for the needs of the Contractor’s people and all waste material from the toilets shall be disposed of away from the site. The Contractor shall be responsible for keeping his/her work areas clean of refuse of any kind and shall dispose of all refuse off the site.

SECTION C (Cont’d)

e. Parking Areas. The Contractor and his/her work crews shall park their vehicles at areas designated by the COTR. Vehicles required for transporting equipment and materials to and/or from the work site shall not be parked at the work site for long periods of time without prior approval of the COTR.

f. Work Areas. The work site required by this contract comprises the spare gate storage area as shown on the contract and reference drawings.

g. Restricted Areas. The Contractor will be required to confine his/her operations to the work area as designated in the previous subparagraph. Except for specifically designated areas, the adjacent roads, parking areas and Corporation buildings and floating plant shall be kept free of the Contractor’s personnel, materials and equipment. When necessary for the Contractor’s personnel, materials, or equipment to occupy or transit these restricted areas, the COTR shall be notified to coordinate this with Corporation operations.

h. Existing Conditions and/or Existing Features. Most of the work will be done in locations which are normally underwater. There are spare gate sections located about 5 feet north of the sheetpiling bulkhead. These will be removed from the two easternmost towers by the Corporation to facilitate access by the Contractor. The anchored wall south face is equipped with two horizontal rows of timber fenders which the Contractor will need to remove in order to install a cofferdam or otherwise establish dry and stable access to the work areas. The Contractor will remove the timber fenders where necessary, and upon completion of the project, replace them with new Corporation-furnished timber fenders.

i. Permits. This project is anticipated to require New York State Department of Environmental Conservation (NYSDEC) permits under Chapter VI Part 621, as it pertains to work regulated under parts 608, 666 and possibly 617, and also a joint application permit from the US Army Corps Of Engineers (ACOE), prior to beginning of construction. These permits have yet to be issued. The contractor will be required to comply with all permit conditions normally included in joint NYSDEC/US ACOE permits issued by these agencies for the type work shown and specified. The Corporation is responsible for these permits, has begun the application process and will furnish copies of these permits to the Contractor. The Contractor cannot begin work in the water until the permits have been issued.

C.4. LAYOUT OF WORK.

The Contractor shall furnish, at his/her own expense, all stakes, templates, platforms, equipment, range markers, or other guides as may be required in laying out any part of the work. The Contractor will be held responsible for the execution of the work to such lines and grades as may be established or indicated by the COTR. It shall be the responsibility of the Contractor to maintain and preserve all controls established by the COTR until authorized to remove them.

C.5. CONTRACTOR/CORPORATION-FURNISHED MATERIALS.

The Contractor shall furnish all materials required for the satisfactory completion of this contract, except for replacement timber fenders which will be furnished by the Corporation. All materials furnished by the Contractor shall be of the type and quality described in the Technical Provisions.

C.6. ENVIRONMENT PROTECTION.

a. General. For the purpose of this specification, environment protection is defined as the retention of the environment in its natural state to the greatest possible extent during project construction and the enhancement of the natural appearance in its final condition. Environment protection requires consideration of SECTION C (Cont’d) air, water, and land and involves noise, solid waste management, and management of radiant energy and radioactive materials, as well as other pollutants. In order to prevent and to provide for abatement and control of any environmental pollution arising from the construction activities in the performance of this contract, the Contractor and his/her subcontractors shall investigate and comply with all Federal, State, and Local laws and regulations concerning environmental pollution control and abatement. Any non-compliance shall be immediately corrected and the Contracting Officer notified.

b. Notification. The Contracting Officer will notify the Contractor of any noncompliance detected by the Corporation with the aforementioned Federal, State or Local laws or regulations. Such notice, when delivered to the Contractor or his/her authorized representative at the site of the work, shall be deemed sufficient for the purpose. The Contractor shall, after receipt of such notice, immediately inform the COTR of the proposed corrective action and take such action as may be approved. If the Contractor fails or refuses to comply promptly, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to any such stop order shall be made the subject of a claim for extension of time or for excess costs or damages by the Contractor.

c. Protection of Land Resources. The land resources within the project boundaries and outside the limits of permanent work performed under this contract shall be preserved in their present condition or be restored to a condition after completion of construction that will appear to be natural and not detract from the appearance of the project. The Contractor shall confine his/her construction activities to areas defined by the plans and specifications.

d. Protection of Water Resources. The Contractor shall not pollute the River with fuels, oils, bitumens, calcium chloride, acids, insecticides, herbicides, or other harmful materials. The Contractor shall identify and comply with all applicable Federal, State, County, and Municipal laws concerning protection of the St. Lawrence River and its contributing waterways.

C.7. SITE VISIT.

Prospective bidders are expected to visit the work site prior to entering a bid to determine the extent of work required. Failure to do so will not relieve the successful bidder of the responsibility for the completion of the intended work. A proper understanding of the type of work required, the conditions under which the work will be done, and consideration of possible methods of performing the various tasks comprising the work can only be obtained through a site inspection. Site visit will be conducted at 9:00 a.m. on Thursday, September 1, 2011. Arrangements must be made with the Office of Engineering and Maintenance, Phone 315-764-3240 (no collect calls). Any expenses involved in site inspection will be borne by the bidder.

C.8. PLANT.

The Contractor will furnish all plant to meet the requirements of the work. The Contractor-furnished plant shall be in satisfactory operating condition and capable of safely and efficiently performing the work. The plant shall be subject to the inspection of the COTR at all times. The Contractor shall indicate the minimum plant, which he/she agrees to place on the job in the "Statement of Plant", Part IV, Section K. The listing of such equipment is not to be construed as an agreement on the part of the Corporation that the equipment is adequate for the performance of the work.

SECTION C (Cont’d)

C.9. DISPOSAL OF SPOIL.

Any waste material, except for concrete and asphalt paving removed by the Contractor and unused fresh concrete, generated by the Contractor must be removed from the work site by the Contractor and disposed of at his/her own expense in strict accordance with New York State Department of Environmental Conservation regulations. Asphalt pavement removed by the Contractor may be spoiled on Corporation property in an area designated by the COTR.

C.10. DISPOSAL BY BURNING.

Burning will not be permitted.

C.11. USE OF EXPLOSIVES.

Blasting will not be permitted.

C.12. SAFETY.

The Williams-Steiger Occupational Safety and Health Act of 1970 (as amended) as set forth in 29 CFR 1926/1910, where applicable, shall govern this contract. If divers are utilized on the project, all applicable OSHA requirements for that activity must be adhered to.

C.13. WAGE RATES.

a. In accordance with the requirements of Clause (a), Davis Bacon Act, (40 U.S.C. 276 a-7), see Part II, Section I, General Provisions, Clause 52.222-6 of this contract, the minimum wages to be paid to laborers and mechanics on this project, as most recently determined by the Secretary of Labor to be prevailing for the corresponding classes of laborers and mechanics employed on projects of a character similar to the contract work in the pertinent locality, are as set forth in Attachment I. The complete determination is incorporated in the contract specifications regardless of whether the Contractor will employ all of the classes of laborers and mechanics listed.

b. Any class of laborers and mechanics not listed in Attachment I, which will be employed on this contract shall be classified or reclassified to conform with Attachment I, by mutual agreement between the Contractor and the class of labor concerned, subject to the prior approval of the Contracting Officer. In the event the interested parties cannot agree on the proper classification or reclassification of a particular class of laborers and mechanics to be used, the question, accompanied by the recommendation of the Contracting Officer, shall be referred to the Secretary of Labor for final determination.

TECHNICAL PROVISIONS

C.14. SUBMITTALS.

a. Bidders. Bidders shall submit the following with their bids:
1. Outline conceptual work plan including proposed plant and equipment for performing the project.
2. Manufacturer’s data and catalog cut sheets for materials proposed for the project.

SECTION C (Cont’d)

b. Contractor. The Contractor shall submit the following after contract award and prior to a preconstruction meeting:

1. A detailed work plan and progress schedule showing the order in which work is to be performed and the dates on which the Contractor contemplates starting and completing the salient features of the work including acquiring materials, plant and equipment. The schedule shall be in the form of a progress chart of suitable scale to indicate approximately the percentage of work scheduled by any given date during the period.
2. A schedule of values to be used by the Corporation when making progress payments.

3. A detailed safety plan to describe the measures to be utilized to insure that all aspects of the work are accomplished in accordance with OSHA Standards.

4. The work plan with shop drawings as necessary to provide detailed information shall be prepared, signed and sealed by a New York State licensed professional engineer. As a minimum, this document shall include cofferdam design and details (where proposed for wall access), detailed repair procedure, sheet pile to waler connection details, details of how existing storage pad pile foundations are to be stabilized and methods to be used in restoring the original sheetpiling bulkhead alignment.

5. Qualification/training certificates for divers and support personnel.

For the purposes of this specification, “approval” of submittals means that the Corporation has reviewed them for general conformance to the design concepts. “Approval” of any submittal does not relieve the Contractor from responsibility for proper workmanship, material conformance, dimensional accuracy and design adequacy for those elements not detailed on the contract drawings. The Contractor retains sole responsibility for dimensional accuracy of new fabrications and installations.

C.15. ANCHORED WALL REPAIRS.

a. General. The Basic Requirement Bid Items 1a. and 1b. are based on the premise that satisfactory repairs can be made by moving the displaced sheetpiling back to the original position and then restoring the failed waler connections at the sheetpiling. The sheetpiling shall be re-connected to the walers by reinforcing the connection areas in the sheetpiling web and then installing new bolts and other hardware as depicted on the contract drawings to complete the connection. It is assumed the waler and anchor tie rods and anchor wall are functional and will not require repairs. A 60 foot section of wall (designated as the “WORK AREA” and shown on the contract drawings) shall be cofferdammed or otherwise prepared so that all sheetpiling-to-waler connections within that section can be accessed for inspection and repair. Within that 60-foot work area, assume for bid purposes that 50 feet of wall containing fifteen (15) sheet piling-to-waler connections with two (2) bolts each will require restoration. The remainder of the connections within the 60-foot work area shall be inspected and any connections that appear close to failure or to have experienced significant sheetpiling thickness loss at the connection as determined by the COTR, shall also be restored as were the failed connections and paid for under Optional Requirement Bid Item No. 2a.

If, during the course of the work other deteriorated items, such as damaged/corroded walers, anchor tie rods or additional connections needing repair are discovered (beyond the designated fifteen (15) sheet piling to waler connections) and the COTR directs the Contractor to do this work, these repairs will be covered under either Optional Requirement Bid Items Nos. 2a. or 2b.

SECTION C (Cont’d)

b. Access. The sheetpiling-to-waler connections that require repair are normally below the waterline. They may best be accessed for repair by means of a cofferdam. It will be necessary for the Contractor to remove the existing timber fenders in order for the cofferdam to seal against the wall. Access to the sheetpiling-to-waler connections will also be required behind the wall (landward side). This will require excavation of the fill while simultaneously maintaining stability of the adjacent spare gate storage pad bearing pile foundations. It will be necessary for the Contractor to maintain a sump in the excavation or otherwise operate and maintain a dewatering system so that the work can be performed in the dry. To facilitate access by the Contractor, the Corporation will remove the spare gate sections from the two (2) easternmost towers.

c. Repair Procedure. In general the repair procedure will comprise the following steps:

1. The Contractor shall secure, expose and otherwise prepare a 60-foot section of the anchored wall encompassing the failed section as discussed above and shown on the contract drawings. Remove existing timber fenders as required, and then construct and dewater cofferdam, dewatering box or other mechanism as required to access the portion of the wall containing the connections to be inspected/repaired. The exact design, construction, installation, operation and maintenance of the cofferdam or other mechanism, stabilization system and dewatering system is the responsibility of the Contractor. The cofferdam/dewatering box must be able to withstand hydrostatic pressures, limit incursions of water into the dewatered area and provide adequate space for the work crews. The cofferdam could consist of a steel box or other type of structure sealed against the sheetpiling wall along the vertical sides and with a floor or possibly sealed into the bottom soils. Form-fitting flexible gasket material will reduce water leakage into the cofferdam. The Contractor shall maintain the work areas in a dewatered condition during repairs. The cofferdam/mechanism shall be designed, signed and sealed by a New York State registered professional engineer. The design shall be submitted to the COTR for approval.

2. Remove existing fill behind the wall as necessary to relieve lateral pressure, provide a work space and to provide a space to accommodate the wall as it is moved back to the original position. It will be necessary to maintain stability of the bearing H-pile supported spare gate storage pad foundations as the fill is removed. Contract Drawing No. SLS-340-73/2 shows a conceptual design for a method of maintaining existing foundation stability, but exact methods and details shall be the responsibility of the Contractor. The Contractor shall employ a New York State registered professional engineer to design the plan to maintain the foundation’s stability during the work. The design shall be included in the work plan submittal.

3. Move the displaced wall back to its original alignment as shown on the reference drawings. This could be done by pushing against an external reaction, jacking against the existing walers, jacking with a temporary external waler against the existing anchors or new drilled and grouted-in tieback anchors. The method shall be stated in the work plan submittals. The order the Contractor proposes to perform the work items (repair and reinforce, rebuild connections, move back to original alignment) shall be included in the work plan.

4. Repair and reinforce as necessary holes and weakened areas of the sheetpiling as necessary to provide a suitable bearing surface for the anchor connections. Details shall be provided in shop drawing submittals.

5. Rebuild the sheetpiling to waler connections following the concepts shown on Contract Drawing No. SLS-340-73/2. Shop drawing details shall be submitted for approval.

6. Place 2 inch minus crusher run crushed stone fill in accordance with Paragraph C.18 “Fill” behind the repaired wall to the level of the top of the sheetpiling. Care shall be taken not to overstress any part of the anchored wall system.

SECTION C (Cont’d)

7. Those connections within the work area that are not obviously damaged will be inspected by the COTR. The inspection will include a visual examination and ultrasonic thickness measurements of the sheetpiling material in the connection area in at least four (4) locations around the immediate perimeter of each washer plate. Those areas that are visibly deformed or have experienced significant thickness loss (25% or more) as judged by the COTR shall be repaired as described above.

8. Remove cofferdam, demobilize, etc. to restore the work area to original condition.

b. Methods and Materials. The exact methods and materials to accomplish the above shall be determined by the Contractor and shall be detailed in shop drawing and work plan submittals for Corporation approval per Paragraph C.14 “Submittals” above. They shall conform with the requirements of these specifications and/or approved work plan/shop drawing submittals. Materials and products not described in these specifications that will be part of the final project shall be submitted with the work plan submittals, which will form a part of the contract documents upon approval by the Corporation. In the event extra work is required per Optional Requirement Bid Items Nos. 2a. and 2b., the Contractor shall submit a work plan for these items to include materials and detailed procedures to conduct the repairs. Upon approval, this will form the basis of a contract modification under which the contractor will be compensated.

C.16. CONCRETE WORK.

a. General. If the Contractor chooses to incorporate concrete into the repair work that will remain in place, the concrete mix design shall be approved by the COTR and the concrete shall be placed and cured in accordance with all applicable American Concrete Institute (ACI) practices.

C.17. STEEL WORK.

a. General. This paragraph covers general requirements for steel work associated with repairs to the existing anchored wall. References made here to specific sections or subsections of the AWS D1.1 Structural Welding Code are based on the 2006 edition.

b. Materials. Materials shall be as shown on the contract drawings, approved submittals or described in the specifications for the specific work being performed. New steel plate, shapes and fasteners shall be hot-dip galvanized G90 per ASTM Standards A-123, A-153 or A-563 as appropriate for the item. All structural steel shapes and plate shall be A36 or better.

c. Fabrication. Material must be straight before being laid out or worked. If straightening is necessary it shall be done by methods that will not damage the metal. Sharp kinks or bends shall be cause for rejection of the material. Material with welds will not be accepted except where welding is specified, indicated or otherwise approved. Bends shall be made by approved dies, press brakes or bending rolls. Where heating is required, precautions shall be taken to avoid overheating the metal and it shall be allowed to cool in a manner that will not impair the original properties of the metal. Proposed flame cutting of material other than structural steel shall be subject to approval and shall be indicated on the Contractor’s shop drawing submittals. Shearing shall be accurate and all portions of the work shall be neatly finished. Corners shall be square and true unless otherwise shown. Re-entrant cuts shall be filleted to a minimum radius of 3/4 in. unless otherwise approved. Finished members shall be free of twists, bends and open joints. Bolts, nuts and screws shall be tight. ASTM A 325 high strength bolted joints shall be tensioned in accordance with the procedures specified in “Specification for Structural Joints Using ASTM A325 or A490 Bolts” found in the AISC Manual of Steel Construction. Unless stated otherwise for a specific application, dimensional tolerances shall be 1/16 in. for cut pieces and hole placements and 1/64 in. for pieces with milled or machined edges. Structural steel may be cut by SECTION C (Cont’d) mechanically guided or hand-guided torches, provided an accurate profile with a surface that is smooth and free from cracks and notches is obtained. Surfaces and edges to be welded shall be prepared in accordance with AWS D1.1, Subsection 5.15.

d. Welding.

1. General. Any welding that is incorporated into the permanent repair, shall conform to the requirements stated below:

2. Size and Placement. Welds shall be of the size, type and placement shown on the approved shop drawings. Fillet welds shall be of a size corresponding to the thickness of the thinnest member joined less 1/16 in. unless otherwise shown on the contract drawings or approved shop drawings.

3. Welding Procedures. All structural steel welding shall be performed in accordance with the applicable provisions of the AWS Structural Welding Code D1.1 (AWS D1.1). Welding of structural steel shall be by low-hydrogen shielded metal arc (SMAW) or flux-cored arc (FCAW) processes conforming to the applicable provisions of AWS D1.1, Sections 1 thru 7, 9, 10 and 11. Low hydrogen processes shall be used. Welding shall be such as to minimize residual stresses, distortion and shrinkage. Welding procedures for structural steel shall be prequalified as described in AWS D1.1, Subsection 4.1 or shall be qualified by tests as prescribed in AWS D1.1, Section 4. Properly documented evidence of compliance with all requirements of these specifications for previous qualification tests shall establish a welding procedure as prequalified. For welding procedures qualified by tests, the test welding and specimen testing must be witnessed and the test report document signed by an independent testing agency acceptable to the COTR. Approval of any welding procedure will not relieve the Contractor of the responsibility for producing a finished structure meeting all requirements of these specifications. The Contractor will be directed or authorized to make any changes in previously approved welding procedures that are deemed necessary or desirable by the COTR. The Contractor shall submit a complete schedule of welding procedures for each steel structure to be welded. The schedule shall conform to the requirements specified in the applicable provisions of AWS D1.1. The schedule shall provide detailed procedure specifications and tables or diagrams showing the procedures to be used for each required joint. Welding procedures must include filler metal, preheat, interpass temperature and stress-relief heat treatment requirements. Each welding procedure shall be clearly identified as being prequalified or required to be qualified by tests. The electrode, electrode-flux combination and grade of weld metal shall conform to the appropriate AWS specification for the base metal and welding process being used or shall be as shown where a specific choice of AWS specification allowables is required. The AWS designation of the electrodes to be used shall be included in the schedule of welding procedures. Only low hydrogen electrodes shall be used for manual shielded metal-arc welding regardless of the thickness of the steel. A controlled temperature storage oven shall be used at the job site as prescribed by AWS D1.1 to maintain low moisture of low hydrogen electrodes.

4. Preheat and Interpass Temperature. Preheating shall be performed as required by AWS D1.1, Section 5 or the approved welding procedure specification except that the temperature of the base metal shall be at least 70 degrees F. Higher preheats may be required if specified for the particular welding application. The weldments to be preheated shall be slowly and uniformly heated by approved means to the prescribed temperature, held at that temperature until the welding is completed and then permitted to cool slowly in still air.

5. Workmanship. Welding workmanship shall be in accordance with AWS D1.1, Section 6 and other applicable requirements of these specifications.

SECTION C (Cont’d)

6. Preparation of Base Metal. Joint surfaces shall be smooth, uniform, clean and free from dirt, rust, oil, moisture and other foreign matter. When welding galvanized parts, the galvanizing shall be removed from the weld joint surfaces by grinding. All surfaces to be welded shall be in compliance with AWS D1.1, Subsection 5.15.

7. Temporary and Tack Welds. Temporary and tack welds are subject to the same workmanship and quality requirements as for permanent welds and shall be made under the controlled conditions prescribed for permanent work.

8. Inspection by Contractor. The Contractor shall visually inspect all welds for workmanship and dimensional conformance. Completed welds shall be cleaned and carefully examined for insufficient throat or leg sizes, cracks, undercutting, overlap, excessive convexity or reinforcement and other surface defects to ensure compliance with the requirements of AWS D1.1. In addition, the Contractor must perform ultrasonic testing (UT) on all full penetration welding. Acceptance criteria for visual examination and UT are per AWS D1.1 requirements for cyclically loaded structures.

9. Defective Weld Repairs. Defective welds caused by the Contractor’s work shall be repaired in accordance with AWS D1.1, Subsection 5.26. or AWS D1.6. Defective weld metal shall be removed to sound metal by use of air carbon-arc gouging or by grinding. The surfaces shall be thoroughly cleaned before welding. Welds that have been repaired shall be retested by the same methods and acceptance criteria that were used in the original inspection. All costs of repairs and retesting shall be borne by the Contractor.

10. Weld Touch-up: Completed welds that join all galvanized parts shall be coated with a cold galvanizing material approved by the COTR. The cold galvanizing material shall be applied and cured in accordance with the manufacturer’s instructions.

e. Bolted Connections. Bolts, nuts and washers shall be of the type specified or indicated. All nuts shall be equipped with washers except for high strength bolts. Beveled washers shall be used where bearing faces have a slope of more than 1:20 with respect to a plane normal to the bolt axis. Where the use of high strength bolts is specified or indicated, the materials, workmanship and installation shall conform to the applicable provisions of ASTM A325. Bolt holes shall be accurately located, smooth, perpendicular to the member and cylindrical. Bolt holes shall be drilled or subdrilled and reamed in the shop and shall not be more than one sixteenth (1/16) inch larger than the diameter of the bolt. Burrs resulting from reaming shall be removed. The threads of bolts shall be entirely outside of the holes. If the thickness of the material is not greater than the diameter of the bolts, the holes may be punched. If the thickness of the material is greater than the diameter of the bolts, the holes may be drilled full size or subpunched or subdrilled at least one eighth (1/8) inch smaller than the diameter of the bolts and then reamed to full size. Poorly matched or unfair holes will be cause for rejection. Drifting occurring during assembly shall not distort the metal or enlarge the holes. Subject to approval by the COTR, reaming to a larger diameter of the next standard size bolt will be allowed for slight mismatching.

C.18.FILL.
a. General. This paragraph covers fill to be placed behind the bulkhead once the repairs are complete.

b. Materials. Materials shall consist of No. 2 size crusher run limestone or equal which is 100% the product of crushing ledge rock at a quarry.

c. Procedure. Place crushed stone in loose lifts of no more than 1 ft. and compact by tamping with four to six passes of a hand-guided compactor.

END OF SECTION C

PART I

SECTION D

PACKAGING AND MARKING

D.1. PRESERVATION, PACKAGING, AND MARKING.

Preservation, packaging, and marking for all items delivered shall be according to standard commercial practice and adequate to ensure acceptance by common carrier and safe arrival at destination.

All containers shall be plainly marked on or adjacent to the exterior shipping label to show the contract number, description of contents, and the contractor’s name.

Packages can be addressed/delivered to:

U.S. Department of Transportation Saint Lawrence Seaway Development Corporation 251 Fregoe Road

END OF SECTION D

SECTION E
INSPECTION AND ACCEPTANCE

52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this address: www.arnet.gov/far/

I. FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996)

E.1. Inspection of services provided hereunder shall be made by the Contracting Officer’s Technical Representative (COTR) or any inspectors designated the Contracting Officer. The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer’s written authorization.

All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.

END OF SECTION E
PART I
SECTION F
DELIVERIES OR PERFORMANCE

52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this address: www.arnet.gov/far/

I. FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.242-14 SUSPENSION OF WORK (APR 1984)

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

(The clause is modified to read as follows:)

The Contractor shall be required to: (a) commence work under this contract within ten (10) calendar days after the date the Contractor receives the notice to proceed; (b) prosecute the work diligently; and (c) complete the entire work ready for use not later than December 15, 2011. The time stated for completion shall include final cleanup of the premises. Please note that the on-site portion of the work shall not commence until the Corporation has secured the appropriate permits.

F.1. SCHEDULES FOR CONSTRUCTION CONTRACTS.

The Contractor shall prepare and submit to the Contracting Officer after award and prior to a preconstruction meeting, for approval, a copy of a project schedule and work plan as described in Section C, Technical Provisions, Clause C.15, Submittals.

END OF SECTION F

SECTION G
CONTRACT ADMINISTRATION DATA

G.1. CONTRACT ADMINISTRATOR

Patricia L. White, Contracting Officer, Saint Lawrence Seaway Development Corporation, 180 Andrews Street, PO Box 520, Massena, New York, 13662-0520, telephone number (315) 764-3236, facsimile number (315) 764-3268, and e-mail address patricia.white@dot.gov will administer the contract.

No oral or written statement by anyone other than the Contracting Officer shall modify or otherwise affect any contract clause. Only Contracting Officers acting within their scope of authority can execute contract modifications on behalf of the Government (Corporation). No claim by the Contractor for any increase in the contract price or adjustment in the performance schedule shall be valid except as may be covered by a duly executed contract modification.

G.2. REQUIRED INSURANCE

a. The Contractor shall procure and maintain during the entire period of his/her performance under this contract the following minimum insurance coverage:

(1) Workmen's Compensation Coverage: As required by applicable New York Statutes in effect as of contract award date.

(2) Comprehensive General Liability Insurance:

Bodily Injury Liability: $500,000 each person; $1,000,000 each accident

(3) Comprehensive Automotive Liability Insurance:

Bodily Injury Liability: $500,000 each person; $1,000,000 each accident
Property Damage: $50,000 each accident

b. Prior to commencement of work hereunder, the Contractor shall furnish to the Contracting Officer a certificate or written statement of the required insurance including Professional Liability Insurance. The policies evidencing required insurance shall contain an endorsement to the effect that cancellation or any material change in the policies adversely affecting the interests of the Corporation in such insurance shall not be effective until ten (10) days after written notice thereof to the Contracting Officer.

c. The Contractor shall insert the substance of this clause, including this paragraph (c), in subcontracts under this contract that require work on a Government installation and shall require subcontractors to provide and maintain the insurance required in paragraph (a). The Contractor shall maintain a copy of all subcontractors’ proofs of required insurance, and shall make copies available to the Contracting Officer upon request.

G.3. CONTRACTING OFFICER DELEGATION OF AUTHORITY

The Contracting officer may delegate all or part of her authority to administer this contract. Such a delegation will be in writing and will describe the extent of the authority delegated. The Contracting Officer will provide a copy of such delegation to the Contractor.

SECTION G (Cont’d)

G.4. CONTRACTING OFFICER'S TECHNICAL REPRESENTATIVE (COTR)

The Contracting Officer may designate Government personnel or other Contractors to act as the Contracting Officer’s Technical Representative (COTR) to perform functions under the contract such as review and/or inspection and acceptance of supplies, services, including construction, and other functions of a technical nature. The Contracting Officer will provide a written notice of such designation to the Contractor within five working days after contract award or for construction, not less than five working days prior to giving the contractor the notice to proceed. The designation letter will set for the authorities and limitations of the COTR under the contract. The COTR will ensure that the Corporation's project objectives are met, along with providing necessary information, direction, coordination, etc., within the contractual work description. The COTR is not authorized to change any of the terms or conditions of this contract nor sign documents such as contracts or contract modifications.

When in the opinion of the Contractor, the COTR requests work outside the existing scope of the contract, the Contractor shall promptly notify the Contracting Officer in writing. The Contractor shall take no action until the Contracting Officer has issued a contractual change or otherwise resolved the issue. A copy of all written correspondence to the COTR by the Contractor shall also be mailed or otherwise furnished to the Contracting Officer at the address set forth in Clause G.1.

G.5. ADDITIONAL WORK

a. The Contractor shall not perform any additional work without the Contracting Officer's authorization.

b. The Contractor, in connection with any proposal he/she makes for a contract modification, shall furnish a price breakdown directly to the Contracting Officer, itemized as required by the Contracting Officer. Unless otherwise directed, the breakdown shall be in sufficient detail to permit an analysis of all materials, labor, equipment, subcontract, overhead costs, and profit covering all work involved in the modification whether such work was deleted, added or changed. Any amount claimed for subcontracts shall be supported by a separate, similar price breakdown. If the proposal includes a request for a time extension, justification shall be furnished with the proposal.

c. The Contracting Officer reserves the right to accomplish additional work on the basis of a negotiated fixed price when it is in the best interest of the Corporation.

G.6. REQUEST FOR PROGRESS PAYMENTS

The contractor shall furnish a breakdown of the total contract price, showing the amount included therein for each principal category of work, which shall substantiate the payment amount requested, in order to provide a basis for determining progress payments, in such detail as requested by the Contracting Officer.

The Government shall make progress payments monthly as the work proceeds on estimates of work accomplished which meets the standards of quality established under the contract, as approved by the Contracting Officer.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .