Amendment_0001_-_AR_ERFO_BUFF_2015-1(3).pdf

PDF 133 KB Posted

Attached to
Buffalo National River Federal contract opportunity
Solicitation number
DTFH71-17-B-00025
Issued by
Department of Transportation Federal Highway Administration

About this file

The Bid Opening date of June 29, 2017, at 2:00 p.m. EST will remain the same.

View the file

Other files for this federal contract opportunity

Other files attached to Buffalo National River, newest first.
File Type Posted
ROBO_-_AR_ERFO_BUFF_2015-1(3).pdf PDF
VETS-4212_Form.pdf PDF
Categorical_Exclusion_Form_NEPA.pdf PDF
FP14_Eng.pdf PDF
IFB_Solicitation_-_AR_ERFO_BUFF_2015-1(3).pdf PDF
ADV_Bidder's_Qualifications_Form.doc DOC document
Plans_-_AR_ERFO_BUFF_2015-1(3).pdf PDF
Synopsis_-_AR_ERFO_BUFF_2015-1(3).doc DOC document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

DTFH7117B00025

x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

Sterling VA 20166-6511

EFLHD-CO

21400 Ridgetop Circle Construction Office Eastern Federal Lands Highway Div.

Federal Highway Administration

Sterling VA 20166-6511

EFLHD-AC

21400 Ridgetop Circle Acquisitions Office Eastern Federal Lands Highway Div.

Federal Highway Administration

SEE BLOCK 1406/27/20170001

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

05/31/2017

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Project: AR ERFO BUFF 2015-1(3)

The purpose of this Amendment is to:

1) Revise the Special Contract Requirements (J-pages) to remove load restrictions for hauling on National Park Service roads.

2) Provide a summary of responses to questions/clarifications submitted by potential bidders.

The Bid Opening date of June 29, 2017, at 2:00 p.m. EST will remain the same.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

NSN 7540-01-152-8070

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

Amendment No. 0001

Info Page 1 of 1

U.S. DEPARTMENT OF TRANSPORTATION

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

Project AR ERFO BUFF 2015-1(3)

Buffalo National River Solicitation: DTFH71-17-B-00025

The purpose of this Amendment is to:

1) Revise the Special Contract Requirements (J-pages) to remove load restrictions for hauling on National Park Service roads.

2) Provide a summary of responses to questions/clarifications submitted by potential bidders.

The Bid Opening date of June 29, 2017, at 2:00 p.m. EST will remain the same.

Special Contract Requirements (J Pages) changes

1. Delete the first paragraph of Subsection 104.05, page J-2.

2. Delete Table 104-1, page J-2.

Questions/Clarifications

Bidders can send written questions or inquiries for clarification to: eflhd.contracts@dot.gov.

Questions can be submitted at any time, but questions submitted within 7 days of the bid opening may not be answered in time for the bidder to properly incorporate the responses into their bids.

The following questions and issues were submitted via email. The Government response or clarification is provided. Due to the repetitive nature of several questions and issues, the wording of the questions may have been revised and some questions have not been included.

The Government’s direct response to the sender may also have been updated below for better clarity.

1. Is the FHWA providing the SWPPP for this contract? I did not find it addressed anywhere in the contract.

Response: A Stormwater Pollution Prevention Plan (SWPPP) is not required for this project. The Contractor is responsible for installing, maintaining, and removing the erosion and sediment control measures according to the plans and specifications. The Contractor is also responsible for complying with all requirements of the permits obtained for the project, which include a U.S. Army Corps of Engineers Section 404 Nationwide Permit and State 401 Water Quality Certification. The Water Quality Certification will be provided before the award of the contract.

2. Special Contract Requirement 104.05 is too restrictive. If the contractor must follow the load restrictions listed, the necessary equipment and materials cannot get to the jobsites. A fairly large excavator will be necessary to place the class 4 riprap and a fairly large excavator or a crane will be necessary to place the articulated concrete block. The trucks delivering the aggregates, riprap, and articulated concrete block will also most likely exceed the load restrictions listed. Can the contractor get a variance on these restrictions?

Response: The load limits shown in Table 104-1 will be removed in an amendment. The Contractor will be required to meet legal load restrictions according to FP-14 Subsection 104.05.

3. When does the government anticipate issuing the NTP? The time of year that this work will take place will impact the price.

Response: The date of the NTP cannot be determined at this time. See the Bid Schedule Instructions for information regarding the expected beginning of construction activities.

4. I am requesting an “Or/Equal” status on the articulated concrete block mat that is specified on the Buffalo National River project. We have a similar product that we believe can meet everything you are looking for. Our mat system utilizes air entrained wet cast concrete. This mix design allows for higher strengths and is able to handle freeze/thaw cycles much better than a dry cast mix. I’ve included the product brochure of the proposed system. I’ve also included a screen shot of the product we are requesting the “or/equal” status.

mailto:eflhd.contracts@dot.gov

Response: Please see Note 2 on Sheet S06 of the plans, the articulated concrete block (ACB) revetment mat details and dimensions shown on Sheet S06 have been provided as a general guide only. The actual details and dimensions of the ACB revetment mat used by the Contractor in construction may vary, depending on which specific product is submitted and approved. The Contractor may submit for approval any ACB revetment mat meeting the requirements of Section 258, Subsection 725.09(h), and Subsection 725.09(i). Material submittals will be reviewed and approved after award of a contract.

5. Section 152 specs. Will the state set/ find all of the control points before start of job? I went to all the sites last week and could not find any points.

Response: The Government will not replace control points. As specified in Subsection 152.04, the Contractor is responsible for reestablishing any missing control points and stakes set by the Government.

6. This question is referring to plans (Detail E157-08 in-stream diversion berms). When we put up a diversion wall to divert water while we work in creek for each phase. What are the proper steps for installing the wall initially since water will be running in stream. I am wondering if we will be able to get in stream to level the spot for the diversion wall and install the wall so we can start diverting the water.

Response: The Government will not dictate the means and methods used by the Contractor. The Contractor is responsible for installing any stream diversions necessary to complete the work, which includes preparing plans for approval by the CO. As stated in Note 1 on Detail E157-08, on sheet S04 of the plans, the diversion methods shown are suggested configurations only. The Contractor may choose one of the options shown or use an alternative means of diverting the stream. The work must comply with the requirements of permits obtained for the project.

7. Section 705 specs. States that the rock needs to be color of rock in nature. That would be a dirty white or bleached brown color of the river rock. That would be next to impossible to find rock of that color in a class 4 riprap size. I am wondering what is the flex on that? We would be using the concrete revetment which is white/ light grey and a granular backfill that is also a white/ light grey color. All 3 of these items would be placed right next to each other. Please clarify for me.

Response: The intent is to use rock that matches the character of natural rock outcrops in the project area, not the streambed material.

8. I visited all 4 sites last week. The work area at wells creek seems to have been washed out.

There is a tree down where the bank had washed out from underneath it. It looks like some of the road that should be there has washed away. What is process in case there is more embankment to be installed. Change order?

Response: The Contractor is advised to bid on the work as shown in the plans. The work limits and pay item quantities will be adjusted as necessary to fit the actual field conditions at the time of construction. Changes made during construction will be addressed through contract modifications in accordance with FAR Clause 52.243-4 Changes. See Subsection

101.04 for additional information.

Amendment 1 info.pdf
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
Amendment No. 0001
Project AR ERFO BUFF 2015-1(3)
Solicitation: DTFH71-17-B-00025