Drawing.pdf
PDF 6 MB Posted
- Attached to
- REPLACE GENERATOR Federal contract opportunity
- Solicitation number
- 140P6423Q0001
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Specifications_-_Updated_0002.pdf | ||
| 26_24_13_Switchboard_Pictures_0002.pdf | ||
| Sol_140P6423Q0001_Amd_0002.pdf | ||
| Sol_140P6423Q0001_Amd_0001.pdf | ||
| Specifications.pdf | ||
| Past_Performance_Questionnaire.doc | DOC document | |
| Sol_140P6423Q0001.pdf | ||
| Construction_Contract_Administration.docx | DOCX document | |
| Technical_Questionnaire.docx | DOCX document | |
| Construction_Wage_Determination.pdf | ||
| Price_Schedule.xlsx | XLSX spreadsheet | |
| Price_Schedule.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
HEADQUARTERS COMPLEX
REPLACE GENERATOR
INDIANA DUNES NATIONAL PARK
VICINITY MAP REGIONAL MAP
LOCATION MAP
INDIANA DUNES NATIONALPARK1100 NORTH MINERAL SPRINGS ROAD
PORTER, IN 46304
80051
G A
S G
A S
DEMOLITION KEY NOTES:
1. REMOVE EXISTING DUCTWORK BETWEEN GENERATOR
AND LOUVER.
2. DISCONNECT AND REMOVE EXISTING GENERATOR, AND
GENERATOR EXHAUSTER.
3. SHUT GAS VALVE AND REMOVE GAS PIPING BETWEEN
VALVE AND GENERATOR.
4. DISCONNECT AND REMOVE THE ONAN 12.5 GENSET
GENERATOR, AND GENERATOR EXHAUSTER. DISABLE
TRANSFER SWITCH.
5. DISCONNECT AND REMOVE TRANSFER SWITCH.
6. DISCONNECT AND REMOVE GENERAL DUTY 600 AMP
240-VOLT 3-POLE INDOOR FUSIBLE SAFETY SWITCH.
7. EXISTING FANS TO REMAIN.
x
DEMOLITION GENERAL NOTES:
1. THE OWNER SHALL HAVE THE FIRST RIGHT OF SALVAGE
FOR ALL MECHANICAL, ELECTRICAL, AND PLUMBING ITEMS
BEING REMOVED OR DEMOLISHED. IF OWNER DECLINES,
THE CONTRACTOR SHALL REMOVE FROM THE PREMISES
AND DISPOSE OF PROPERLY. VERIFY OWNER'S INTENT
PRIOR TO REMOVAL OR DEMOLITION.
2. REMOVE ALL DUCTWORK, PIPING, AND EQUIPMENT SHOWN
DASHED. INFORMATION PERTAINING TO THE EXISTING
BUILDING HAS BEEN OBTAINED THROUGH THE BUILDINGS
ORIGINAL DRAWINGS WHERE AVAILABLE. REPORT
DISCREPANCIES TO THE ARCHITECT AND ENGINEER PRIOR
TO ANY DEMOLITION. CONTRACTOR SHALL FIELD VERIFY
ALL EXISTING CONDITIONS PRIOR TO COMMENCING
WORK.COORDINATE SHUTDOWN OF ALL UTILITIES FOR
DEMOLITION WORK WITH THE OWNER. DISCONNECT,
DEMOLISH, AND REMOVE MECHANICAL SYSTEMS,
EQUIPMENT, AND COMPONENTS INDICATED AS HATCHED
TO BE REMOVED.
3.
PIPING TO BE REMOVED: REMOVE PORTION OF PIPING
INDICATED TO BE REMOVED AND CAP OR PLUG REMAINING
PIPING WITH THE SAME OR COMPATIBLE PIPING MATERIAL.
4. PIPING TO BE ABANDONED IN PLACE: DRAIN PIPING AND
CAP OR PLUG PIPING WITH THE SAME OR COMPATIBLE
PIPING MATERIAL.
5. DUCTS TO BE REMOVED: REMOVE PORTIONS OF DUCT
AND PLUG REMAINING DUCTS WITH THE SAME OR
COMPATIBLE DUCTWORK MATERIAL.
6. DUCTS TO BE REMOVED AND REPLACED: REPLACEMENT
DUCTS WITH THE SAME OR COMPATIBLE DUCTWORK
MATERIAL.
7. EQUIPMENT TO BE REMOVED: DISCONNECT AND CAP
SERVICES AND REMOVE EQUIPMENT.
8. EQUIPMENT TO BE REMOVED AND REINSTALLED:
DISCONNECT AND CAP SERVICES AND REMOVE, CLEAN,
AND STORE EQUIPMENT. WHEN APPROPRIATE, REINSTALL,
RECONNECT, AND MAKE EQUIPMENT FULLY OPERATIONAL.
9. EQUIPMENT TO BE REMOVED AND SALVAGED:
DISCONNECT AND CAP SERVICES AND REMOVE
EQUIPMENT AND DELIVER TO OWNER.
10. IT IS HIGHLY RECOMMENDED CONTRACTOR VISIT SITE AND
FIELD VERIFY ALL EXISTING CONDITIONS PRIOR TO
BIDDING PROJECT.
11. COORDINATE DEMOLITION WITH THE WORK OF OTHER
TRADES. PROVIDE TEMPORARY UTILITIES AS REQUIRED
TO ALLOW THE WORK OF OTHER TRADES TO PROCEED.
12. REMOVE EXISTING SHED INCLUDING WALLS, ROOF, SLAB,
AND ELECTRICAL PANELS. INSTALL A NEW TRANSFER
SWITCH AND ELECTRICAL CONDUITS FOR AN OUTDOOR
GENERATOR UNIT.
INDIANA DUNES NATIONALPARK1100 NORTH MINERAL SPRINGS ROAD
PORTER, IN 46304
80051
X
HVAC KEY NOTES:
1. INSTALL NEW GENERATOR WITH HEAVY DUTY SAFETY
SWITCH, AND CONNECT POWER TO IT.
2. CONNECT THE GAS FROM THE EXISTING GAS VALVE TO
THE GENERATOR. GAS PIPING SIZE SHALL MATCH THE
EXISTING AND HAVE A FLEXIBLE CONNECTION.
3. INSTALL NEW TRANSFER SWITCH AND CONNECT TO
GENERATOR.
4. INSTALL NEW 6-IN THICK CONCRETE EQUIPMENT PAD.
SIZE OF PAD TO OFFSET 1-FOOT FROM ALL SIDES OF
GENERATOR HOUSING, OR MATCH MANUFACTURER'S
RECOMMENDED SIZE OF EQUIPMENT PAD, WHICH EVER IS
LARGER.
G A
S G
A S
GAS
TRANSFER
SWITCH
GENERATOR
INDIANA DUNES NATIONALPARK1100 NORTH MINERAL SPRINGS ROAD
PORTER, IN 46304
80051
LATEST NATIONAL ELECTRICAL CODE
CONNECT GENERATOR TO EXISTING NATURAL GAS LINE TO MEET
MANUFACTURER AND NORTHERN INDIANA PUBLIC SERVICE COMPANY'S
(NIPSCO) REQUIREMENTS AND RECOMMENDATIONS.
| Sheets and Views |
| COVER-COVER SHEET |
| help |
| E1.pdf |
| Sheets and Views |
| MEP-E1 |
| ED1.pdf |
| Sheets and Views |
| MEP-ED1 |
| G1.pdf |
| Sheets and Views |
| MEP-G1 |