Draft SOW Sumas FA and Sprinkler Rev 06032.pdf

PDF 405 KB Posted

Attached to
Sumas Fire Alarm and Fire Suppression Modernization Federal contract opportunity
Solicitation number
EQ10-PCP-0014
Issued by
General Services Administration Public Buildings Service Region 10

About this file

This document outlines a scope of work for a design-build project to replace the fire alarm and suppression systems at the Sumas Land Port of Entry in Sumas, Washington. The project involves replacing the existing fire alarm control panel and devices and installing a new fire suppression sprinkler system throughout the 50,000 square foot occupied facility. Interested small businesses are requested to respond with capabilities statements by June 21, 2021 for consideration to complete the project, estimated to be valued under $1 million. Respondents must demonstrate experience designing and installing similar fire protection systems in occupied federal buildings, and key personnel are required to have qualifications in project management, construction supervision, quality control, and fire alarm and sprinkler system design. The selected contractor must provide training and warrant all labor and materials for one year following acceptance of the completed project.

View the file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sumas Land Port of Entry/Fire Suppression System Replacement D/B SOW Page 1

Statement of Work for

Design-Build (DB) Contract

PROJECT IDENTIFICATION

Project Name: Fire Alarm and Fire Suppression System Modernization Design-Build

(DB) Construction Project, Sumas Land Port of Entry (LPOE), Sumas, Washington

Project Number: 47PL0120R0025

Region: 10 – Northwest/Arctic Region

Building Name: Sumas Land Port of Entry – WA0653SB

Building Address 103 Cherry Street, Sumas, WA 98295

Sumas Land Port of Entry/Fire Suppression System Replacement D/B SOW Page 2

Sumas Land Port of Entry (LPOE) Fire Alarm and Fire Suppression System Design and

Modernization

Scope of Work

The objective of this system replacement scope of work is to describe all the performance criteria expected at project completion in order to design and replace the current fire alarm control panel, conductors and associated devices at the Sumas LPOE. In addition, the scope of work will include installation of a code compliant Fire suppression system. The current fire panel that serves the LPOE has reached the end of its useful life and needs to be replaced. The manufacturer of the current fire alarm panel and hardware is Simplex Grinnell (Simplex 4002). The existing dry fire suppression system is partially installed (Primary and Secondary Canopies as well as Warehouse and Cargo Canopy); however, the existing fire sprinkler cross main has leaked and has been repaired but needs to be replaced.

This scope of work for fire alarm replacement shall include the design and replacement of the fire panel with horn/strobe type of notification devices, and all other fire life safety devices which upon completion will comprise a fully operational and code compliant system. Project will consist of the replacement of complete fire alarm system to include all control panels, devices, wiring, and the addition of new conduits and/or risers where necessary to ensure a fully functional, code compliant class “A” system when complete including notification devices serving the Attic’s Walkway and the Attic Fan Room. Fire Alarm Control Panel (FACP) installation must conform to all applicable codes and standards. Please be advised that fire alarm notification devices may not be require under the canopy serving the officers booth/vehicles.

The incinerator building is not part of the SOW of the project, however, if the Post Indicator Valve (PIV) tamper switch located adjacent to this building is currently being monitored by the existing fire alarm system, this is included in the SOW of the project and usage of the existing pathway is strongly encouraged to be re-used. If the PIV tamper switch is not currently monitored by the existing fire alarm system and is located in the area being described, it will not be included in the current SOW of the project.

The scope of work for fire suppression sprinkler system will consist of all design and installation for a complete, code compliant fire sprinkler system throughout the entire facility which will include the replacement of the existing dry fire suppression systems cross main. Installation of fire sprinklers at the attic space shall be limited to the Fan Room which shall be provided with an isolation valve that serves this room (only). Location of this valve will be place in the main building and not in the attic space. The contractor shall be responsible to gather all necessary information which may include testing the existing suppression system. Currently, GSA does not have any recent flow and/or pressure information serving the existing fire suppression system. In order to mitigate costs GSA will consider extending the existing dry fire sprinkler system throughout the entire building.

No assumption of current systems code compliance should be made. Contractor will be responsible for complete design and installation which conforms to all current codes and standards. All electrical connections, terminations and integration to existing equipment will be the responsibility of installing contractor and all costs for associated effort will be included in cost proposal. All as-built information provided by GSA must be field verified by contractor prior to design. Due diligence site walk to confirm space configurations is required and will be the basis of design for fire alarm and suppression sprinkler systems. Appropriate time for this due diligence inspection must be built into CPM schedule.

Sumas Land Port of Entry/Fire Suppression System Replacement D/B SOW Page 3

The replacement of the fire alarm and installation of fire suppression system will be accomplished while facility is fully occupied. The D/B Team will be required to ensure minimal disruption to tenants and their mission. The DB Contractor will provide required fire protection and safety of the fully occupied space during construction to will be monitored at all times. The Contractor shall submit a fire protection plan that in accordance with PBS P-100 and R10 Fire Alarm System Installation Policy. GSA reserves the right to stop work any time tenant’s mission is adversely impacted.

1. GSA envisions a highly collaborative D/B delivery approach for this project. The expectation is that the D/B Team will work closely with all stakeholders to deliver a project that meets the expectations and needs of all stakeholders and GSA’s requirements for a fully functional, code compliant fire alarm and fire suppression systems. Further, since this is a design/build retrofit project, there are existing fire suppression materials and/or equipment installed in the building. The Design Build Contractor shall include any missing materials and/or equipment in their project costs to ensure a fully operational, code compliant, fire suppression sprinkler system.

2. All project documentation shall be submitted through the Google Drive Folder set up specifically for this project.

Standards. All efforts, materials and work performed under this contract shall comply with and/or shall be with knowledge and forethought of applicable federal, state and local building codes based on the requirements of the current edition of recognized and accepted building standards, codes, and regulations, including, but not limited to the following: Uniform Building Code (International Conference of Building Officials.)

▪ National Environmental Standards for Hazardous Air Pollutants (Environmental Protection Agency.)

▪ Part 1910 Code of Federal Regulations, Occupational Safety and Health Standards.

▪ PART 1926 Code of Federal Regulations - Safety and Health Regulations for Construction

▪ GSA P-100 - Facilities Standards for the Public Building Service 2018 version.

http://www.gsa.gov/portal/content/104821

▪ P-120 Project Estimating Requirements for the Public Buildings Service

▪ ABAAS / ADA for federal facilities

▪ Underwriters Laboratories codes applicable to Fire alarm systems

▪ Hazardous materials inventory (to be provided)

▪ GSA Region 10 – Fire Alarm Design, Installation and testing

▪ GSA Region 10 - Policy for Fire Watches for Fire Suppression Related Projects

▪ PBS CAD Standards

▪ NFPA – (National Fire Protection Association)

▪ NFPA 13

▪ NFPA 14

▪ NFPA 20

▪ NFPA 72

▪ NFPA 101

▪ NFPA 70

A. General Description - Fire alarm system:

1. Non-coded, addressable fire alarm system with manual and automatic alarm initiation;

automatic sensitivity control of certain smoke detectors; and multiplexed signal transmission dedicated to fire alarm service only.

Sumas Land Port of Entry/Fire Suppression System Replacement D/B SOW Page 4

2. Smoke detectors, duct-mounted smoke detectors, heat detectors, manual pull stations, tamper switches for fire sprinkler control valves, water flow detectors for fire sprinklers.

3. Interfacing for fan shut-down Contractor will be required to provide all electrical terminations and equipment to ensure a fully functional, code compliant system.

4. Fully addressable initiating devices and control devices.

5. Integral back-up batteries in all control panels.

6. Supervision of primary (110 volt AC) power, batteries, wiring, data communications, panel status, devices status, and general system integrity.

7. UL-listed system, consisting of devices UL-listed as fire alarm appliances and listed as compatible with the system.

B. Initiating Functions:

1. Alarm Signals: Audible and visual signals in the affected zones, and audible indicators and visual annunciators to indicate an activation signal from the following:

a. Smoke detectors, except duct mounted smoke detectors.

b. Heat detectors.

c. Manual pull stations.

d. Sprinkler flow switch.

e. Other initiating alarm devices.

2. Supervisory Signals: Audible and visual indicators to indicate the following:

a. Closed or partially closed sprinkler valve, via its tamper switch.

b. Alarm signals from duct-mounted smoke detectors.

c. Supervisory alarm signals from the emergency generator control.

3. Trouble Signals: Audible and visual indicators at the FCC / control center to indicate the following:

a. Open circuit, ground fault, or short circuit of initiating device or circuit, notification device or circuit, control device, or data communications wiring.

b. Loss of data communications from any control panel, or from any addressable device.

c. Irregular changes in smoke detector sensing levels, such as when detection chamber is dirty.

d. Loss of primary AC power.

e. Low backup battery voltage, or missing or poorly connected battery.

f. Missing or faulty placement of a system module.

C. Indicating Functions:

1. Visual Alarms:

a. Shall flash continuously during an alarm, silencing of the audible alarms shall not stop the flashing of the strobes.

b. Non-volatile, digital storage mechanism.

D. Electrical Supervision and Wiring Styles:

1. Addressable initiating and control circuits: Looped Class A.

2. Indicating circuits (audio, strobes, bells): Looped Class A.

3. Data communications circuits between panels: Class A wiring, redundant circuits and paths, separate conduits for each circuit and path.

4. Looped Class A circuits shall be installed in conduits routed as a loop. Return legs shall not be in the same conduit as the departing leg. The device and all devices on the circuit shall be operable during one single open circuit or ground fault condition no matter where the open circuit or ground fault appears.

5. Looped Class A circuits shall not have any devices connected by "T" tapping, wire nuts or splices.

6. Circuit faults shall activate a trouble signal, by type and location, with time and date.

E. Interfacing functions:

Sumas Land Port of Entry/Fire Suppression System Replacement D/B SOW Page 5

1. Central Station Reporting:

a. Non-zoned alarm, supervisory, and trouble signals shall automatically report to the

Central Station via communicators provided by the contractor.

2. HVAC Control:

a. Provide Form-C "dry contact" outputs of each zone to the Building Control System at a terminal cabinet in the building control room or adjacent to the FACP, fan shutdown, fire dampers, etc.

b. Provide Form-C "dry contact" outputs of each duct-mounted smoke detector, at a terminal block in the detector housing, for shutdown of fans associated with each detector.

F. Performance Requirements:

1. Minimum Capacity of Back-up Batteries: 24 hours of non-alarm (supervisory) operation, followed by 15 minutes of alarm operation.

2. Maximum Response Times: 15 seconds between activation of an initiating device and activation of indicating appliances, and 200 seconds between occurrence of a trouble condition and activation of trouble indicators.

3. Surge Protection:

a. Provide surge protection for all conductors of data communications line and addressable signal lines.

G. Programming Requirements:

1. Program zoning of annunciation, initiation devices, indicating devices, interfacing outputs, and LCD annunciation, and all other functions which are programmable.

2. Programming shall be stored via non-volatile memory. Provide back-up copy, with capability to reload all programming of each panel within 1 hour per panel.

1.2 GENERAL OPERATION – Fire Alarm System

A. The system shall be solid state, microprocessor based, using a true digital format between the CPU and each addressable device. Systems which do not transmit digital data between CPU and devices over a one (1) pair cable are not acceptable.

B. Adding points within the system, up to its maximum point capacity shall not require memory additions.

C. Control panels, subordinate control panels and remote power supplies shall be sized to accommodate 25% future growth beyond the scope of the current project. All secondary power supply batteries shall be sized for future system growth. Spare battery capacity required by NFPA 72 and local codes shall be in addition to future system growth capacity.

D. Under normal conditions the fire alarm control panel shall display a "SYSTEM NORMAL" message and the current time and date.

E. Should an abnormal condition be detected the appropriate LED (Alarm, Supervisory, or Trouble) shall flash. The panel audible signal shall pulse for alarm conditions and sound steadily for trouble and supervisory conditions.

F. The panel shall display the following information relative to the abnormal condition of a point in the system. These three characteristics relative to an abnormal condition of a point shall be displayed simultaneously:

1. Custom location label (80 characters minimum)

2. Type of device (i.e. smoke, manual station, water flow)

3. Point status (i.e. alarm, trouble, and supervisory signals)

Sumas Land Port of Entry/Fire Suppression System Replacement D/B SOW Page 6

G. All information displayed by the fire alarm control panel shall also be capable of being transmitted and printer. Include UL fire alarm approved printer.

1.3 SPARE COMPONENTS

A. Furnish the Owner with the following spare components:

Quantity Item

5 Spare lamps and LED’s for each type of field replaceable lamps 2 Manual stations.

2 Ceiling-mount photoelectric smoke detectors, with bases.

2 Photoelectric duct smoke detectors, with bases.

5 Heat detectors, with bases.

3 Each type of fire alarm visual notification device(s) provided.

3 Each type of fire alarm audio notification device(s) provided.

1 box Fan-fold paper (1000 sheets minimum) for printer.

1 Spare ribbons for Control Console printer.

1 Back-up copies of all programming data and software.

3 Spare modules of each type used in the system 3 Spare fuses for each type and amperage used in the system 5 Fire sprinklers (per type) provide and located in the fire sprinkler cabinet

B. Tools:

1. Provide 2 spare tools (or keys) to open the manual stations.

2. Provide 2 tools for testing the smoke detectors.

C. Keys:

1. Provide 5 complete sets of keys.(Such as FACP, booster panel, manual pull, etc)

2. Each set shall contain one key for each type and code of lock used in the system.

3. Label each key with its function, and the location of the locks for which it is cut. Labeling may be permanently applied directly to the keys, or attached as a tabulated list showing the key numbers that are stamped on the key.

1.4 SUBMITTALS – Fire Alarm and Fire Suppression

General: Provide submittals as per the following.

A. Incomplete submittals will not be acceptable and will be returned without review. All project document controls must comply with GSA 3490.2 for Sensitive but Unclassified documents.

B. In-progress CD (65% and 95% design) submissions. In addition, 100% conformed set will be provided which will incorporate all 95% submittal comments.

1. Contractor shall prepare and submit separate in-progress CD submissions for each system (fire alarm and fire suppression) in accordance with GSA P-100. Submissions shall contain all calculations and drawings and Design Basis Narrative with enough detail for a GSA review at each design phase. Submittal shall emphasize project phasing and coordination efforts. Prepare construction specifications (in Masterspec format) and engineering drawings to include all necessary work for a fully functioning, and Code compliant fire alarm system and fire suppression sprinkler system.

Sumas Land Port of Entry/Fire Suppression System Replacement D/B SOW Page 7

2. GSA project team will have 10 working days for each design phase review. All comments will be answered and responses provided to GSA in writing before progressing to next design phase. Design Review Meeting review will be scheduled by the GSA PM and contractor upon completion of the GSA review period.

C. Product Data: Submittals shall include a compilation of manufacturer's catalog or specification sheets of all system components. Items being provided shall be clearly indicated. Any variations of the submittal from the specifications shall be clearly indicated. Include the following additional information:

1. Point Schedule

2. Complete schedule of customized English message formats of alarms and troubles for system.

3. Battery systems and standby battery load calculations.

4. Fire Alarm zone and address schedule including alphanumeric description for each monitor and control point.

5. Actual graphic drawings.

6. Outputs zone schedule for off-premise UL Central Station Monitoring.

7. Complete sequence of operations for all fire alarm system functions.

8. Fire suppression components

9. Fire suppression zones and piping configurations showing all system details

10. Fire suppression system calculations

D. Shop Drawings

1. All drawings shall be done in accordance with the PBS CAD Standards. A copy of the PBS CAD Standards will be forwarded to the successful contractor upon award of the contract.

The standards may be viewed on the internet at www.gsa.gov/pbs/cifm. Hard copies of the drawings shall also be forwarded for review.

2. Riser Diagrams. Fire alarm materials supplier and/or subcontractor shall develop CAD based original fire alarm riser diagram to show main geographical, fire alarm zones and point to point wiring requirements.

3. Floor Plans. CADD based floor plans shall be drafted to show conduit routing, device locations, end of line resistors, wire count and color coded wiring between device locations on each plan. Show room names and numbers for each room where a fire alarm device is located.

4. Release of CADD files for shop drawings. Contractor may request to utilize the project CAD drawing files in producing shop drawings. Request shall be made by design team via "Agreement for Release of CADD Files" letter.

5. Ownership. All original shop drawings shall become the property of the owner at the completion of the project.

6. All information contained in shop drawings must be field based and verified.

E. Resubmit to Authorities Having Jurisdiction if required to make clarifications or revisions to obtain concurrence or approval.

F. Provide device drawing submittal indicating audible and visual alarms device locations only for coordination with the authority having jurisdiction (AHJ). Obtain GSA approval of audible and visual alarm device locations before preparing final shop drawing submittals.

G. Provide sprinkler system device drawing submittal indicating all device locations for coordination with AHJ Obtain approval of all drawings before preparing final shop drawings.

I. Installer Certificates: Signed by manufacturer certifying that installers comply with requirements.

J. Field Test Reports: Indicate and interpret test results for compliance with performance requirements. Comply with NFPA 72, NFPA 13, 14 and 20 if pumps are installed

K. Certificate of Completion: Comply with NFPA 72.

Sumas Land Port of Entry/Fire Suppression System Replacement D/B SOW Page 8

L. Operation and Maintenance Manual. Include record drawings, Certificate of Completion and test results

1. List of equipment installed, locations, serial numbers, make/model number, power location, etc. Include a spreadsheet version that can be opened in Microsoft Excel

2. Original Manufacture’s and Installer’s warranties.

3. Original Prime Contractors warranty.

4. Manufacturer’s product data, instruction/maintenance manuals.

M. Applicable documentation as identified in the P100.

1.5 RECORD DRAWINGS

A. All Record drawings shall be drawn in accordance with PBS CAD Standards. Electronic copy of the drawings shall be submitted via PDF and CAD along with one (1) hard copy and one (1) CD archival electronic copy. Record drawings shall clearly indicate:

1. Actual routing of all raceways, piping and location of all devices to include junction boxes.

2. Actual cable types, numbers and routing.

3. Actual system wiring diagrams, connection diagrams and interface of all components in the system.

PART 2 - PRODUCTS

2.1 MANUFACTURERS – Fire Alarm System

All equipment for fire alarm system shall be the product of a single manufacturer except that certain individual components which are regularly used as part of the system may be the product of a different manufacturer.

2.2 PRINTOUT OF EVENTS – Fire Alarm Control Panel (FACP)

On receipt of the signal, print alarm, supervisory, and trouble events. Identify zone, device, and function. Include type of signal (alarm, supervisory, or trouble), and date and time of occurrence. Differentiate alarm signals from all other printed indications. Also print system reset event, including the same information for device, location, date, and time. Commands initiate the printout of a list of existing alarm, supervisory, and trouble conditions in the system and a historical log of events.

2.3 Fire Alarm Control Panel (FACP ALPHANUMERIC DISPLAY)

The contractor shall provide Plain-English-language descriptions of alarm, supervisory, and trouble events; and addresses and locations of alarm-initiating or supervisory devices originating the report. Display monitoring actions, system and component status, system commands, programming information, and data from the system's historical memory.

2.4 CENTRAL Fire Alarm Control Panel (FACP)

A. Cabinet: Lockable steel enclosure. Arrange interior components so operations required for testing or for normal maintenance of the system are performed from the front of the enclosure.

Sumas Land Port of Entry/Fire Suppression System Replacement D/B SOW Page 9

If more than one unit is required to form a complete control panel, fabricate with matching modular unit enclosure to accommodate components and to allow ample gutter space for field wiring and interconnecting panels.

1. Identify each enclosure with an engraved, red, and laminated, phenolic-resin nameplate with white lettering not less than 1 inch (25 mm) high. Identify individual components and modules within cabinets with permanent labels.

2. Mounting: Surface, using screws. The use of adhesive materials is unacceptable.

B. Alarm and Supervisory Systems: Separate and independent in the FACP. Alarm-initiating zone boards consist of plug-in cards. Construction requiring removal of field wiring for module replacement is unacceptable.

C. Control Modules: Include types and capacities required to perform all functions of fire alarm systems.

D. Indications: Local, visible, and audible signals announce alarm, supervisory, and trouble conditions. Each type of audible alarm has a different sound.

E. Resetting Controls: Prevent the resetting of alarm, supervisory, or trouble signals while the alarm or trouble condition still exists.

F. Alphanumeric Display and System Controls: Arranged for interface between human operator at the FACP and addressable system components, including annunciation, supervision, and control.

1. Display: A minimum of 80 characters; alarm, supervisory, and component status messages; and indicate control commands to be entered into the system for control of smoke detector sensitivity and other parameters.

2. Keypad: Arranged to permit entry and execution of programming, display, and control commands.

2.5 SUBORDINATE CONTROL PANELS

A. Provide microprocessor-based subordinate control panels, located in Life Safety Closets on appropriate floors. To provide direct interface, supervision, and termination points for initiating and indicating circuits, control circuits and digital communications with the Main Control Panel.

B. In the event of communications loss with the FACP, the subordinate control panel must be capable of reacting to all its connected input devices and applying its own stand-alone local mode programming instruction to determine the status of all its connected outputs.

C. Provide sufficient cabinet space, power supply capacity, etc., to provide for the ability to increase the number of field devices and zone circuits by at least 25 percent.

D. Provide sufficient strobe outputs to provide 25 percent spare capacity, based on the rated current of the strobes.

E. Each subordinate control panel shall be provided with maintenance free battery backup system sized for the hours specified herein; 24 hours plus 15 minutes of alarm operation.

2.6 TRANSIENT PROTECTION DEVICES

A. All control equipment shall have transient protection devices to comply with UL 864 requirements:

Sumas Land Port of Entry/Fire Suppression System Replacement D/B SOW Page 10

1. Provide an Isolated Loop Circuit Protector (ILCP) device on all fire alarm initiating circuits, alarm indicating appliance circuits, signaling line circuits which extend beyond the main building by either aerial, underground or other methods, walkways, bridges or other above ground connectors.

2. The ILCP shall be located as close as practicable to the point at which the circuits leave or enter the building.

3. The ILCP grounding conductor is to be a No. 12 AWG wire having a maximum length of 28 feet to be run in as straight a line as practicable and connected to a building ground electrode system (unified ground) per Article 800 of the National Electrical Code.

4. The ILCP is to have a line to line response time of less than one (1) nanosecond capable of accepting greater than 2000 amps (9joules each line) to earth. Shield to earth current is to be 5000 amps maximum.

5. The ILCP shall be protected by a high dielectric insulating material and of small enough size to mount in a standard 4" square 2 -1/8" deep electrical box.

6. Spark gap devices or devices incorporated in or installed within the fire alarm control panel in lieu of the specified ILCP are not acceptable.

7. All ILCP's shall comply with UL 497B requirements.

2.7 SECONDARY POWER SUPPLY

A. General: Components include gel cell sealed battery, charger, and an automatic transfer switch and will be located in areas where environmental conditions meet battery manufacturers requirements without the need for supplemental cooling/heating.

1. Battery Nominal Life Expectancy: 5 years, minimum.

B. Battery Capacity: Comply with NFPA 72.

C. Battery Charger: Solid-state, fully automatic, variable-charging-rate type. Provide capacity for 150 percent of the connected system load while maintaining batteries at full charge. If batteries are fully discharged, the charger recharges them completely within four hours. Charger output is supervised as part of system power supply supervision.

D. Integral Automatic Transfer Switch: Transfers the load to the battery without loss of signals or status indications when normal power fails.

2.8 MANUAL PULL STATIONS

Description: Fabricated of metal or plastic, and finished in red with molded, raised-letter operating instructions of contrasting color.

1. Double-action mechanism requiring two actions, such as a push and a pull, to initiate an alarm.

2. Station Reset: Key or wrench operated, rated for the voltage and current at which it operates.

3. Integral Addressable Module: Arranged to communicate manual-station status (normal, alarm, or trouble) to the FACP.

2.9 SMOKE DETECTORS

A. General: Include the following features:

1. Operating Voltage: 24-V dc, nominal.

2. Self-Restoring: Detectors shall not require resetting or readjustment after actuation to restore them to normal operation, except resetting the control panel.

Sumas Land Port of Entry/Fire Suppression System Replacement D/B SOW Page 11

3. Plug-in Arrangement: Detector and associated electronic components are mounted in a module that connects in a tamper-resistant manner to a fixed base with a twist-locking plug connection. Terminals in the fixed base accept building wiring.

4. Integral Visual-Indicating Light: LED type to indicate when detector has operated.

5. Sensitivity: Can be tested and adjusted in-place after installation.

6. Integral Addressable Module: Arranged to communicate detector status (normal, alarm, or trouble) to the FACP.

7. Remote Controllability: Unless otherwise indicated, detectors are analog-addressable type, individually monitored at the FACP for calibration, sensitivity, and alarm condition, and individually adjustable for sensitivity from the FACP.

B. Photoelectric Smoke Detectors: Include the following features:

1. Sensor: LED or infrared light source with matching silicon-cell receiver.

2. Detector Sensitivity: Between 2.5 and 3.5 percent/foot (0.008 and 0.011 percent/mm) smoke obscuration when tested according to UL 268A.

C. Ionization Detector: Include the following features:

1. Responsive to both visible and invisible products of combustion.

2. Self-compensating for changes in environmental conditions.

D. Duct Smoke Detector: Photoelectric type.

1. Sampling Tube: Design and dimensions as recommended by the manufacturer for the specific duct size, air velocity, and installation conditions where applied.

2. Relay Fan Shutdown: Rated to interrupt fan motor-control circuit. Provide two sets of auxiliary control contacts, one set for the fan shutdown, and one set for interface to the automatic temperature control system/smoke management system control panel.

3. All duct detectors shall be provided with remote test switch with keyed access.

2.10 OTHER DETECTORS

A. Heat Detector, Combination Type: Actuated by either a fixed temperature of 135 deg F (57 deg C) or rate of rise of temperature that exceeds 15 deg F (8.3 deg C) per minute, unless otherwise indicated.

1. Mounting: Plug-in base, interchangeable with smoke detector bases.

2. Integral Addressable Module: Arranged to communicate detector status (normal, alarm, or trouble) to the FACP.

B. Heat Detector, Fixed-Temperature Type: Actuated by temperature that exceeds a fixed temperature of 190 deg F (88 deg C).

1. Mounting: Plug-in base, interchangeable with smoke detector bases.

2. Integral Addressable Module: Arranged to communicate detector status (normal, alarm, or trouble) to the FACP.

2.11 NOTIFICATION APPLIANCES

A. Description: Equip for mounting as indicated and have screw terminals for system connections.

1. Combination Devices: Factory-integrated audible and visible devices in a single-mounting assembly and enclosure.

B. Visible Alarm Devices: Xenon strobe lights listed under UL 1971 with clear lens. The word "FIRE" is engraved in minimum 1-inch- (25-mm-) high letters. Flash rate shall not exceed two flashes per second nor be less than one flash per second. Maximum pulse duration shall be 0.2 seconds with a maximum duty cycle of 40 percent. Shall be suitable for installation in a single

Sumas Land Port of Entry/Fire Suppression System Replacement D/B SOW Page 12 gang outlet box. Color of housing shall be white in finished areas such as offices and corridors, red housing in unfinished areas such as garage and mechanical areas. Synchronized strobe lights shall remain synchronized through-out the device's listed voltage range.

1. Strobe Leads: Factory connected to screw terminals.

2. Combination visual/audible notification devices allowed only when shown.

2.12 REMOTE DEVICE LOCATION-INDICATING LIGHTS AND IDENTIFICATION PLATES

Description: LED indicating light near each smoke detector that may not be readily visible.

Light is connected to flash when the associated device is in an alarm or trouble mode. The lamp is flush mounted in a single gang plate. A red, laminated, phenol-resin identification plate at the indicating light identifies, in engraved white letters, device initiating the signal and room where the smoke detector is located.

2.13 MONITOR MODULE

Description: Microelectronic monitor module listed for use in providing a multiplex system address for listed fire and sprinkler alarm-initiating devices with normally open contacts.

2.14 CONTROL RELAY MODULE

Description: Microelectronic control module listed for use in controlling smoke/fire dampers, door release service.

2.15 FIRE ALARM TERMINAL CABINETS

NEMA Type 1 enclosure, hinged door front with flush hinge and latch. Latch shall have lock.

Provide terminal blocks in all cabinets with 25% spare capacity. Box and front shall be steel, painted red with label "Fire Alarm". Flush mounted.

2.16 GUARDS FOR PHYSICAL PROTECTION

Description: Welded wire mesh of size and shape for the fire alarm manual pull station, smoke detector, gong, or any other device requiring protection as determined by GSA.

1. Factory fabricated and furnished by the manufacturer of the device.

2. Finish: Paint of color to match the protected device.

2.17 TESTING

A. Constructor shall be responsible for all quality control related to all phases of project.

Contractor will provide quality control plan to GSA for review before any design or on-site work begins. Any and all work deemed unsatisfactory by GSA and/or AHJ shall be replaced or repaired at the discretion of GSA with no additional cost.

B. Manufacturer's Field Service: Engage a factory-authorized service representative to inspect field-assembled components and connections and to supervise pretesting, testing, and adjustment of the system. Report results in writing.

Sumas Land Port of Entry/Fire Suppression System Replacement D/B SOW Page 13

C. The completed fire alarm system shall be subjected to two required tests. The initial test shall be a preliminary test which will be witnessed by the GSA Property Manager’s representatives.

Should the results not be satisfactory to the GSA Contracting Officers Representative, then corrections will be made and a re-test will be required at the contractor's expense. A contractor's representative and contractor supplied fire alarm technician shall be present for all tests. The fire alarm technician shall conduct the tests.

D. The preliminary test shall be in accordance with a written Acceptance Test Procedure (ATP) to demonstrate and certify proper system operation. The ATP shall be prepared by the contractor and submitted to GSA for approval six (6) weeks or more prior to the performance of the ATP.

As a minimum, the ATP shall provide a detailed method of testing the following to demonstrate to the GSA that the systems function as intended by the design:

A point-to-point test for each alarm initiating and indicating device and the operation of door holder releasing mechanisms. A test of the batteries shall be completed at the end of the point-to-point test. Interface with smoke control system, Smoke evacuation system, fire pumps and associated ATS(s), and any door locks affected by fire alarm system shall be tested and correct operation confirmed.

E. Upon the successful completion of the preliminary fire alarm system test, the final acceptance test can be arranged. It shall be witnessed by the representative of the GSA Regional Safety and Environmental Section (AHJ). The test shall prove the Class A features of each device, which will include the removal of each alarm initiating device from its mounted position and placing it in an alarm condition, open circuit condition & ground fault condition for both positive and negative sides, alarm condition while in the open circuit condition and alarm condition while in a ground fault condition. The alarm indicating devices shall have the class A features tested, which will include the removal of up to 100% of the devices as chosen by GSA and placing the device in an open circuit condition, ground fault condition for both positive and negative sides and sending an alarm signal while the device is in an open and ground fault condition. Each auxiliary system that is affected by the fire alarm system shall be tested to ensure the proper operation and supervision

F. The following items shall be required beside the requirements as a minimum for the preliminary testing of the system.

1. Perform a mega ohm meter test (or approved equivalent) for each circuit prior to connecting the devices and record the results of the test. A copy of the test shall be forwarded to GSA for their records. Copies of the test documentation tests shall be received by the contracting officer prior to starting the acceptance test.

2. All detectors shall be removed from their mounting boxes. A wire shall be lifted from each detector, one at a time, to verify proper supervision of the devices.

3. Up to 100% of all audible alarm devices shall be removed from their mounting boxes. A wire shall be lifted from each device, one at a time, to verify proper supervision of the devices.

4. All bypass and control switches shall be operated to indicate proper supervision of the switch.

5. All valve and sprinkler supervision switches shall be operated to verify proper response.

6. All valve and supervision switches shall have one wire removed to verify proper supervision.

7. Each alarm output, detection and supervision zone will be tested for proper response to ground conditions.

8. The supervisory transmitter shall be tested for proper operation.

9. All zone annunciator transmitters shall be tested for proper operation.

10. All critical fuses shall be removed to check for proper supervision.

11. All detectors shall be tested for alarm operation.

Sumas Land Port of Entry/Fire Suppression System Replacement D/B SOW Page 14

12. All flashing light units shall be tested for class ‘A” wiring supervision by removing a wire from the device. The device shall also be tested for proper alarm operation.

13. All alarm sounding devices shall be tested for proper operation.

14. Audibility tests shall be conducted to determine compliance with the audibility requirements of this specification. A copy of the space layout drawings for each level of the building shall be used to record the audible levels through-out the building. The audible test shall be done using a sound level meter and performed in the presence of the GSA Construction Management Team. The results shall be forwarded to the GSA Regional Fire Protection Engineer for review to determine if any additional speakers are required prior to the beginning of the final acceptance test.

15. Test each initiating and indicating device and circuit for proper operation and response at the control unit.

16. Test the system for all specified functions in accordance with the contract drawings and specifications and the manufacturer's operating and maintenance manual.

17. Test both primary power and secondary power. Verify, by test, the secondary power system is capable of operating the system for the time period and in the manner specified.

18. Determine that the system is operable under the trouble conditions as specified.

19. Visually inspect all wiring.

20. Verify that all software control and data files have been entered or programmed into the

FACP. Hard copy records of the software shall be provided to the contracting officer.

21. Verify that as-built drawings are accurate.

22. Measure the current in circuits to assure there is 25% spare capacity for the circuits.

23. Measure the current in circuits to assure that voltage drop is not excessive.

24. Disconnect the verification feature for smoke detectors during testis to minimize the amount of smoke or test gas needed to activate the detector.

G. The requirements for final testing shall be as requested by GSA via Contracting officer and GSA Fire protection engineer (Authority Having Jurisdiction) AHJ. Should the results not be satisfactory to the GSA Contracting Officer's Representative, then corrections will be made and a re-test will be required at the contractor's expense to include all costs for GSA AHJ.

H. In addition to all aforementioned testing, there will be a requirement for a 10% test of the entire fire alarm system at 24months after original acceptance by GSA. The same testing process as previously mentioned in this section will apply.

2.18 CONSTRUCTION PERIOD OF PERFORMANCE

Period of performance will be 205 calendar days after construction NTP.

2.19 CLEANING PAINTING and REMOVAL

Cleaning: Remove paint splatters and other spots, dirt, and debris. All debris must be cleaned up daily to ensure occupied spaces are ready for tenant occupancy. Touch up scratches, penetrations and marred finish to match original finish. Patch and paint to logical breaks TBD by GSA project manager. All damage to existing finishes will be repaired before project is accepted. Any broken ceiling tile will be replaced to match existing. All accessible conduit, abandoned wires and accessible boxes will be removed.

2.20 TRAINING

The contractor, within two weeks after final acceptance test and system has been accepted by

Sumas Land Port of Entry/Fire Suppression System Replacement D/B SOW Page 15

GSA shall conduct a training session during which all maintenance and operational of the systems will be described and demonstrated to personnel selected by the government. The time of the sessions shall be agreed upon by all parties and shall be conducted by the manufacturer's representative that is thoroughly familiar with the characteristics of the installed system, preferably the individual who accomplishes original system programming. Notification of this training session shall be given to the Contracting Officer's Representative. The contractor shall provide up to 8 hours of training. Contractor shall video tape training session and provided to GSA for future training and reference.

2.21 LAYDOWN AREA

Laydown area will be provided on site and will be determined by the Facility Manager and the client.

2.24 WARRANTY

All Materials and labor will be warranted for a one year period (12 months) following acceptance by GSA. At the end of the 12 month, a re-test of at least 10% of the system shall not be required to be conducted. Contractor will be held financially responsible for correction/replacement of failed components and all other costs associated with any retests should any be deemed necessary by GSA within the time of the warranty.

2.25 CLOSEOUT

A. Final Record Documents The DB-Contractor shall update the construction drawings (record-drawings) and specifications (record-specifications) to document all changes that occur, or unforeseen conditions impacting delivered work during construction. The DB-Contractor shall produce final record documents, based on as-built drawings and specifications, to reflect all contract modifications and noted field conditions. The DB-Contractor shall update the CAD drawings (record-drawings) and electronic specifications (record-specifications) to formally incorporate all cumulative approved changes (omit deltas and clouds). Documents will be provided in both native software and PDF versions.

Provide 2 hard copy sets of as-built plans (1 full-size, 1-half size) along with submittals and specifications to be incorporated into the O&M Binders in addition to the electronic copies at project completion.

B. Final Project Photographs The DB-Contractor shall provide digital images of up to 50 color photographs depicting the completed project. Each image must be tagged with the project name and the specific view, with city and state in which it is located. Captions and photo credits must also be keyed to each image. The DB-Contractor shall provide a compact disk (CD) containing digital images of all photographs in a JPG format, with a minimum resolution of 1024x768 pixels. All pictures will be labels in the file name with a specific description of the image.

C. Contract Closeout The DB-Contractor shall:

Resolve all remaining punch-list items;

Submit signed release of claims;

Submit warranty documents;

Provide all Spare Components;

Return all Government-issued security credentials; Destroy all reference materials not otherwise required to be retained.

Sumas Land Port of Entry/Fire Suppression System Replacement D/B SOW Page 16

3.1 GOVERNMENT TEAM

A. Contracting Officer (CO) - GSA’s procurement agent directly responsible for the general supervision, direction, control and approval of the Government’s contract with the Contractor.

B. Contracting Officers Representative (COR) - GSA’s representative responsible for administering contracts under the immediate direction of the CO. The COR’s specific duties are listed in the COR Delegation Memorandum.

C. Property Manager - GSA’s representative responsible for maintaining/repairing the facility and addressing the needs of the client agencies housed within the facility.

D. Stake Holder(s) - Additional personnel, who are involved in or may be affected by the project’s activities such as FDA Local and Headquarters. Authority Having Jurisdiction (AHJ) GSA’s representative responsible for fire life safety and the only person who can make decisions or changes regarding the fire life system.

3.1 CONTRACTORS TASKS

A. Site Conditions. Contractor access to the site shall be coordinated with local GSA personnel and l. The Tenant Agency Hours of operation: 6:00 am to 6:00 pm Monday – Friday

B. Coordination. The Contractor shall coordinate all site activities with the GSA Project Manager who will coordinate with the GSA Project Manager and Facility Manager. This will then be coordinated with FDA to ensure access to the building

C. Work Hours. It is anticipated that all work will occur after business hours Monday through Friday 1800 to 0600. Any site access during normal business hours shall be coordinated through the GSA PM and CBP.

3.2 DESIGN REVIEWS

A. Each design phase will have a Government review period of 14 calendar days, during which time the Contractor will not continue development until Government comments are received.

B. Each design phase will have a Government review period of 14 calendar days, during which time the Contractor will not continue development until Government comments are received.

3.3.1.1Milestone design reviews will be electronic reviews, the Contractor will provide PDF versions of the design to the COR for distribution to the Government team. The COR will consolidate written comments from the Government team and provide them back to the Contractor.

C. Concluding each Government review period there will be a conference call meeting with the

Contractor and the Government team to discuss comments and concerns in a workshop format. These meetings will be using teleconference and screen-sharing technology, to be coordinated with the COR. The Contractor will respond to all comments provided by the Government during each meeting, to be added to the overall written Government comments for that phase of the design. Approval of the design phase shall not be considered valid until the design is approved in writing by the Contracting Officer or his/her representative.

D. The Contractor shall formally respond to all written review comments from GSA within one week of receipt. This response, directed to the COR, should indicate agreement/disagreement, and how the concern will be addressed within the next submission or resubmission.

Sumas Land Port of Entry/Fire Suppression System Replacement D/B SOW Page 17

A. Meetings

1. Meetings will be held in the GSA Regional Office Building, or through the use of teleconference and screen-sharing technology as approved by the COR, and the Contractor shall have appropriate representatives attend. The contractor will provide the meeting agenda 3 days prior to the meeting for government review and comment. Meeting notes will be taken by the contractor via format provided by the government. Meeting notes will be provided to the government for review 3 days following scheduled meeting. Government will have 3 days to review and make comments prior to contractor making notes final. These meetings include:

a. Kick-off Meeting/Site Visit

b. 65% Design Review Meeting

c. 95% Design Review Meeting

d. 100% Final Design Review Meeting

2. Periodic progress meetings will be scheduled by the COR, with the interval to be determined by the team based on the needs of the project. Progress meetings will be conducted by telephone.

3. Design Phase Schedule

a. Work Plan / Schedule. The intent of this task is to develop a working schedule for the implementation of this design. The Contractor team shall collaborate to develop a plan and schedule in MS Project Gantt format for the design. This will be used by the project team to track progress as well as scheduling on-site activities, meeting and review participation by Government stakeholders. The Schedule shall be prepared by the Contractor and provided to the COR prior to the Kick-off Meeting.

b. Kick-off Meeting. The intent of this task is to review and confirm the parameters of the Design. To accomplish this task the Contractor shall attend a Kick-off Meeting with the Government Team. The Kick-off Meeting shall address the following but not limited to:

1. Confirm the scope of the design and any other contractual items;

2. Confirm and prioritize the design goals;

3. Discuss how decisions will be made;

4. Identify opportunities and constraints with the existing site, facility and physical infrastructure;

5. Verify and affirm the stakeholders who will be involved in identifying requirements;

6. Schedule the site visit(s); and Identify action items, deadlines, and the responsible parties.

7. Data Collection and Analysis. The intent of this task is to gather, organize, and analyze the data that will be included in the Design. Validate the as -built drawing information only for the portion of the site impacted by this design.

c. 65% Design Review. The contractor shall submit a 65% design to the Government within 28 calendar days after the accepted 35% design. The design review package shall be submitted electronically, via PDF. The government will conduct a written review of the 65% Design and provide those written comments to the contractor within 14 calendar days of receipt. A 65%

Sumas Land Port of Entry/Fire Suppression System Replacement D/B SOW Page 18 design review meeting will be conducted with the contractor and government.