DID Project Schedule CDRL A001.pdf

PDF 231 KB Posted

Attached to
M241 Barge Availability Federal contract opportunity
Solicitation number
N0016723Q0064
Issued by
Department of the Navy Naval Sea Systems Command

About this file

This document contains a Data Item Description and related federal contract opportunity. The Data Item Description provides the format and content requirements for a Project Planning Chart deliverable, including depicting actual and scheduled progress for work breakdown structure subdivisions using symbols and dates. It must include the contractor name, contract title and number, and security classification.

The related federal contract opportunity is a solicitation from the Naval Surface Warfare Center seeking firm-fixed price support services for maintenance and repairs to the M241 Barge research platform. The anticipated period of performance is from May 15th to July 31st, 2023. Interested parties should read the Combined Synopsis and Solicitation attached for full details on response requirements and pricing terms. No site visits will be provided for this opportunity.

View the file

Other files for this federal contract opportunity

Other files attached to M241 Barge Availability, newest first.
File Type Posted
N0016723Q00640001.docx DOCX document
CDRL A002 Digital Imaging.pdf PDF
DID Test Inspection Report.pdf PDF
DID Vessel Docking Plan.pdf PDF
CDRL A004 Test Inspection Reporting.pdf PDF
CDRL A003 Vessel Docking Plan.pdf PDF
CDRL A001 Project Schedule.pdf PDF
DID Digital Imaging CDRL A002.pdf PDF
CDRL A005 GFP Report_signed.pdf PDF
DID GFP Report.pdf PDF
N0016723Q0064 CSS.docx DOCX document
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DATA ITEM DESCRIPTION

Title: Project Planning Chart

Number: DI-MGMT-80507C Approval Date: 14 Apr 2009 AMSC Number: 9061 Limitation: N/A DTIC Applicable: No GIDEP Applicable: No Office of Primary Responsibility: NS/BA02 Applicable Forms: N/A

Use/relationship:

The Project Planning Chart graphically depicts the schedule and actual progress of work on a contract.

This Data Item Description (DID) contains format and content preparation instructions for the data product generated by the specific and discrete task requirement as delineated in the contract.

This DID is used as a attachment to a status or progress report to illustrate the amount of work accomplished relative to the work schedule.

For fixed prices contracts, tailor out 3.18 and 3.19.

This DID supersede DI-MGMT-80507B

Requirements:

1. Reference documents. None.

2. Format: The chart shall be in contractor’s format.

3. Content.

3.1 Project planning chart. It shall depict actual and schedules progress for each subdivision using horizontal lines and symbols. Actual progress will be noted by a percentage of the completion figure.

3.2 Progress of work. Subsequent additions to the work breakdown shall be made as they occur in contract work performance. Items shall not be deleted even though work may be cancelled or stopped before completion.

3.3 Description. Description entry on the chart will be by task. Tasks are divided into

DI-MGMT-80507C

subdivisions. For computer software task, the subdivisions shall be Design, Coding, Debugging, Acceptance Testing, and Management. Entries shall be complete and reflect all contract effort.

3.4 Milestone symbol. The triangle symbol will be white if the task has not be achieved. It shall be shaded if the task has been achieved.

3.5 Date released. Last date to which chart was posted.

3.6 Date revised. Date of subsequent contract modification.

3.7 Contractor name.

3.8 Contract title.

3.9 Contract number.

3.10 Purchase description number.

3.11 Security classification.

3.12 Delivery dates. Includes dates for all deliverable items.

3.13 Scheduled starting date. Date each subdivision of work is scheduled to start.

3.14 Actual starting date. Date each subdivision of work actually started.

3.15 Scheduled completion date. Date each subdivision of work is scheduled for completion.

3.16 Actual completion date. Date each subdivision of work actually was completed.

3.17 Manhours Expended. Total manhours expended per task for each reporting period.

Manhours defined as total number of direct labor hours regardless of type.

3.18 Funds expended. Contracts funds expended per task for each reporting period.

Costs defined as total direct cost plus burden, overhead, general and administrative

(G&A), and any other load. Total of all items to equal the total target cost.

DI-MGMT-80507C

3.19 Expenditures. Manhours expended figures and contract funds expended figures used on the chart will be developed on the same basis as the planned figures. Chart depicts these figures for each report period as cumulative totals, accurate to the as-of-date of the report.

4. END OF DI-MGMT-80507C