Determination_to_solicit_from_a_single_source.pdf
PDF 340 KB Posted
- Attached to
- HARDBOOK SOFTPLC CONTROLLER Federal contract opportunity
- Solicitation number
- 140R1724Q0019
About this file
This document is a determination to solicit from a single source for a federal contract opportunity with the Department of the Interior Bureau of Reclamation. The Bureau requires a Hardbook SoftPLC controller to replace failing end-of-life controllers used in its Grand Coulee Power Office for communication and control between hydroelectric generation equipment and the Bonneville Power Administration. The SoftPLC hardware has been implemented for 13 years and its programming cannot be easily ported to a different PLC without significant time and cost. Using any other device would require substantial cost and effort to develop new tools and programming, estimated at $150,000, and impact system maintenance and downtime. While this will be a brand name single source solicitation, market research found multiple distributors can provide competitive quotes for the specified SoftPLC brand. The solicitation is for a firm fixed price order with anticipated delivery in 6-8 weeks.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140R1724Q0019_Amd_0001.pdf | ||
| Revised_Clauses_and_Provisions_0001.docx | DOCX document | |
| Sol_140R1724Q0019.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
140R1724Q0019 Page 1 of 2
WBR 1413.106-1 Template 1 (11/2020)
DETERMINATION TO SOLICIT FROM A SINGLE SOURCE
Pursuant to Federal Acquisition Regulation (FAR) 13.106-1(b)(1)(i), for purchases not exceeding the Simplified Acquisition Threshold (SAT) Contracting Officers may solicit from only one source if the circumstances of the contract action deem only one source is reasonably available (e.g., urgency, exclusive licensing agreements, brand name, or industrial mobilization).
Pursuant to FAR 13.106-1(b)(1)(ii), when a single source is identified to provide a portion of the purchase as a Brand-Name, the documentation in paragraph 3 must state that this determination is only for a portion of the requirement.
1. Agency and Contracting Activity.
U.S. Department of the Interior Bureau of Reclamation C-PN, Team 2 Supply-Service
2. Name and Address of Single Source.
SoftPLC Corporation 25603 Red Brangus Drive Spicewood TX 78669
3. Description of Supplies/Services and Estimated Cost.
The Bureau of Reclamation, Grand Coulee Power Office has a requirement for a Hardbook SoftPLC (Programable Logic Controller). This item is required for the Industrial Control Group and will be utilized for the Generic Data Acquisition and Control System (GDACS) and Supervisory Control and Data Acquisition System (SCADA) used for communication and control between the hydroelectric generation equipment and the Transmission Authority (Bonneville Power Administration) for reliability and stability of the regional power grid. The resultant purchase order will be firm fixed price with a delivery schedule of 6-8 weeks ARO and an estimated value of
Item: Model HB2-HDC2-NK-ASSY: Hardbook SoftPLC Model HB2-HPQA USACE Assembly, No RT License
4. Description of Circumstances, including why only one source is reasonably available.
The SoftPLC Hardbook is part of an existing overall larger system and is the only approved device for providing its functionality within the system. The GDACS control programming is developed exclusively on the SoftPLC platform and cannot be easily ported to a different PLC without significant time and monetary expense. The SoftPLC hardware has been implemented at Reclamation for the past 13 years and this requirement is for new controllers to replace failing end-of-life controllers. This hardware is part of a large critical integrated SCADA system and is the only system approved and supported by the US Army Core of Engineers (USACE) via an interagency agreement between the Bureau of Reclamation and USACE to serve its function within the SCADA system. Maintenance and development on this SCADA system uses a set of tools and programming that are set up to work with the SoftPLC Hardbook. Using any device other than the SoftPLC Hardbook would require a substantial cost and effort to develop new tools and programming to work with the new device. Estimated costs, outside of the equipment costs, are approximately $150,000 for this effort and that does not take into account the time lost in the
140R1724Q0019 Page 2 of 2
WBR 1413.106-1 Template 1 (11/2020) development of these new tools and software. A different piece of equipment would also require additional training and associated costs for maintenance and development personnel, time and costs in updating documentation, and time and costs associated with system downtime to convert to the new equipment. We would also lose our support on this piece of equipment within the overall SCADA system as any other controller would not be supported or approved by USACE.
These additional costs both monetary and time would create an undue burden on the government.
5. Determination of Fair and Reasonable Price.
In accordance with FAR part 13.106-3(a)(1), fair and reasonable cost will be determined through competitive quotes received in response to a solicitation issued for the brand name products specified.
6. Description of Market Research.
Market research was conducted and it was found that there were different brands of controllers but none of the sources found, other than the SoftPLC brand can be utilized. Although this will be a brand name single source requirement, market research has shown that there are several distributors that can provide a competitive quote.
SIGNATURES
PREPARED BY:
CONTRACTING OFFICER (CO) (FAR 13.106-1(b)):(All Values)
X Donald Richer Contract Specialist
X Jeri Wahl Contracting Officer
| 2024-02-14T15:13:56-0800 | |
| DONALD RICHER |
| 2024-02-15T06:39:47-0800 | |
| JERI WAHL |