Attach_A_PWS.pdf

PDF 5 MB Posted

Attached to
Microwave Tower Inspection and Maintenance Services Federal contract opportunity
Solicitation number
DE-SOL-0005897
Issued by
Department of Energy Western Area Power Administration

About this file

Attachment A Performance Work Statement

View the file

Other files for this federal contract opportunity

Other files attached to Microwave Tower Inspection and Maintenance Services, newest first.
File Type Posted
Amendment_000001.pdf PDF
Cover_Letter.pdf PDF
Attach_B_Location_Maps.pdf PDF
Attach_E_Past_Performance.docx DOCX document
Attach_D_W3000-72.doc DOC document
DE-SOL-0005897.pdf PDF
Attach_C_Wage_Determinations.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT A

DE-SOL-0005897

Performance Work Statement

U.S. DEPARTMENT OF ENERGY

WESTERN AREA POWER ADMINISTRATION

PERFORMANCE WORK STATEMENT

MICROWAVE TOWER INSPECTION & MAINTENANCE SERVICES

1. GENERAL

1.1. Scope of Work

The Western Area Power Administration (Western) requires a contractor to perform comprehensive inspection and maintenance services on guyed and self-supported microwave towers at various locations throughout its territory. The work will be performed predominantly for the Rocky Mountain Region (RMR) and the Upper Great Plains Region (UGPR) in the following states: Colorado, Wyoming, Utah, Nebraska, New Mexico, Montana, North Dakota, South Dakota, Minnesota, and Iowa. Work may also be performed for other Western’s Desert Southwest Region (DSWR) and Sierra Nevada Region (SNR) in the following states:

Arizona, Nevada and California.

A five (5) year interval for performing microwave tower inspections has been established for the RMR and UGPR. Attached to this Performance Work Statement (PWS) is a spreadsheet (Exhibit 3) listing the year each tower is to be inspected, the name of the site, the Facility Identification Code (FID), the height of the structure, and the type of structure.

At least one Task Order will be issued each contract year, including the option years if exercised. These Task Orders will include the specific towers identified for inspection that year (Exhibit 3). Tower inspections should normally be completed between May and September of each year to guarantee access to each site.

Inspections may be allowed outside of this window, at the discretion of the Contracting Officer.

If additional towers are identified for inspection, or non-routine maintenance is identified and required to be performed, additional Task Orders will be issued as required.

1.2. Background

Western, part of the U.S. Department of Energy (DOE), is a Federal power marketing administration that markets and delivers reliable, cost-based hydroelectric power and related services within a 15-state region.

The RMR serves preference customers in Colorado, Wyoming, Nebraska and Kansas. RMR also services the Colorado River Storage Project Management Center (CRSP-MC) in Salt Lake City, Utah. The CRSP-MC provides transmission services to facilities in Arizona, New Mexico, Colorado, Utah, Texas and Wyoming.

RMR’s mission includes maintenance and operation of the high-voltage transmission system including 80 substations and over 5,400 miles of high-voltage power transmission lines that deliver power from CRSP-MC and over 19 power plants to its wholesale customers. The UGPR serves preference customers in Iowa, Minnesota, Montana, Nebraska, North Dakota, and South Dakota. UGPR’s mission includes maintenance and operation of the high-voltage transmission system including nearly 100 substations and 7,800 miles of high-voltage power transmission lines

1.3. Location

The work is located at various communication sites throughout Western, some of which are inside energized high voltage electrical substations. States in which the sites are located include, but are not limited to the following: Arizona, California, Colorado, Iowa, Minnesota, Montana, Nebraska, Nevada, New Mexico, North Dakota, South Dakota, Utah, and Wyoming

1.4. Government Personnel

1.4.1. The Contracting Officer is the individual executing this contract on behalf of the Government and is responsible for the overall administration of the contract. He/she is the only person authorized to make any changes in the prices, terms or other conditions of the contract.

1.4.2. The Contracting Officer’s Representative (COR) is responsible for giving the Contractor any special technical instructions or guidance necessary to ensure contract execution. The COR has no authority to alter the terms of conditions of the contract.

1.5. Contractor Personnel

1.5.1. The contractor shall furnish adequate supervision at the premises to ensure that work is performed in a satisfactory manner. It is the responsibility of the contractor to maintain close surveillance over personnel employed to perform work on the contract.

1.5.2. The contractor shall have a competent on-site representative authorized to act on behalf of the contractor, available to the CO or COR to receive instructions or information regarding work under the contract. The on-site representative must be able to fluently speak and understand English.

1.5.3. No unauthorized personnel are permitted on the premises.

1.6. Hours of Work

Normal work hours for Maintenance personnel are from 7:00 a.m. to 5:30 p.m. daily, Monday through Thursday. Maintenance personnel from each Region will escort Contractor at each site of inspection, so the normal work hours shall be taken into consideration in developing the inspection schedule (See paragraph

1.7.3. below). Differing from this schedule may be authorized on a case-by-case basis with the COR’s and CO’s prior approval.

1.7. Submittals.

1.7.1. Safety and Health Program. Contractor shall submit an electronic copy of its Safety and Health

Program to the CO and COR no later than 10 calendar days after contract award. Inspection services shall not begin until approval of the Safety and Health Program. Approval of the Safety and Health Program, including amendments and supplements thereto, is for the purpose of determining compliance with this Work Statement only, and shall not relieve the Contractor of the responsibility for the safety and health of persons and property. Safety and Health Program shall include, but is not limited to:

1.7.1.1. Designation of the on-site superintendent to carry out the safety and health program.

Include superintendent’s resume of qualifications and experience in the type of work to be performed and all safety and hazard recognition training.

1.7.1.2. Statement of company safety and health policy encompassing compliance with applicable Federal, State and local safety standards and the safety and health requirements of these specifications.

1.7.1.3. Provision for RF Exposure Policy and Employee Training.

1.7.1.4. Provision for first aid and medical care of injured employees as required by OSHA

1926.50, “Medical Services and First Aid.”

1.7.1.5. Provision for instruction of employees in the recognition and avoidance of unsafe conditions using methods such as new employee orientation and daily “tool box” meetings.

1.7.1.6. Procedures that will be implemented to protect employees against high wind conditions and lightning storms.

1.7.1.7. Fire protection procedures and facilities, including requirements in OSHA 1926, Subpart F, “Fire Protection and Prevention.”

1.7.1.8. Health and sanitation facilities, including requirements in OSHA 1926.51, “Sanitation.”

1.7.1.9. Procedures for specific sequences of work to ensure adequate analysis of hazards and provision of protective measures (e.g., working adjacent to energized electrical equipment, minimum approach distances for non-electrical workers, etc.).

1.7.1.10. Provisions for the use and furnishing of personal protective equipment as required by

OSHA.

1.7.1.11. A copy of the Company’s “Fall Protection” program, as well as a complete listing of Certified Company Climbers and training method for certification.

1.7.1.12. Procedures for protecting the public.

1.7.1.13. Company policy and procedures for enforcing safety and health regulations.

1.7.1.14. Copy of the current certificate of compliance with industrial compensation insurance statutes.

1.7.1.15. A comprehensive inspection program for inspecting tools, equipment, and facilities.

1.7.1.16. Industrial hygiene program that provides occupational health and environmental controls as required by OSHA 1926, Subpart D, “Occupational Health and Environmental Controls.”

1.7.2. List of Employees. Contractor shall furnish a list of all employee names/personnel performing work on this contract to the CO and COR no later than 10 calendar days after contract award. The list shall include the Contractor’s confirmation that all proposed employees are U.S. citizens. Any Foreign Nationals proposed to work at Western sites, must complete Attachment D to the contract and submit to the Contracting Officer, at least 30 days prior to starting work. All Foreign Nationals must be approved by the Government, prior to starting work. No unidentified or unauthorized personnel shall be allowed or permitted on the work site.

1.7.3. Inspection Schedule. Contract shall submit a proposed inspection schedule to the CO and COR no later than 10 business days after award of each Task Order. Western’s approval of the work schedule is required prior to the commencement of work.

1.7.4. Inspection Reports. An electronic copy of the inspection report only (PDF file format, no photographs) shall be e-mailed to the applicable point of contact for each tower, as well as the CO at the e-mail address indicated in Exhibit 5. Contractor shall also furnish completed inspection report (PDF file format) with photos (JPEG file format), and a completed Tower Inventory Form (Exhibit 4) for each tower, within 30 business days of inspection on Computer Disc (CD). The disc should be mailed to the applicable point of contact at the address listed in Exhibit 5.

1.8. Pre Performance Meeting

The CO will schedule a meeting with the contractor within 30 days following contract award to discuss the requirements of the contract and other administrative matters.

1.9. Quality Control and Quality Assurance

1.9.1. The Contractor is responsible for quality control and shall utilize its own internal quality control processes in the performance of this contract. The contractor shall develop and maintain a Quality Control Plan (QCP) to ensure all services are performed in accordance with the Government’s performance standards outlined in the Performance Requirements Summary (PRS) section of this

PWS.

1.9.2. Performance Standards. See Exhibit 1. The PRS is a listing of significant performance objectives with associated performance standards that will be monitored and inspected by Government personnel. Each performance objective represents a critical function as identified by the Government at the time of contract award. The performance standard represents the minimum acceptable level of Contractor performance. The performance objectives and standards represent only the critical components of this Contract, and do not excuse the Contractor from performance of other responsibilities identified in the PWS. All services described in this PWS are subject to inspection/surveillance by the Government.

1.9.3. Government Surveillance of Contractor Performance. In order to supplement the Contractor’s QCP, Western Inspectors, Foreman, Regional Points of Contact, and/or the Contracting Officer will monitor the Contractor’s performance to verify compliance with essential performance requirements.

1.9.4. Contract Discrepancy Report (CDR). A CDR (PWS Exhibit 2) will be initiated by the CO or COR if, at any time during the performance, the results of Western’s surveillance show the number of observations of unacceptable performance during the period exceeds the threshold specified in the PRS, and the CO/COR determines that the unacceptable performance was not caused by the Government. Instructions for completing the CDR are as follows:

1.9.4.1. The COR completes Blocks l through 6 and sends the form to the CO. Block 6 must include the PRS number corresponding to the discrepancy, the threshold of that PRS item, the number of discrepancies documented, and the PWS paragraph reference describing the Government’s expectations for that PRS item.

1.9.4.2. The CO evaluates the CDR, and if appropriate, signs it and sends it to the Contractor with a cover letter requesting a response within a specified number of days.

1.9.4.3. The Contractor must complete Blocks 7 through 10 and return the CDR to the CO within the specified time period on the cover letter.

1.9.4.4. Upon receipt of the Contractor’s response, the CO, in consultation with the COR, will evaluate the Contractor’s response and take appropriate action. The CO will document the evaluation in Block 11 and action taken in Block 12.

1.9.4.5. In most cases, the preferred action is re-performance by the Contractor at no additional cost to the Government. If deduction from payment is the appropriate action, the COR and CO will calculate the payment deduction based on the performance period in which the discrepancy occurred. The deduction is taken from the Contractor’s payment as close as possible to the month in which the discrepancy occurred, but not necessarily the same month.

The Government should not withhold payment of an invoice while calculating the deduction.

1.9.4.6. The COR will complete Blocks 13a and 13b. The CO signs the CDR in Block 13c. These signatures indicate concurrence with the actions taken.

1.9.4.7. In the event the CO determines that issuance of a CDR is not appropriate; the CO shall document the contract file indicating why such action is not appropriate.

1.10. Compliance with Regulations

In performing the work required by this Contract, the Contractor shall comply with all applicable Federal, State and local laws and regulations.

1.11. Licenses and Permits

The Contractor shall obtain and maintain, at its sole expense, all necessary licenses and permits required to meet the requirements of the contract.

1.12. Materials, Equipment and Storage

1.12.1. The Contractor shall furnish all materials and supplies required for the performance of work under this contract.

1.12.2. The contractor shall determine and furnish all equipment required for the performance of the work under this contract. All equipment shall comply with applicable OSHA guidelines, and shall be in good operating condition. The Contractor shall operate the equipment in accordance with the original manufacturer’s recommendation and applicable laws and regulations

1.12.3. The contractor shall provide off-site storage space for its materials and equipment. Materials and equipment shall not be stored on Western property.

1.13. Interference with Business

The Government may undertake or award other contracts for additional work, and the Contractor shall fully cooperate with such other contractors and Government employees and carefully schedule its own work to such additional work as may be directed by the COR. The Contractor shall not commit or permit any act that will interfere with the performance of work by any other contractor or by Government employees.

The services under this contract shall be performed in such a way that there will be no interruption to or interference with the normal operation of Government business on the premises. Persons employed by the contractor shall, while on the premises, comply with all applicable regulations.

1.14. Government Furnished Property, Equipment, Materials and Utilities

1.14.1. The Government will not furnish any property, equipment or materials for use under this contract.

1.14.2. Electrical power is available for contractor use at most sites; however, if contractor requires electrical power, contractor shall furnish and provide power for those sites without electrical power.

1.14.3. Contractor shall provide water for its use as necessary at each of the sites.

1.15. Security of Facilities

Security of Government facilities is a shared responsibility of all employees, both Federal and contractor.

1.15.1. Contractor personnel shall not prop open doors, and when entering or leaving the complex shall ensure that doors and gates are secure. Contract staff shall notify the COR if they are unable to secure a door or gate.

1.15.2. Contractor personnel shall not allow any person to enter Western property without proper clearance from the RMR Security Office.

1.15.3. The Government may require immediate removal of the employee from the contract and the job site for conduct issues deemed by the Government to be serious (for example, violent behavior or comments, theft, misuse of Government equipment, unsafe work practices, fraudulent activity, etc.).

1.16. Safety and Reporting Requirements

1.16.1. The Contractor shall take all reasonable precautions in the performance of the work under this contract to protect the safety and health of employees and members of the public. The Contractor shall comply with the latest effective standards promulgated by the Department of Labor, Occupational Safety and Health Administration, Safety and Health Standards, 29 CFR 1904, 29 CFR 1910 and 29 CFR 1925. Contractor shall keep a copy of these OSHA standards at the jobsite.

Certain standards have been referenced for emphasis. All OSHA standards shall apply, whether referenced or not. If there is a conflict between the requirements of this PWS and applicable Federal, State, or local safety, health, or industrial regulations or code, the more stringent requirements shall prevail.

1.16.2. Failure to implement, monitor, and enforce the safety and health program submitted to and approved by Western as well as the requirements of this PWS may result in the Contracting Officer’s direct removal of the job superintendent or may result in the suspension of all or part of the work. Western’s failure to order discontinuance of the Contractor’s operations shall not relieve the Contractor of responsibility for the safety and health of personnel and property.

1.16.3. Contractor shall be responsible for determining the integrity of the structure and use all reasonable means to ensure the safety of workers before climbing begins. It will be the contractor’s responsibility to assess the safety of the structure prior to and while the inspection is undertaken. A Western representative will be on-site to observe safety procedures and is authorized to stop work if safe practices are not being used. The failure of the Western Representative to spot an unsafe condition shall not incur liability to Western or to the United States Government.

1.16.4. The Contractor shall maintain an accurate record of, and report work-related fatalities, injuries and illnesses in accordance with the requirements of 29 CFR 1904.

1.16.5. Contractor shall immediately report (verbally) to the CO and COR, all cases of death, occupational disease, or traumatic injury to employees or the public, and any property damage as a result of performance under this contract. Written reports are required within 48 hours in the form and manner prescribed by 29 CFR 1904.

1.16.6. Contractor shall report worksite equipment and motor vehicle accidents, regardless of extent of injury or cost, to the CO and COR.

1.16.7. Contractor shall report property damage or loss in excess of $1,000 resulting from any accident to the CO and COR. Damage to Government or public property, regardless of cost, shall be reported to the CO and COR.

1.16.8. When requested by the Government, Contractor shall participate in any investigation of accidents or incidents.

1.16.9. The Contractor shall ensure that its employees have been appropriately instructed and trained in the proper use of any equipment, vehicles, and/or personal protective equipment and where required, have the necessary exams, certification, skills and knowledge necessary to safely perform their assigned duties.

1.16.10. Contractor shall ensure each employee receives initial work site safety orientation and continued safety and health training addressing the hazards associated with the work and the measures necessary to control or eliminate hazards. Employees shall be physically qualified to perform their assigned duties. Employees shall not work while their ability or alertness is impaired because of fatigue, illness, medications, drugs or alcohol, or any other reason that may expose them or others to injury.

1.16.11. The Contractor shall be responsible for identifying and providing its employees the personal protective equipment (PPE) as necessary in accordance with established OSHA and other applicable Federal, State and local regulations.

1.16.12. Equipment utilized under this contract shall be designed, manufactured, maintained, and operated as required by OSHA 29 CFR 1926 and 1910 requirements. All of the manufacturer’s safety restrictions, warning, and advisements shall be adhered to.

1.16.13. Lifting devices utilized under this contract shall be designed and manufactured or fabricated for their intended use and shall conform to applicable ANSI standards and OSHA 29 CFR 1910 requirements. Annual inspection records in accordance with ANSI B30 and ANSI A92.2-79, as applicable, shall be available for COR inspection if requested.

1.17. Environmental Requirements

1.17.1. The Contractor shall comply with all applicable Federal, State, and local environmental laws and regulations, and current Western policies and procedures.

1.17.2. The Contractor shall dispose of or recycle hazardous, universal, and non-hazardous waste material that may be used in the course of this contract in accordance with all applicable Federal, State and local laws, regulations and ordinances and current policies and procedures identified by Western.

Wastes shall be reduced by recycling, reusing, or reprocessing to the maximum extent practicable.

1.17.3. Hazardous, Universal, and Non-Hazardous Wastes. The Contractor shall manage any hazardous, universal, and non-hazardous wastes in accordance with all applicable State, Federal and Local regulations, and existing policies and procedures identified by Western.

1.17.4. Contractor’s Liability for Regulated Material Incidents. The Contractor is solely liable for all expenses related to spills, mishandling, or incidents of regulated material (such as, but not limited to petroleum products and pesticides) attributable to its employees’ actions or the actions of its subcontractors. This includes all response, investigation, cleanup, disposal, permitting, reporting, and requirements from applicable environmental regulation agencies.

1.18. PWS Exhibits

The exhibits listed below are attached to and incorporated into this PWS.

Exhibit 1: Performance Requirements Summary (PRS). The purpose of the PRS is to communicate the Government’s quality expectations and the process to evaluate the Contractor’s performance.

Exhibit 2: Contract Discrepancy Report (CDR).

Exhibit 3: Tower Inspection Listing, by year

Exhibit 4: Tower Inventory Form

Exhibit 5: Submittal Addresses

2. SCOPE OF WORK

Inspection and Routine Maintenance. Contractor shall provide all labor, equipment, material and supervision to perform inspections and routine maintenance in accordance with this PWS, to include but not be limited to inspections of: the tower, guy wires, foundation and anchors, antenna system, electrical, lightning protection systems and grounding. Routine inspection and maintenance to be performed shall be conducted in accordance with paragraphs 2.1 through 2.8 below.

2.1. Foundation and Anchors

2.1.1. Inspect and note condition of concrete bases and anchor concrete.

2.1.2. Inspect and note anchor for erosion and creeping.

2.1.3. Visually inspect and note condition of anchor head welds.

2.1.4. Inspect and note anchor rod head for cracks, splits, bends, twist, or rust.

2.1.5. Excavate to a depth of 1 foot below the surface, inspect, and note anchor rods not embedded in concrete for corrosion.

2.1.6. Inspect anchor fencing for damaged fabric, missing hardware, bent or broken posts, rusting or missing locks or security issues.

2.1.7. Inspect guy anchors for vegetation overgrowth.

2.1.8. Repair damage to galvanized coating on anchors and bolted connectors.

2.2. Tower

2.2.1. Measure and record plumb and twist.

2.2.2. Visually inspect all tower hardware. Replace missing hardware, broken clips, and tighten loose hardware (except antenna or reflector adjustments hardware and feed line hardware in RMR’s WNMO), and check for air leaks. Hardware associated with antenna reflectors and feed lines found loose shall be documented in the inspection report.

2.2.3. Hand-inspect 100% of bolted connections with a wrench, tighten and re-torque those found loose (note number of connections found loose), and re-torque a minimum of 10% of the bolts on the tower.

2.2.4. Inspect for cracked, bent, twisted, or missing members and areas that show signs of fatigue.

2.2.5. Inspect and note condition of tower main members and guy plates.

2.2.6. Inspect and note condition of safety climbing device.

2.2.7. Inspect and note galvanized finish for damage or fading. Repair damage to galvanized coating on tower structure members.

2.2.8. Inspect and clean all weep holes in pipe legs and bracing for proper drainage.

2.2.9. Inspect and note condition of work platforms and hatches.

2.3. Guy Wires

2.3.1. Inspect and note broken strands, wear/abrasion, and/or rust.

2.3.2. Inspect and note condition of thimbles, turnbuckles, and clamps.

2.3.3. Inspect and note bolted clamps for tightness.

2.3.4. Inspect and note condition of turnbuckles.

2.3.5. Tension guys.

2.3.6. Repair damage to galvanized coating on guy wires and bolted connectors.

2.4. Antenna System

2.4.1. Inspect and note visible damage or distortion.

2.4.2. Inspect and note hardware conditions – do not adjust or tighten hardware that affects antenna adjustment (reference 2.4.8 below).

2.4.3. Inspect radomes and note any visible damage.

2.4.4. Measure and note the resistance of radome heater.

2.4.5. Inspect and note waveguide supports, ice/transmission-line bridge, retainers, and grounds. Also inspect waveguide for dents and condition of flex sections.

2.4.6. Inspect reflectors and note visible damage, loose hardware, bent members, and tower attachment.

Do not adjust reflector.

2.4.7. Inspect condition of ice shields if mounted.

2.4.8. NOTE: Contractor shall not tighten nuts, bolts and fasteners on RFS antennas in the RMR’s

Wyoming Nebraska Maintenance Division (WNMO); and shall only document condition in the inspection report. Contractor shall tighten nuts, bolts and fasteners for all antennas in the Eastern Colorado Maintenance Division RMR (ECMO), the Western Colorado Maintenance Division RMR (WCMO), and Upper Great Plains Region (UGPR)

2.5. Electrical

2.5.1. Inspect and note condition of electrical conduit, pull boxes, vents and drains, and mechanical connections of conduit system to tower.

2.5.2. Inspect tower lights and note loose or missing mounting bolts, loose sockets, and inspect for proper operation of tower lights.

2.6. Lightning Protection Systems

Inspect lightning protection systems on towers and note condition of rods or brush, ground wires, and connection to ground cable at the base of the tower. Not all towers have lightning protection installed.

2.7. Grounding

Inspect and note condition of all ground wires and ground connections above ground.

2.8. Tower Photographs and Inventory Form

2.8.1. Contractor shall at a minimum, take the photographs listed below for each tower. Photographs shall be in full color and a minimum of 5 megapixels each. Photographs shall be included on the CD with completed inspection report submitted to the applicable Government point of contact shown in Exhibit 3 to the PWS.

2.8.1.1. Minimum of three photos at various angles and at a distance from the tower such that the entire tower is in a single shot.

2.8.1.2. One photo taken directly up each side of the tower, showing the majority of the antennas on that side of the tower.

2.8.1.3. One photo taken directly up the center of the tower.

2.8.1.4. Photo(s) of waveguide port(s) including associated ground bar/system taken from both inside and outside the building.

2.8.1.5. One photo of the waveguide ladder from each side of the ladder.

2.8.1.6. One photo of foundation on tower or each leg.

2.8.1.7. Photos of visible tower and waveguide grounding.

2.8.1.8. One photo of each antenna.

2.8.1.9. Photos of tower lighting (if applicable).

2.8.1.10. One photo of tower light controller (if applicable).

2.8.1.11. Photo of tower nameplate if found.

2.8.1.12. Photos of any problems found.

2.8.1.13. Photos of each guy point on the tower (if applicable).

2.8.1.14. Photos of each guy anchor (if applicable).

2.9. Non-Routine Miscellaneous Maintenance. If maintenance other than routine maintenance listed in paragraphs 2.1 through 2.8 above is required, contractor shall provide a written estimate to the Contracting Officer and applicable point of contact listed on Exhibit 5 for review and approval prior to performing such maintenance. If approved, a modification to the Task Order or separate Task Order will be issued to obligate funding. The estimate shall include the loaded labor rate(s)and estimated hours to perform the maintenance and any required materials. No maintenance work shall be performed until approved by the Contracting Officer. A lump sum obligation will be included in the Schedule at Line Items 0002, 1002, 2002, 3002, and 4002.

PWS

EXHIBIT 1

PERFORMANCE REQUIREMENTS SUMMARY

Performance Objective PWS Section Performance Standard

1. Provide tower inspections within the timeframes set forth in the approved plan. Deviations from the plan are minimal except for those that may be changed due to inclement weather and other circumstances outside normal control.

No more than 10% of the scheduled inspections are changed for reasons other than weather or other unanticipated events.

2. Complete inspections are performed on each tower as required by the PWS.

95% of all elements of the inspection and routine maintenance is completed as required by the PWS.

3. Inspection documentation is complete and submitted to the applicable individuals within the timeframes required by the PWS.

90% of the inspection reports, photographs and inventory forms are complete and submitted to the applicable individuals by the required timeframe.

4. Work is performed in a safe manner without accidents or near misses.

100% of the tower inspections are completed without accidents in accordance with the Contractor’s safety and health program and the safety requirements of the PWS.

EXHIBIT 2

Contract Discrepancy Report

Contract No. 1. Report No. for this Discrepancy:

Contractor’s Name:

2. From: (Name of Contracting Officer representative)

Dates

3. Prepared:

4. Returned by Contractor:

5. Action Complete:

6. Discrepancy or Problem: (Describe in detail; include reference to PWS directive; attach continuation sheet, if necessary):

Signature of CO:

7. To: (Contracting Officer)

8. From: (Contractor)

9. Contractor Response as to Cause, Corrective Action and Actions to Prevent Recurrence (Attach Continuation Sheet if Necessary)

10. Signature of Contractor Representative:

Date:

11. Government Evaluation:

12. Government Actions:

13 Close Out Name Title Signature Date

(13a) Contractor Notified

(13b) COR

(13c) CO

EXHIBIT 5

OFFICE E-MAIL NOTES

ROCKY MOUNTAIN REGION (RMR) POINTS OF CONTACT

Technical Support Telecommunications Lead Engineer

ATTN: J5520

5555 E. Crossroads Blvd.

Loveland, CO 80538

To be provided at award

Electronic Reports and CD for all RMR Towers (WNMO, ECMO and

WCMO).

Eastern Colorado Maintenance Office EEC Foreman

ATTN: J5280

5555 E. Crossroads Blvd.

Loveland, CO 80538

To be provided at award

Electronic Report and CD for RMR ECMO Towers Only

Wyoming Nebraska Maintenance Office EEC Foreman

ATTN: J5186

5600 W. Poison Spider Road Casper, WY 82604

To be provided at award

Electronic Report and CD for RMR WNMO Towers Only

Western Colorado Maintenance Office EEC Foreman

ATTN: J5380

1800 South Rio Grande Avenue Montrose, CO 81404-4800

To be provided at award

Electronic Report and CD for RMR WCMO Towers Only

UPPER GREAT PLAINS REGION (UGPR) POINTS OF CONTACT

Western Area Power Administration Electronics Engineer

ATTN: B5130

301 East Kansas Avenue Fort Peck, MT 59223

To be provided at award

Electronic Report and CD For all DSWR Towers.

Western Area Power Administration Electronics Engineer

ATTN: B5332

200 – 4th Street, SW Huron, SD 57350

To be provided at award

Electronic Report and CD For all DSWR Towers.

CONTRACTING OFFICER - ALL REPORTS

Western Area Power Administration Contracting Officer Amy Wright, J1533 5555 E. Crossroads Blvd.

Loveland, CO 80538 awright@wapa.gov

Electronic Report only for all RMR, DSWR, and UGPR Towers mailto:awright@wapa.gov

1. GENERAL
1.1. Scope of Work
1.2. Background

File details come from the government source that posted it. Updated .