Deaeration_Pumps_PWS.doc

DOC document 4 MB Posted

Attached to
WA-SPRING CRK NFH-DEAERATION PUMPS Federal contract opportunity
Solicitation number
140F0121Q0063
Issued by
Department of the Interior Fish and Wildlife Service

View the file

Other files for this federal contract opportunity

Other files attached to WA-SPRING CRK NFH-DEAERATION PUMPS, newest first.
File Type Posted
Pic_2.jpg JPG image
Pic_1.jpg JPG image
Sol_140F0121Q0063.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT (PWS)

Spring Creek NFH Deaeration Pump Service and Repair Part 1 General Information

1. General: This is a non-personal services contract to provide service on four vertical pumps at Spring Creek National Fish Hatchery. The Government shall not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers shall be accountable solely to the Contractor who, in turn is responsible to the Government.

1.1 Description of Services/Introduction: The contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform service on the pump assemblies as defined in this Performance Work Statement except for those items specified as government furnished property and services. The contractor shall perform to the standards in this contract.

1.2 Background: Spring Creek NFH is a recirculating facility and is dependent on a series of vertical pumps that form part of the Biofilter Treatment System. The deaearation pumps mix spring and well water to control the water temperature that feeds the incubation building. Once the water flows through the incubation building it will become part of the reuse system. The pump assemblies from the motor, down to the pump have not been serviced in several years. Servicing the deaerating motors and pump components will increase their life span, prevent unexpected failures and minimize the noise levels.

1.3 Objectives: Service two 25HP and two 15HP vertical pump assemblies and motors.

1.4 Scope: Perform service on all components and advice if replacements are needed to include, but not limited to: Re-bush packing gland, intermediate shafts, head shaft, bearing inserts, bowl assembly, adapter plate, necessary repairs to motor, reinstall pump assemblies and motors, and perform start up. Remove and properly dispose of all waste material. See technical exhibit 2 for existing motor and pump details.

1.5 Period of Performance: The period of performance will be from date of award to 08/06/2021. The funding for this award expires 9/30/2021, and invoices must be submitted through ipp.gov on or before 10/31/2021.

1.6 General Information

1.6.1 Quality Control: The contractor shall develop and maintain an effective quality control program to ensure services are performed in accordance with this PWS. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The contractor’s quality control program is the means by which he assures himself that his work complies with the requirement of the contract.

1.6.2 Quality Assurance: The government shall evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan. This plan is primarily focused on what the Government must do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the minimum acceptable defect rate(s).

1.6.3 Recognized Holidays:

New Year’s Day

Labor Day

Martin Luther King Jr.’s Birthday

Columbus Day

President’s Day

Veteran’s Day

Memorial Day

Thanksgiving Day

Independence Day

Christmas Day

1.6.4 Hours of Operation: The contractor is responsible for conducting business, between the hours of 7:00 am and 4:00 pm Monday thru Friday except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. For other than firm fixed price contracts, the contractor will not be reimbursed when the government facility is closed for the above reasons. The Contractor must at all times maintain an adequate workforce for the uninterrupted performance of all tasks defined within this PWS when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce are essential.

1.6.5 Place of Performance: The work to be performed under this contract will be performed at Spring Creek NFH at 61552 State Road 14 in Underwood, WA 98651.

1.6.6 Type of Contract:

1.6.7 Security Requirements: N/A

1.6.7.1 PHYSICAL Security: N/A

1.6.7.2 Key Control. Not applicable

1.6.7.3 Lock Combinations: N/A

1.6.8 Special Qualifications: N/A

1.6.9 Post Award Conference/Periodic Progress Meetings: The Contractor agrees to attend any post award conference convened by the contracting activity or contract administration office in accordance with Federal Acquisition Regulation Subpart 42.5. The contracting officer, Contracting Officers Representative (COR), and other Government personnel, as appropriate, may meet periodically with the contractor to review the contractor's performance. At these meetings the contracting officer will apprise the contractor of how the government views the contractor's performance and the contractor will apprise the Government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the government.

1.6.10 Contracting Officer Representative (COR): The (COR) will be identified by separate letter. The COR monitors all technical aspects of the contract and assists in contract administration The COR is authorized to perform the following functions: assure that the Contractor performs the technical requirements of the contract: perform inspections necessary in connection with contract performance: maintain written and oral communications with the Contractor concerning technical aspects of the contract: issue written interpretations of technical requirements, including Government drawings, designs, specifications: monitor Contractor's performance and notifies both the Contracting Officer and Contractor of any deficiencies; coordinate availability of government furnished property, and provide site entry of Contractor personnel. A letter of designation issued to the COR, a copy of which is sent to the Contractor, states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates or changes in delivery dates. The COR is not authorized to change any of the terms and conditions of the resulting order.

1.6.11 Key Personnel: The following personnel are considered key personnel by the government: David Carie/Hatchery Manager, Kenneth Lujan/Assistant Manager, and Jorge Alcala/Facilities Operations Specialist, Spring Creek NFH. The contractor shall provide a contract manager who shall be responsible for the performance of the work. The name of this person and an alternate who shall act for the contractor when the manager is absent shall be designated in writing to the contracting officer. The contract manager or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The contract manager or alternate shall be available between 7:00 a.m. to 4:00p.m, Monday thru Friday except Federal holidays or when the government facility is closed for administrative reasons.

1.6.12 Identification of Contractor Employees: All contract personnel attending meetings, answering Government telephones, and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression in the minds of members of the public that they are Government officials. They must also ensure that all documents or reports produced by contractors are suitably marked as contractor products or that contractor participation is appropriately disclosed.

1.6.13 Contractor Travel: N/A

1.6.14 Data Rights : N/A

1.6.15 Organizational Conflict of Interest: Contractor and subcontractor personnel performing work under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent Organizational Conflict of Interests (OCI) as defined in FAR Subpart 9.5. The Contractor shall notify the Contracting Officer immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the Contracting Officer to avoid or mitigate any such OCI. The Contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the Contracting Officer and in the event the Contracting Officer unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the Contracting Officer may effect other remedies as he or she deems necessary, including prohibiting the Contractor from participation in subsequent contracted requirements which may be affected by the OCI.

PART 2

DEFINITIONS & ACRONYMS

2. Definitions and Acronyms:

2.1. DEFINITIONS:

2.1.1. CONTRACTOR. A supplier or vendor awarded a contract to provide specific supplies or service to the government. The term used in this contract refers to the prime.

2.1.2. CONTRACTING OFFICER. A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note: The only individual who can legally bind the government.

2.1.3. CONTRACTING OFFICER'S REPRESENTATIVE (COR). An employee of the U.S. Government appointed by the contracting officer to administer the contract. Such appointment shall be in writing and shall state the scope of authority and limitations. This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.

2.1.4. DEFECTIVE SERVICE. A service output that does not meet the standard of performance associated with the Performance Work Statement.

2.1.5. DELIVERABLE. Anything that can be physically delivered, but may include non-manufactured things such as meeting minutes or reports.

2.1.6. KEY PERSONNEL. Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the Key Personnel listed in the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.

2.1.7. PHYSICAL SECURITY. Actions that prevent the loss or damage of Government property.

2.1.8. QUALITY ASSURANCE. The government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.

2.1.9. QUALITY ASSURANCE Surveillance Plan (QASP). An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.

2.1.10. QUALITY CONTROL. All necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.

2.1.11. SUBCONTRACTOR. One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.

2.1.12. WORK DAY. The number of hours per day the Contractor provides services in accordance with the contract.

2.1.12. WORK WEEK. Monday through Friday, unless specified otherwise.

2.2. ACRONYMS:

ACOR

Alternate Contracting Officer's Representative

CCE

Contracting Center of Excellence

CFR

Code of Federal Regulations

CONUS

Continental United States (excludes Alaska and Hawaii)

COR

Contracting Officer Representative

COTR

Contracting Officer's Technical Representative

COTS

Commercial-Off-the-Shelf

FAR

Federal Acquisition Regulation

KO

Contracting Officer

NFH

National Fish Hatchery

OCI

Organizational Conflict of Interest

OCONUS

Outside Continental United States (includes Alaska and Hawaii)

ODC

Other Direct Costs

PIPO

Phase In/Phase Out

POC

Point of Contact

PRS

Performance Requirements Summary

PWS

Performance Work Statement

QA

Quality Assurance

QAP

Quality Assurance Program

QASP

Quality Assurance Surveillance Plan

QC

Quality Control

QCP

Quality Control Program

TE

Technical Exhibit

PART 3

GOVERNMENT FURNISHED PROPERTY, EQUIPMENT, AND SERVICES

3. GOVERNMENT FURNISHED ITEMS AND SERVICES: N/A

PART 4

CONTRACTOR FURNISHED ITEMS AND SERVICES

4. CONTRACTOR FURNISHED ITEMS AND RESPONSIBILITIES:

4.1 General The Contractor shall furnish all supplies, equipment, facilities and services required to perform work under this contract that are not listed under Section 3 of this PWS.

4.2 Secret Facility Clearance: N/A

4.3. Materials: Contractor shall provide all materials to perform service on vertical pumps, and motors (two 25 hp and two 15 HP).

4.4. Equipment:

PART 5

SPECIFIC TASKS

5. Specific Tasks:

5.1. Basic Services.

5.2 Inspect and Service the pump assemblies. Advise if replacement is needed

5.2.1 (Option Item, if exercised)- Full replacement of bowl assemblies

5.3 Inspect and Service the column, shaft and different stage bearings. Advise if replacement is needed

5.3.1 (Option Item, if exercised)- Full replacement of head shaft, intermediate shaft and adapter plate.

5.7 Rebush and pack gland

5.8 Dismantle and inspect motors. Bake and treat windings & balance, De insulate upper bearing carrier, furnish and install AEGIS shaft grounding ring, furnish and install FAG ceramic ball bearing. Advise if additional replacement parts are needed.

5.9 Reinstall all components and provide start-up

PART 6

APPLICABLE PUBLICATIONS

6. Applicable Publications (Current Editions)

6.1. The Contractor must abide by all applicable regulations, publications, manuals, and local policies and procedures.

PART 7

ATTACHMENT/TECHNICAL EXHIBIT LISTING

7. Attachment/Technical Exhibit List:

7.1. Attachment 1/Technical Exhibit 1 – Performance Requirements Summary

7.2. Attachment 2/Technical Exhibit 2 – Additional Pump and Motor information sheet

TECHNICAL EXHIBIT 1

Performance Requirements Summary The contractor service requirements are summarized into performance objectives that relate directly to mission essential items. The performance threshold briefly describes the minimum acceptable levels of service required for each requirement. These thresholds are critical to mission success.

Performance Objective

(The Service required—usually a shall statement)

Standard
Performance Threshold (This is the maximum error rate. It could possibly be “Zero deviation from standard”)

Method of Surveillance

PRS # 1.

Provide service and repairs of all components to include, but not limited to: bowl assemblies, column, shaft and spider assemblies if applicable, bushing and packing for housing, motors dip & bake and balance, reinstall pump assembly and motor, and perform start up. Advice if replacement of parts are needed. Remove and properly dispose of all waste material

Provide service and repairs of all components to include, but not limited to: pump assembly, column, shaft and spider assemblies if applicable, bushing and packing for housing, motors dip & bake and balance, reinstall pump assembly and motor, and perform start up. Advice if replacement of parts are needed. Remove and properly dispose of all waste material
Zero deviation from standard
100% Inspection

TECHNICAL EXHIBIT 2

Additional Pump and Motor information sheet