| | | FY 15 | | | | FY 16 | | | | FY 17 | | | | FY 18 | | | | |
| Start | End | 1-Oct-14 | 1-Jan-15 | 1-Apr-15 | 1-Jul-15 | 1-Oct-15 | 1-Jan-16 | 1-Apr-16 | 1-Jul-16 | 1-Oct-16 | 1-Jan-17 | 2-Apr-17 | 2-Jul-17 | 2-Oct-17 | 2-Jan-18 | 2-Apr-18 | 2-Jul-18 | |
| TA 1 - Robustness | | | | | | | | | | | | | | | | | | | |
| Phase 1 | 17-Feb-15 | 16-Aug-15 | | | | | | | | | | | | | | | | | Convention: |
| Task 1.1 | | | | | | | | | | | | | | | | | | | Task X.Y.Z |
| Sub-Task 1.1.1 | | | | | | | | | | | | | | | | | | | X = Technical Area [1, 2, or 3] |
| Milestone 1.1.1.1 | | | | | | | | | | | | | | | | | | | Y = Task # |
| | | | | | | | | | | | | | | | | | | Z = Sub-task # |
| Phase 2 | 17-Aug-2015 | 16-Aug-2016 | | | | | | | | | | | | | | | | | |
| Task 1.2 | | | | | | | | | | | | | | | | | | | Use additional levels of hierarchy, if necessary |
| Sub-Task 1.2.1 | | | | | | | | | | | | | | | | | | | |
| Milestone 1.2.1.1 | | | | | | | | | | | | | | | | | | | Gantt Chart Must Match SOW |
| Phase 3 | 17-Aug-2016 | 16-Aug-2017 |
| Task 1.3 | | |
| Sub-Task 1.3.1 | | |
| Milestone 1.3.1.1 | | |
| TA 2 - Stability | | |
| Phase 1 | 17-Feb-2015 | 16-Aug-2015 |
| Task 2.1 | | |
| Sub-Task 2.1.1 | | |
| Milestone 2.1.1.1 | | |
| Phase 2 | 17-Aug-2015 | 16-Aug-2016 |
| Task 2.2 | | |
| Sub-Task 2.2.1 | | |
| Milestone 2.2.1.1 | | |
| Phase 3 | 17-Aug-2016 | 16-Aug-2017 |
| Task 1.3 | | |
| Sub-Task 1.3.1 | | |
| Milestone 1.3.1.1 | | |
| TA 3 - Safety | | |
| Phase 1 | 17-Feb-2015 | 16-Aug-2015 |
| Task 3.1 | | |
| Sub-Task 3.1.1 | | |
| Milestone 3.1.1.1 | | |
| Phase 2 | 17-Aug-2015 | 16-Aug-2016 |
| Task 3.2 | | |
| Sub-Task 3.2.1 | | |
| Milestone 3.2.1.1 | | |
| Phase 3 | 17-Aug-2016 | 16-Aug-2017 |
| Task 3.3 | | |
| Sub-Task 3.3.1 | | |
| Milestone 3.3.1.1 | | |