CS Powder SOW- SAM.GOV sources sought posting.docx
DOCX document 24 KB Posted
- Attached to
- ABC Powder and Storage Unit for WVA Federal contract opportunity
- Solicitation number
- W911PT24Q0102
About this file
This document is a Statement of Work (SOW) for a federal contract opportunity to enable the scale-up of powder processing and storage capabilities. The key requirements include:
The contractor shall purchase 1,100 lbs. of raw ABC CS powder, perform in-house testing, and package at least 900 lbs. of the powder for the government within 14 months after contract award. The contractor shall also increase the powder storage capacity to at least 2,000 lbs. at both the contractor facility and Watervliet Arsenal (WVA) within 12 months after contract award. Deliverables include a kickoff meeting, packaging of at least 900 lbs. of powder, and providing 2,000 lbs. of powder storage capacity. Reporting requirements include certification documentation, monthly progress reports, and final reports. The powder and storage cabinets shall be delivered to the US Army DEVCOM-AC, Benet Labs in Watervliet, NY. The powder integrity must be certified for at least 24 months of storage.
The related federal contract opportunity is a pre-solicitation for a new ABC Powder and Storage Unit, with the U.S. Army Contracting Command - Watervliet Arsenal as the contracting office. This is a request for information only, and no solicitation or contract award is planned at this time.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SAM Market Survey Questionnaire - Powder Storage Unit- Fill Ins (1).pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (SOW)
for Powder Scale-up
1.0 BACKGROUND
1.1 Cold Spray uses specialized, highly engineered powders with tight chemistry requirements in order to achieve a high-quality product with good repeatability and reliability.
1.2 The Customer has provided funding in order to expand powder processing and storage capabilities in order to meet anticipated powder requirements without opening up the existing powder specification.
2.0 PURPOSE
2.1 This Statement of Work defines the requirements and deliverables to be used in order to enable a scale-up in powder processing and storage in order to meet anticipated powder requirements.
3.0 REQUIREMENTS
3.1 COA #1A - The contractor shall purchase 1,100 lb. of raw, ABC CS powder, shall perform the necessary in-house testing and evaluation in order to ensure that the powder, and shall inertly package at least 900 lb. of powder for the Gov’t within 14 months after contract award.
3.2 COA #2A - The contractor shall increase the powder storage capacity to at least 2,000 lbs. at both the contractor facility and WVA within 12 months after contract award.
4.0 DELIVERABLES
4.1 Kickoff meeting – Initial Program Plan Provided.
4.2 Package at least 900 lb. of ABC CS powder within 14 months after contract award.
4.3 Provide powder storage capability of at least 2,000 lbs. at both the contractor facility and WVA within 12 months after contract award.
5.0 REPORTING REQUIREMENTS:
5.1. Certification documentation demonstrating that the powder meeting the requirements of drawing (#12528617) and the powder specification (V5c or later).
5.2 Certification documents from NFPA and/or other sources demonstrating that the storage capacity at both the contractor facility and WVA meets the requirements of Sect. 3.2.
5.3 Monthly progress reports shall be provided to DEVCOM AC Benet Labs for programmatic review.
5.4 Final reports delivered after COAs #1 and #2 have been completed.
6.0 DELIVERY
6.1 Unless otherwise specified, the powder and safety storage cabinet/s shall be delivered to:
| US Army DEVCOM-AC, Benet Labs |
| 1 Buffington St. |
| Watervliet, NY 12189 |
| United States |
6.2 Freight shall be included.
7.0 TRAINING
| 7.1 | The training site will be at WVA during and will be at least 1 day in duration. |
| 7.2 | The training will be provided for at least 2 personnel from both WVA and Benet Laboratories. |
8.0 WARRANTY
| 8.1 | The integrity of the powder must be certified for at least 24 months of storage. |
| 8.2 | The warranty starts from the signature of the final acceptance. |