Copy of P11 Device Testing Data Sheets.xlsx

XLSX spreadsheet 32 KB Posted

Attached to
H344--SDVOSB SET ASIDE | Boiler Safety Device Testing St. Cloud VAMC Federal contract opportunity
Solicitation number
36C26320Q0625
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 23

View the file

Other files for this federal contract opportunity

Other files attached to H344--SDVOSB SET ASIDE | Boiler Safety Device Testing St. Cloud VAMC, newest first.
File Type Posted
36C26320Q0625.docx DOCX document
STC WD.docx DOCX document
P11 Low O2 Testing Data Sheet.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Boiler Devices

Boiler Safety Device Testing Data Sheet Boiler No. ______ Date___________
Department of Veterans Affairs Facility _______________________________________________
Boiler Make, Type and Model, Year Built _________________________________________________________________________________________
Burner Make, Type, Fuels, Year Built____________________________________________________________________________________________
Test Personnel/Company_____________________________________________________________________________________________________
VA Personnel _____________________________________________________________________________________________________________
Operation -Normal System
Trip PointOperationRemarks - Device OK/Adjusted/Replaced
Pressure Vessel
High water alarminches upNormal water level _____inches up
Low water alarminches up
Low water cutout (slow drain)inches up
Aux low water cutout (slow drain)inches up
Low water cutout shunt switchOK Failed
Aux low water cutout shunt switchOK Failed
High steam press cutout (recycle)psiHeader____ psi
High steam press cutout (non-recycle)psi
Steam safety valve No.1 - poppsiSet _____psi
- blowdownpsi
Steam safety valve No. 2 - poppsiSet _____psi
- blowdownpsi
Steam safety valve No. 3 - poppsiSet _____psi
- blowdownpsi
Steam safety valve accumulation testOK Failed
Main Gas
High pressure cutoffpsi/in.wcPRV set at ____psi/in.wc
Low pressure cutoffpsi/in.wc
Safety shut off valves proof of closureOK Failed
Leak test safety shut off valves (seats)OK Failed
Leak test vent valve (seats)OK Failed
Oil
High pressure cutoffpsiOperating ____ psi
Low pressure cutoffpsi
High temperature cutoff (heated oil)degrees FOperating ____deg F
Low temperature cutoff (heated oil)degrees F
Low atomizing pressure (No. 1 switch)psipsi
Low atomizing pressure (No. 2 switch)psi
Low atomizing/oil differential pressurepsipsi
Oil burner position switch (if provided)OK Failed
Safety shut off valves proof of closureOK Failed
Leak test safety shut off valves (seats)OK Failed
Cold start steam atom burners on compr airOK Failed
LP gas igniter operationOK Failed
Atomizing air compressor motor interlockOK Failed
Igniter Gas (Pilot)
Low gas pressurepsi/in. WCpsi/in. WC
Leak test safety shut off valves (seats)OK Failed
Leak test vent valve (seats)OK Failed
Combustion Air, Flue Gas, Burner Management Programming
Forced draft fan motor energized interlockOK Failed
Forced draft damper wide open for purgeOK Failed
Outlet dmpr (if provided) wide open for purgeOK Failed
Prepurge airflow interlockin. WCin. WC@100%
Prepurge timingsecsec
Ignition timingsec10 sec*
Postpurge timingsec15 sec
Low fire position interlockOK Failed
Combustion air flow interlockin. WCin.WC min
Low flue gas oxygen interlock%O2
High /furnace/boiler outlet/ pressure (if prov)in. WCin. WC
Pneumatic control air press interlock (if prov)psipsi
FGR damper(if provided) set for prepurgeOK Failed
Main flame out - time to close SSO valvessec4 sec
Ignition flame out - programmed shutdownsecsec
Minimum igniter flame testOK Failed
Scanner not sensing ignition spark (UV only)OK Failed
* 15 seconds allowed on No. 5 and No. 6 oil.
VACO 183A 08/22/07Reference - Test Methods: VHA Boiler Plant Safety Devices Testing Manual, Fourth Ed., October 2017

Calibration

Checklist - Boiler Plant Inspections, Calibrations and Tests - One Year Period
Department of Veterans Affairs Facility ________________________ Year 2____
Boiler Safety Devices - Testing - Twice per year (Utilize "Boiler Safety Device Testing Data Sheet".)
First Test DateCorrections CompletedSecond Test DateCorrections Completed
Boiler No. 1
Boiler No. 2
Boiler No. 3
Boiler No. 4
Boiler Internal and External Inspections - Once per year (Qualified professional inspector - provide detailed reports.)
Internal Inspection DateCorrections CompletedExternal Inspection DateCorrections Completed
Boiler No. 1
Boiler No. 2
Boiler No. 3
Boiler No. 4
Feedwater Deaerator Internal Cleaning and Visual Inspection - Once per year
Internal Insp and Cleaning DateCorrections Completed
Feedwater Deaerator Internal Inspection and Weld Testing -Every 6 years (Qualified professional inspection - provide detailed report.)
Intnl Insp and Weld Testing DateCorrections Completed
Controls and Instruments Calibration -Twice per year (Technicians must provide detailed reports.)
First Calib DateCorrections CompletedSecond Calib DateCorrections Completed
Boiler controlsCombustion
Oxygen trim
Flue gas recirculation (FGR)
Outlet draft
Feedwater level controls
Master pressure
InstrumentationSteam flow
Gas flow
Oil flow
Flue gas oxygen
Stack temperature
Boiler draft gages
Economizer temperatures
Pressure transmitters
Temperature transmitters
Pressure gages
Thermometers
Annunciators
Recorders and indicators
Computer work station
Feedwater DeaeratorHigh level alarm
Low level alarm
Overflow
Safety valve
Vacuum breaker
Water level controls
Condensate Storage TankHigh level alarm
Low level alarm
Overflow
Water level controls
Building combustion air intake interlock
Building dangerous gas detection system
Steam Safety Valves ( non-boiler) and Liquid Relief Valves (Oil Pumps and Economizers) Testing - Once per year
Test DateCorrections Completed
Steam PRV station safety valves
Steam PRV station safety valves
Oil pump relief valves
Economizer relief valves
Burner Performance Testing Dates - Twice per year (Refer to testing data sheets.)
First Test DateCorrections CompletedSecond Test DateCorrections Completed
Boiler No. 1
Boiler No. 2
Boiler No. 3
Boiler No. 4
Reference - Testing Requirements: VHA Directive 1810, Boiler Plant Operations
VACO 183A 1/19/07

Combustion Gas

BOILER NATURAL GAS COMBUSTION PERFORMANCE TEST DEPARTMENT OF VETERANS AFFAIRS MEDICAL CENTER__________________________________ DATE_________________
Boiler No. ____ Boiler Make, Model, Type_______________________________________________ Burner Make, Model, Type____________________________________________
Clock Time for Test PointHour - Min
Firing RateControl Output0 - 100%
Fuel Flow Control Valve0 - 100%
Combustion Air Damper0 - 100%
Forced Draft Fan VFDHz
Flue Gas AnalysesO2 - Test Instrument%
CO - Test InstrumentPPM
NOX-Test InstrumentPPM
O2 - Plant Data System%
Flue Gas Temp.Boiler OutletDegrees F
Economizer OutletDegrees F
DraftWindbox / FurnaceIn WC
Boiler Outlet / Econ OutletIn WC
Fuel DataRegulator Press - InletPSI
Regulator Press - OutletPSI / In WC
Burner PressPSI / In WC
Flow RateSCFH
Energy InputBTU/HR
Flame Appearance
Boiler Steam OutputFlow RateLB/HR
Press - Boiler / HeaderPSI
Boiler Water Level% Glass
FeedwaterPress - Econ In / OutPSI
Press - Control Valve InletPSI
Temp - Econ In / OutDegrees F
Temp - Boiler InletDegrees F
Deaerator Steam PressPSI
Test Personnel: __________________________________________________________________________________________________________________________________________
Notes:
Reference - Test Methods: Refer to VA Master Spec for the boiler, Part 3, Inspections and Tests.
VACO 183A 1/19/07

Combustion Oil

BOILER NO. 2 FUEL OIL COMBUSTION PERFORMANCE TEST DEPARTMENT OF VETERANS AFFAIRS MEDICAL CENTER__________________________________DATE_________________
Boiler No. ____ Boiler Make, Model, Type_______________________________________________ Burner Make, Model, Type____________________________________________
Clock Time for Test PointHour - Min
Firing RateSubmaster0 - 100%
Fuel Flow Control Valve0 - 100%
Comb. Air Damper0 - 100%
FD Fan VFDHz
Flue Gas AnalysesO2 - Test Instrument%
CO - Test InstrumentPPM
NOX-Test InstrumentPPM
O2 - Plant Data System%
Smoke
Flue Gas Temp.Boiler OutletDegrees F
Economizer OutletDegrees F
DraftWindbox / FurnaceIn WC
Outlet - Boiler / EconIn WC
Fuel DataPress - Header / Fuel TrainPSI
Burner Press - Oil / AtomPSI
Flow RateGPH
Energy InputBTU/HR
Flame Appearance
Boiler Steam OutputFlowLB/HR
Press - Boiler / HeaderPSI
Boiler Water Level% Glass
FeedwaterPress - Econ In / OutPSI
Press - Control Valve InletPSI
Temp - Econ In / OutDegrees F
Temp - Boiler InletDegrees F
Deaerator Steam Press.PSI
Test Personnel: __________________________________________________________________________________________________________________________________________
Notes:
Reference - Test Methods: Refer to VA Master Spec for the boiler, Part 3, Inspections and Tests.
VACO 183A 1/19/07

File details come from the government source that posted it. Updated .