(Construction Scope of Work)

CONSTRUCTION SCOPE OF WORK

U.S. GENERAL SERVICES ADMINISTRATION, ROCKY MOUNTAIN REGION 8

Date: 3/6/23 Revision: N/A

Section 1: Project Title Pembina Levee Repair

Section 2: Project Location, Building Name, & Building Number 10980 HWY 29 112 W Stutsman, Pembina ND 58271 Building Number: ND0545AO

Section 3: Contact List

Contracting Officer (CO) Name: Laura Funk Email: laura.funk@gsa.gov Address: 657 2nd Ave North Fargo, ND 58102 Phone (O): 701-566-6114

Development Project Manager Name: Jesse Johnson Email: jesse.johnson@gsa.gov Address: 220 East Rosser Ave Bismarck, ND 58501 Phone (O): 701-557-9649 Phone (C): 701-202-9036

Property Manager Name: Curtis Schumaier Email: curtis.schumaier@gsa.gov Address: 100 1st Street SW Minot, ND 58701 Phone (O): 701-552-9852 Phone (C): 701-340-5954

Building Management Coordinator Name: Theuns Steyn Email: theuns.steyn@gsa.gov Address: 10980 I29 Pembina, ND 58271 Phone (O): 303-236-0433 Phone (C): 701-270-2632

Section 4: Project Background & Project Description The GSA has initiated a project to prevent any further damage to the existing clay liner to the flood levee in Pembina ND. There are signs of erosion to the embankment after the 2020 flood and to prevent any further damage to the levee, it is proposed to line the embankment with riprap material.

Section 5: Project Objectives The contractor shall provide labor, materials, equipment, and supervision necessary to perform:

1) The area where riprap will be installed shall be placed at a consistent elevation throughout the dike. The contractor may need to shoot the elevation of the top of riprap and make that consistent throughout the top of the dike. The area of the riprap will be approximately 25’ wide and 350’ long. See picture Below.

2) The RipRap shall be 18” – 24” deep and placed over an approved geofabric material.

3) The contractor shall use stone that is clean and free of deleterious material.

4) The stone shall be field stone or quarry stone that meet the criteria of Grade I on the Riprap Gradation chart under section 256 of the NDDOT Standard Specifications for Road and Bridge Construction.

5) The contractor shall not use field stone that consists of sandstone, shale, or soft limestone, nor shall the stone have cracks or flaws that would cause splitting or breaking up or is easily abraded or crushed.

6) the contractor shall place the stones on sloped areas beginning at the toe of the slope. Set stones to obtain an even outer surface and a uniform appearance.

7) The contractor shall remove any topsoil if present, and place the largest stones in the base, filling gaps with smaller stones.

Contractor shall be careful not to remove any of the existing clay liner.

a. Place stones by mechanical means or by hand.

b. Distribute stones evenly over the riprap area without:

i. Material segregation

ii. Deviating from the designated slope and grade by greater than 6 inches.

c. Do not drop riprap stones from a height greater than 3 feet. Place stones greater that 250 pounds with no free-fall.

Achieve contouring of the stones during initial placement. Do not roll the stones along the surface. Begin placement of the stone cover at the base of the slope and at the center of the fabric covered zone.

8) The contractor shall place the geosynthetic (type RR) with the longest dimension parallel to the direction of the water flow. Place overlaps so the upstream strip overlaps the downstream strip. Overlap splices and joints at least 18 inches. Pin or staple all overlaps at 3-foot intervals.

9) The contractor shall patch damaged areas of the geosynthetic material by overlapping the tear a minimum of 36 inches with geosynthetic and secure the perimeter of the patch area with pins or staples.

10) The contractor shall re-seed any disturbed areas on the top side of the dike.

11) A staging area will be determined by mutual agreement after contract award.

12) The following information is provided for bidding purposes only. The contractor is advised to conduct a site visit and field-verify the exact information required for use in completing the work and submitting an offer.

13) The Contractor is responsible for locating all utilities in project area, both public and private. GSA will make any existing drawing available for reference purposes only, actual locate is still contractor’s responsibility.

14) The contractor is responsible for the protection of all existing building property surfaces from damage due to work performed under this contract. Damages to existing surfaces caused by the performance of this contract shall be repaired as to match the existing surface finish at no additional cost to the Government.

15) The Contractor shall remove all debris generated in the performance of this contract daily.

16) The CO has the right to reject any unsatisfactory or unsuitable material or workmanship.

Section 6: Proposal Pricing & Site Walk

1) Pre-proposal Site Visit Meeting:

a) The site visit shall consist of a meeting to review construction requirements followed by a walk-thru of the project site. The meeting shall be attended by the contractor and GSA project personnel, and appropriate sub-contractors. Contact the Project Manager to schedule a site visit.

b) Review existing conditions of the project area including any field verification.

Review the solicitation/evaluation requirements

2) Cost Proposal Requirements:

a) When submitting a proposal, provide a cost breakdown for each task into the following categories: Materials, equipment, labor hours, subcontractor's quotes, overhead, profit, and bond broken down into shell, tenant improvement (TI) (by tenant), Building- Specific Amortized Capital (BSAC), and environmental (as applicable). Follow P120 guidelines for tier level 3 based on project triage tool. Pricing shall be broken down by Construction Specification Institute (CSI) divisions.

b) Base Bid-

Section 7: Period of Performance Once award has been issued, the contractor has 80 calendar days to complete the project. The contractor must also promptly begin the badging process at the time of award.

Section 8: Universal Scope Requirements ALL of the requirements in this section are MANDATORY for ALL GSA projects

See the attached Universal Scope Requirements document for the full details outlining each item

Failure to comply with any and all of the requirements will result in the project not being accepted as complete

REQUIREMENTS for ALL Projects (Construction, Design & Design/Build)

a. Safety and Health Program

b. Asbestos Containing Materials. To comply with federal and state regulations as well as GSA policy, an asbestos pre-alteration assessment is required for all construction projects as outlined in Section B of the Universal Scope Requirements.

c. Lead Containing Paint / Lead Based Paint

d. Accessibility

e. Green Purchasing

f. Construction Indoor Air Quality (IAQ) Management Plan

g. Construction Waste Diversion

h. Excavation Permit

i. Utility Locates

j. gBuild

k. Historic Compliance

l. Commissioning (for all new AHUs or all new building system equipment)

m. GSA IT Network

n. Building Monitoring and Control Systems (BMC)

o. Advanced Metering System

p. Sustainable Environmental Management System (SEMS)

Section 9: Submittals

1) Contractor shall submit a Method of Procedures (MOP) to the GSA Delivery Project Manager (PM) for approval prior to commencement of work. At a minimum, the MOP shall include:

a) Brief narrative describing method of accomplishment, construction techniques, etc

b) Project schedule (to include critical path, major milestones, long lead time items, mob & de-mob, inspection dates, substantial completion, and occupancy dates)

c) Service/Utility Outages (if necessary)

d) Phasing schedule (if necessary)

e) Any building infrastructure/BAS equipment that may be impacted

2) All new equipment and anything requiring a preventative maintenance plan shall be inputted into Maximo upload template.

Information needed from the contractor will be all: Manufacturer, Model Number, Part Number, Serial Number, Any Manufacturer Warranty Information.

3) Manufacturer's specifications, instructions, and material specification sheets in original form

4) Submittal register/ log for all products specified to establish a standard of quality to include. Submittal register response by the government shall be (14) calendar days or less.

a) For pricing purposed please assume 1 hard copy of submittals and 1 electronic copy to be sent to the project manager.

Distribution list including final quantities will be finalized after receipt of the submittal log/ register by GSA project manager.

5) If product samples are not submitted in a timely fashion, any delays caused by the contractor will not warrant a time extension.

After completion of all work, the Contractor shall submit to the project manager the manufacturer's specifications, instructions, and material specification sheets in original form. Additionally, the Contractor shall submit all inventory changes (removals, additions, upgrades, etc., and new condition codes) to the COR.

6) Submittal response by the government shall be (14) calendar days or less.

Section 10: General Requirements

1) Contractor Use of the Premises

a) During the period of the project, the contractor will have access to the site only during business hours of 6:00 am 6:00

pm. No on-site work shall be performed outside these hours or on holidays unless otherwise directed by the Contracting Officer. The contractor will need to coordinate with the Contracting Officer to arrange access to the parking lot. The contractor shall make every effort to cause a minimum of damage to parking lots, any other paved areas, any items that need to be moved during the course of the project, and any areas not included in this scope of work. Any damage caused will be repaired at the contractor’s expense.

2) Progress Meetings

a) Progress meetings are not required for this project. The project manager and building team representative shall make daily inspections of the work progress.

3) Equipment

The contractor shall provide all equipment associated with the entire project, operate in a safe manner and adhere to all OSHA and GSA standards.

4) Equipment and Material Storage The contractor shall provide and store all equipment, the materials specified above, and any other materials required completing the project. The materials are required to be kept clean and dry throughout the duration of the project.

Contractor to coordinate with building manager for location of storage sheds.

5) Electricity, Water, and Gas GSA will pay for electricity, water, and gas during the course of this project. The contractor is responsible for making connections to the existing systems. Temporary electrical work shall meet the requirements of NFPA 70-1996 (NEC), Article

305. When temporary connections are removed, restore existing utility services to their original condition.

6) Fire Watch Contractor shall be responsible for providing fire watch if required per attached GSA fire watch guidelines.

7) Fire Alarm Impairment and Hot Work When a fire suppression or alarm system impairment is required, contractor shall provide written outage request to GSA for approval in advance of impairing any systems. Contractor shall be responsible for having a GSA approved NICET certified fire alarm contractor perform all system impairments. During fire alarm/suppression impairments or hot work procedures, contractor shall provide a fire watch per the GSA Regional Fire Watch Guidelines.

8) Protection of Public The building site will continue to be used by tenants. The contractor shall fence, barricade, or otherwise block off the immediate work area to prevent unauthorized entry. The contractor shall illuminate barricades and obstructions at night and maintain safe building access and egress for tenants.

9) Housekeeping The project site shall be kept in a neat, orderly, and safe condition at all times. The contractor shall provide enough containers for collecting construction debris and construction materials to be recycled. The contractor shall wet down dry materials and rubbish to prevent blowing dust and keep volatile wastes in covered containers.

10) Transportation and Deliveries The contractor shall arrange deliveries of materials in accordance with construction schedules; coordinate with COR to avoid conflict with other tenants and other work conditions at the site. Contractor must make GSA PM & CO aware of any lead times that may affect the project schedule.

11) Cleaning Before scheduling the final inspection, the Contractor shall accomplish six items: (1) Remove all tools, equipment, surplus material, and rubbish; (2) Restore or refinish, to original condition, surfaces that are damaged due to the work of this contract; (3) Remove grease, dirt, stains, foreign materials, and labels from finished surfaces; (4) Thoroughly clean building interiors; (5) Pickup all construction debris from the site; and (6) At time of final inspection, project shall be thoroughly cleaned and ready for use.

12) Protection of the Building The construction contractor is responsible for the protection of all existing building property for damage due to work performed under this contract. Any damage caused by the performance of this contract shall be repaired to match like or better condition at no additional cost to the government

13) Disruptive Work All painting, staining, or other activity which may cause noxious or undesirable fumes and/ or any noisy work that may be disruptive to the tenants/ public must be performed after normal working hours. The use of paint or stain that does not generate odors is preferred and may be required if the space will be occupied the following day with prior written approval from GSA.

Section 11: Badging & Security

1) The contractor may be subjected to additional background checks by the local agency at any border station projects.

2) US Access shared enrollment centers can be found at fedidcard.gov. Travel distances to the nearest center should be accounted for during the badging process.

Section 12: Payments

1) Information regarding payment requests and payment is in the solicitation/ contract. Please contact the CO if you have any questions regarding payments.

Section 13: Substantial Completion & Final Inspection

1) When project, or designated portion of project is complete, request a final inspection. Upon receipt of request that project is substantially complete, the Contracting Officer will proceed with the inspection within ten days of receipt of request or will advise the contractor of items that prevent the project from being designated substantially complete.

2) Red-lined drawings and CAD and/or BIM as-built drawings, and field training for Operations and Maintenance (O&M) personnel shall be provided at completion of project. Maintain one complete set of contract drawings. Clearly mark changes, deletions, and additions using GSA CAD Standards to show actual construction conditions. Show additions in red, deletions in green, and special instructions in blueprint. Provide to GSA within timeframe negotiated at time of award.

3) The contractor shall provide O&M manuals. The O&M manuals shall contain the following:

Executed Warranties (at project completion) Maintenance and operation manuals

Section 14: Attachments

1) Universal Scope requirements