Construction Scope of Work_2023 03 27.pdf
PDF 2 MB Posted
- Attached to
- Pembina Garage Door Replacement Project Federal contract opportunity
- Solicitation number
- 47PJ0023R0070
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 3in Energy Saver Specifications.pdf | ||
| Universal Scope Requirements v3_8 2022 08 01.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(Construction Scope of Work)
CONSTRUCTION SCOPE OF WORK
U.S. GENERAL SERVICES ADMINISTRATION, ROCKY MOUNTAIN REGION 8
Date: March 27, 2023 Revision: 2.0
Section 1: Project Title 547 Pembina “B” Garage Doors Replacement Project
549 Pembina VACIS Garage Door Replacement Project
Section 2: Project Location, Building Name, & Building Number Pembina Port of Entry Secondary Inspection Building Pembina, ND 58271-9745 Building Number: ND0547AO
Section 3: Contact List
Contracting Officer (CO) Name: Laura Funk Email: laura.funk@gsa.gov Address: 657 2nd Ave North
Fargo, ND 58102 Phone (O): 701 566-6114
Project Manager Name: Jesse Johnson Email: jesse.johnson@gsa.gov Address: 220 East Rosser Ave
Bismarck, ND 58501 Phone (O): 701-557-9649 Phone (C): 701-202-9036
Building Manager Name: Theuns Steyn Email: theuns.steyn@gsa.gov Address: 10980 Highway 29
Pembina, ND 58271 Phone (O): 701-270-2632
Section 4: Project Background & Project Description The General Services Administration is initiating a project to replace (4) four failing garage doors at the Pembina Port of Entry. Two of the doors are in Building B and identified as door #9 east and door #9 west, which are 16’H x 18’W. The other two overhead doors are located in the VACIS building, which are 22’H x 16’W.
Section 5: Project Objectives The contractor shall provide labor, materials, equipment, and supervision necessary to perform:
1) Building B Doors, Door #9 East, and Door #9 West, 16’H x 18’W:
a. Remove and replace two existing doors, tracks, and cables necessary to warranty the work for a period of 1 year.
b. Doors shall be a Midland Garage Door, Model 3” ENERGYSAVER see attached Specification or an approved equal.
The doors shall be 16’H x 18’W.
c. Each door shall have 4 windows installed, with a minimum of ½” insulated glass.
d. Door R-value shall exceed 17.0 with closed cell polystyrene insulation.
e. Door Panel Color shall be Coffee.
f. Doors are to be double style, track to be 3”, and springs shall have no less than 25,000 cycle springs. Spring shaft line to have pillow block bearing on the end plates.
g. Doors shall be prepped for trolley style operator with an exterior center stile and additional strut.
h. Door cable shall be the maximum size allowed on the cable drums.
i. Contractor to field verify door measurements.
j. Contractor to remove and replace miller edge (Safety Strip) with new.
k. Contractor to remove and replace existing ¾ HP commercial operators to include brakes and wall stations.
l. Contractor shall install new 3 button wall stations.
m. The Government shall retain the old operator’s and the wall stations. Contractor shall contact the building manager for location to store these items.
2) VACIS Building Doors, 22’H x 16’W:
a. Remove and replace two existing doors, and cables necessary to warranty the work for a period of 1 year.
b. Doors shall be a Midland Garage Door, Model 3” ENERGYSAVER see attached Specification or an approved equal.
The doors shall be 22’H x 16’W.
c. Each door shall have 4 windows installed, with a minimum of ½” insulated glass.
d. Door R-value shall exceed 17.0 with closed cell polystyrene insulation.
e. Door Panel Color shall be Coffee.
f. Doors are to be double style, track to be 3”, and springs shall have no less than 25,000 cycle springs. Spring shaft line to have pillow block bearing on the end plates.
g. Doors shall be prepped for trolley style operator with an exterior center stile and additional strut.
h. The contractor shall install a new track for the new overhead door.
i. Door cable shall be the maximum size allowed on the cable drums.
j. Contractor to field verify door measurements.
k. Contractor to remove and replace miller edge (Safety Strip) with new.
l. Contractor to remove and replace commercial operators to include brakes and wall stations. Motor shall be sized according to the doors manufacturer’s specifications.
m. The contractor shall dispose of the existing roll up doors accordingly.
n. Contractor shall install new 3 button wall stations.
3) A staging area will be determined by mutual agreement after contract award.
4) The following information is provided for bidding purposes only. The contractor is advised to conduct a site visit and field-verify the exact information required for use in completing the work and submitting an offer.
5) No asbestos or lead containing materials shall be used.
6) All work shall comply with codes and standards applicable to each type of work through the course of this project including the
National Electric Code (NFPA 70). Contractor shall also comply with the requirements of GSA Build Green Standards, and PBS P-100.
7) The Contractor is responsible for locating all utilities in project area, both public and private. GSA will make any existing drawing available for reference purposes only, actual locate is still contractor’s responsibility.
8) The contractor is responsible for the protection of all existing building property surfaces from damage due to work performed under this contract. Damages to existing surfaces caused by the performance of this contract shall be repaired as to match the existing surface finish at no additional cost to the Government.
9) The Contractor shall remove all debris generated in the performance of this contract daily.
10) The contractor shall take all necessary precautions to prevent any dust or debris from filtering into other parts of the building including but not limited to mechanical systems. Should dust or debris filter into other parts of the building the contractor shall take immediate steps to clean the area (no equipment or supplies will be furnished by GSA).
11) At the completion of the project, the project area shall be cleaned to building standards as determined by the GSA Property Manager. Should the contractor fail to clean the project limits in a timely manner, GSA will contract for said cleaning and the cost will be deducted from the contract. Ensure that all penetrations are sealed with fire rated approved material as required by the International Building Code.
12) The CO has the right to reject any unsatisfactory or unsuitable material or workmanship.
Section 6: Proposal Pricing & Site Walk
1) Pre-proposal Site Visit Meeting:
a) The site visit shall consist of a meeting to review construction requirements followed by a walk-thru of the project site.
The meeting shall be attended by the contractor and GSA project personnel, and appropriate sub-contractors.
b) Review existing conditions of the project area including any field verification.
c) Review the solicitation/evaluation requirements.
d) Bidders are to arrange a pre-proposal site visit by contacting the Property Manager.
2) Cost Proposal Requirements:
a) When submitting a proposal, provide a cost breakdown for each task into the following categories: Materials, equipment, labor hours, subcontractor's quotes, overhead, profit, and bond broken down into shell, tenant improvement (TI) (by tenant), Building- Specific Amortized Capital (BSAC), and environmental (as applicable). Follow P120 guidelines for tier level 3 based on project triage tool. Pricing shall be broken down by Construction Specification Institute (CSI) divisions.
b) Base Bid-
Section 7: Period of Performance Once notice to proceed has been issued, the contractor has 110 calendar days to complete the project. The contractor must also promptly begin the badging process at the time of notice to proceed. Please allow a minimum of 30 days to complete the badging process. Because this work will be located on a port of entry, the CBP may require the contractor to provide additional clearance information before work can begin on site. Extensions will be granted for unforeseen conditions and other factors outside of the contractor’s control at the Contracting Officer’s discretion.
Section 8: Universal Scope Requirements ALL of the requirements in this section are MANDATORY
● See the attached Universal Scope Requirements document for the full details outlining each item
● Failure to comply with any and all of the requirements will result in the project not being accepted as complete
Section 9: Submittals
1) Contractor shall submit a Method of Procedures (MOP) to the GSA Delivery Project Manager (PM) for approval prior to commencement of work. At a minimum, the MOP shall include:
a) Brief narrative describing method of accomplishment, construction techniques, etc
b) Project schedule (to include critical path, major milestones, long lead time items, mob & de-mob, inspection dates, substantial completion, and occupancy dates)
c) Service/Utility Outages (if necessary)
d) Phasing schedule (if necessary)
e) Any building infrastructure/BAS equipment that may be impacted.
2) All new equipment and anything requiring a preventative maintenance plan shall be inputted into Maximo upload template.
3) Submittals:
a) Manufacturer's specifications, instructions, and material specification sheets in original form
b) Shop drawings showing size and hardware locations
c) Warranty information
4) Submittal response by the government shall be (14) calendar days or less.
Section 10: General Requirements
1) Contractor Use of the Premises
a) During the period of the project, the contractor will have access to the site only during business hours of 7:00 am -5:00 pm, Monday through Friday. No on-site work shall be performed outside these hours or on holidays unless otherwise directed by the Contracting Officer. The contractor will need to coordinate with the Contracting Officer to arrange access to the parking lot. The contractor shall make every effort to cause a minimum of damage to parking lots, any other paved areas, any items that need to be moved during the course of the project, and any areas not included in this scope of work. Any damage caused will be repaired at the contractor’s expense.
b) Contractor to coordinate a staging area, if needed, with the building manager prior to mobilizing to the site.
2) Progress Meetings
a) Progress meetings are not required for this project. The project manager and building team representative shall make daily inspections of the work progress.
3) Equipment The contractor shall provide all equipment associated with the entire project, operate in a safe manner and adhere to all OSHA and GSA standards.
4) Equipment and Material Storage The contractor shall provide and store all equipment, the materials specified above, and any other materials required completing the project. The materials are required to be kept clean and dry throughout the duration of the project.
Contractor to coordinate with building manager for location of storage sheds.
5) Electricity, Water, and Gas GSA will pay for electricity, water, and gas during the course of this project. The contractor is responsible for making connections to the existing systems. Temporary electrical work shall meet the requirements of NFPA 70-1996 (NEC), Article
305. When temporary connections are removed, restore existing utility services to their original condition.
6) Fire Watch Contractor shall be responsible for providing fire watch if required per attached GSA fire watch guidelines.
7) Fire Alarm Impairment and Hot Work When a fire suppression or alarm system impairment is required, contractor shall provide written outage request to GSA for approval in advance of impairing any systems. Contractor shall be responsible for having a GSA approved NICET certified fire alarm contractor perform all system impairments. During fire alarm/suppression impairments or hot work procedures, contractor shall provide a fire watch per the GSA Regional Fire Watch Guidelines.
8) Protection of Public The building site will continue to be used by tenants. The contractor shall fence, barricade, or otherwise block off the immediate work area to prevent unauthorized entry. The contractor shall illuminate barricades and obstructions at night and maintain safe building access and egress for tenants.
9) Housekeeping The project site shall be kept in a neat, orderly, and safe condition at all times. The contractor shall provide enough containers for collecting construction debris and construction materials to be recycled. The contractor shall wet down dry materials and rubbish to prevent blowing dust and keep volatile wastes in covered containers.
10) Transportation and Deliveries The contractor shall arrange deliveries of materials in accordance with construction schedules; coordinate with COR to avoid conflict with other tenants and other work conditions at the site. Contractor must make GSA PM & CO aware of any lead times that may affect the project schedule.
11) Cleaning Before scheduling the final inspection, the Contractor shall accomplish six items: (1) Remove all tools, equipment, surplus material, and rubbish; (2) Restore or refinish, to original condition, surfaces that are damaged due to the work of this contract; (3) Remove grease, dirt, stains, foreign materials, and labels from finished surfaces; (4) Thoroughly clean building interiors; (5) Pickup all construction debris from the site; and (6) At time of final inspection, project shall be thoroughly cleaned and ready for use.
12) Disruptive Work All painting, staining, or other activity which may cause noxious or undesirable fumes and/ or any noisy work that may be disruptive to the tenants/ public must be performed after normal working hours. The use of paint or stain that does not generate odors is preferred and may be required if the space will be occupied the following day with prior written approval from GSA.
Section 11: Badging & Security
1) Contractor is responsible to follow GSA’s security and badging requirements as detailed at the time of contract award.
2) US Access shared enrollment centers can be found at fedidcard.gov. Travel distances to the nearest center should be accounted for during the badging process.
3) Any work on the Port of Entry grounds will require CBP clearance on each individual working on site. Contractor must complete a
CBP Short Term Contractor Information Sheet and receive an “all clear” prior to commencement of work.
Section 12: Payments
1) Information regarding payment requests and payment is in the solicitation/ contract. Please contact the CO if you have any questions regarding payments.
Section 13: Substantial Completion & Final Inspection
1) When project, or designated portion of project is complete, request a final inspection. Upon receipt of request that project is substantially complete, the Contracting Officer will proceed with the inspection within ten days of receipt of request or will advise the contractor of items that prevent the project from being designated substantially complete.
2) The contractor shall provide O&M manuals. The O&M manuals shall contain the following:
o Executed Warranties (at project completion) o Maintenance and operation manuals
Section 14: Attachments
1) Universal Scope requirements
2) 3in Energy Saver Specifications
PICTURES of Bldg B Doors
PICTURES of VACIS DOORS:
File details come from the government source that posted it. Updated .