Challis Pre-Built Shed Erection_SOW-8-13-20.doc
DOC document 12 MB Posted
- Attached to
- CHALLIS SHOP 2020 Federal contract opportunity
- Solicitation number
- 140L2520Q0048
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140L2520Q0048_Amd_0001.pdf | ||
| Appendix C - Sheeting _ Trim.pdf | ||
| Customers Parts List.pdf | ||
| Building Drawings from Supplier.pdf | ||
| Appendix E - Overhangs.pdf | ||
| Instruction Manual - Gable Buildings.pdf | ||
| Construction Package.pdf | ||
| Appendix D - Glossary.pdf | ||
| Sol_140L2520Q0048.pdf | ||
| Appendix A - Opening Framing.pdf | ||
| Appendix B - Framing Components.pdf | ||
| Wage Determination.pdf | ||
| Drawings eSigned.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work Challis Field Office Pre-Built Shed Erection Delivery Location:
Bureau of Land Management Challis Field Office 721 E. Main Ave. Suite 8
Challis, ID 83226 The Idaho Falls District - BLM intends to procure the services of a General Contractor to perform construction work at the Challis Field Office.
The Contractor shall perform the following construction services:
· Erect the Government supplied pre-engineered shed (Simply Tough Metal Buildings) according to the attached installation instructions onto a Government supplied 4” concrete slab.
1. Supplied pre-engineered shed parts are located on the project site on the supplied 4” concrete slab. (pictures located below)
2. No earthwork is scheduled for this contract.
· Purchase and install a 14’x14’ insulated garage door with chain hoist.
1. Overhead Door - Insulated Sectional Steel-Back Door 470.(or approved equal)
· Purchase and install a 3’ x 6’ 8” man door.
1. TRUDOOR – Flush Commercial Hollow metal door with Polystyrene Core.(or approved equal)
· Purchase and install manufacturer’s recommended insulation.
· Install anchor points into 4” concrete pad and secure building.
Service shall include: materials, labor, equipment, and installation.
Schedule of Items
| Item No. |
| Description |
| Unit |
| Unit Cost |
| Quantity |
| Total Cost |
| 1 |
| Assemble Pre-Engineered building, anchor installation, and all Appurtenances |
| LS |
Period of Performance: 30 Calendar Days From Issuance of Notice To Proceed
1. Pre-Engineered Shed Parts on Concrete Pad
2. Pre-Engineered Shed Parts on Concrete Pad
3. Project Location Challis, ID.
4. Project Location Challis, ID.
File details come from the government source that posted it. Updated .