Questions_-_Answers_0002.doc

DOC document 29 KB Posted

Attached to
PETE NEECE/MALLORY MASTICATION Federal contract opportunity
Solicitation number
140L3922Q0019
Issued by
Department of the Interior Bureau of Land Management Nevada Region

View the file

Other files for this federal contract opportunity

Other files attached to PETE NEECE/MALLORY MASTICATION, newest first.
File Type Posted
Map_0002.pdf PDF
mallory_pete_location_0002.pdf PDF
mallory_topo_0002.pdf PDF
Sol_140L3922Q0019_Amd_0002.pdf PDF
pete_aerial_0002.pdf PDF
mallory_air_0002.pdf PDF
Sol_140L3922Q0019_Amd_0001.pdf PDF
Bid_Schedule.docx DOCX document
A06_Maps.pdf PDF
A04_SOW.docx DOCX document
B03_Wage_Determination.pdf PDF
Sol_140L3922Q0019.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation Number 140L3922Q0019 Pete Neece/Mallory Mastication Questions & Answers

Q1) Are site visits able to be scheduled?

A1) Site visits are not being scheduled for the project. If more specific directions to the site are needed, we can provide them, but the maps are all geo-referenced and should be good for navigation.

Q2) Do you know if the terrain is clear or are there rock beds?

A2) Terrain may have some snow coverage right now. There are no rock beds, but may encounter a few larger rocks. Statement of Work, page 1, Section B. Work Layout states: “Some larger rocks are within the units but are minimal.”

Q3) Out of curiosity why is there a break from April to July?

A3) Statement of Work, page 2, Section D, Environmental Restrictions states: “Due to timing restrictions for sensitive resources, mastication will not occur from April 15 to July 15.” This is due to migratory bird nesting protection requirements.