CAT3221J_1201200002024022203164.pdf
PDF 11 KB Posted
- Attached to
- CONSOLE SHIP CONTROL Federal contract opportunity
- Solicitation number
- 70Z08024QAF046
About this file
This document is a solicitation for the overhaul of a ship control console. The United States Coast Guard Surface Forces Logistics Center requires inspection, reporting, and potential repair of one ship control console. National stock number is 2030-01-612-7381, part number is 60576, and original equipment manufacturer is Allied Systems Company. Quotes are due by February 28, 2024 at 0900 hours Eastern time and shall include separate line items for inspection cost and firm fixed repair price. Delivery is required by May 21, 2024 to the Coast Guard facility in Baltimore. The contract will be awarded to the lowest priced technically acceptable offer. The document outlines packaging and marking requirements, inspection and acceptance criteria, and various flow down clauses pertaining to equal employment, trafficking in persons, and other regulatory requirements.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Mil-Std 2073.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OVERHAUL DESCRIPTION
FOR OFFICIAL USE ONLY
ITEM NAME CONSOLE,SHIP CONTROL
STOCK NUMBER 2030-01-612-7381
PART NUMBER 60576
USED ON 210 WMEC
Items as received by the contractor must be complete and of the proper cited part number. Discrepancies shall be reported to the Coast Guard Contracting Officer.
OVERHAUL REQUIREMENTS:
This description covers the requirements for contractor inspection, estimate, and overhaul of the following cited SHIP CONTROL CONSOLE.
NSN: 2030-01-612-7381
Item Name: Console, Ship Control Part Number: 60576
Application: WMEC 210 Class Allied D5700CT Davit Assembly. Original Equipment Manufacturer: Allied Systems Company, Inc.
The contractor shall immediately notify the Coast Guard Contracting Officer if the make and/or model delivered for overhaul does not conform to the Ship Control Console cited above.
Requirements: The contractor shall provide all labor and materials to perform overhaul services on the Control Console as follows:
PRELIMINARY INSPECTION REOUIREMENTS:
Preliminary disassembly and inspection of the Control Console shall be conducted in accordance with Original Equipment Manufacturer (OEM) recommended procedures to determine the total estimated cost for repair including material, labor, testing, preservation, packing and marking costs.
A detailed estimate shall be submitted to the Coast Guard Contracting Officer (CG KO) for review and approval prior to the start of any repair or order of material. The estimate shall include: stock numbers, serial numbers, part numbers, new parts required with prices, labor rate, labor hours required, and a total estimate for all required services. The contractor shall also provide the replacement cost of a new Control Console for comparison to the overhaul cost. The CG KO shall determine the disposition of any Control Console delivered for inspection that is found to be not suitable for repair for whatever reason.
Upon acceptance of the estimate and authorization to proceed by the CG KO, the Control Console shall be overhauled in accordance with OEM recommended procedures and as follows:
OVERHAUL REQUIREMENTS:
Each Control Console shall be overhauled to a condition, which shall restore the operating and performance characteristics to the "ORIGINAL" design and technical specifications. Overhaul shall be performed in accordance with the original equipment manufacturer (OEM) specifications and standards. All repair parts shall be genuine OEM manufactured parts. All replacement parts used in the overhaul shall be new OEM parts or parts of equal or better quality. Reclaimed or recycled parts are not acceptable and shall not be used.
OUALITY ASSURANCE:
Following completion of overhaul, the contactor shall perform standard production tests and inspections to assure maximum design performance. The Contractor shall provide certifications of successful standard production tests and inspections. One certification shall be placed in the box with each unit and a copy for each unit shall be forwarded to the Coast Guard Contracting Officer.
Example of Marking Layout:
NATIONAL STOCK NUMBER: 2030-01-612-7381
ITEM NAME: Console, Ship Control
PART NUMBER: 60576
SERIAL NUMBER: as applicable GOVERNMENT ORDER NUMBER: as applicable DATE OF REPAIR: as applicable Coast Guard SFLC Material, Condition Code ?A".
SHELF LIFE CD 0
This description covers the requirements for contractor inspection, estimate, and overhaul of the following cited SHIP CONTROL CONSOLE.
NSN: 2030-01-612-7381
Item Name: Console, Ship Control Part Number: 60576
Application: WMEC 210 Class Allied D5700CT Davit Assembly. Original Equipment Manufacturer: Allied Systems Company, Inc.
The contractor shall immediately notify the Coast Guard Contracting Officer if the make and/or model delivered for overhaul does not conform to the Ship Control Console cited above.
Requirements: The contractor shall provide all labor and materials to perform overhaul services on the Control Console as follows:
PRELIMINARY INSPECTION REOUIREMENTS:
Preliminary disassembly and inspection of the Control Console shall be conducted in accordance with Original Equipment Manufacturer (OEM) recommended procedures to determine the total estimated cost for repair including material, labor, testing, preservation, packing and marking costs.
A detailed estimate shall be submitted to the Coast Guard Contracting Officer (CG KO) for review and approval prior to the start of any repair or order of material. The estimate shall include: stock numbers, serial numbers, part numbers, new parts required with prices, labor rate, labor hours required, and a total estimate for all required services. The contractor shall also provide the replacement cost of a new Control Console for comparison to the overhaul cost. The CG KO shall determine the disposition of any Control Console delivered for inspection that is found to be not suitable for repair for whatever reason.
Upon acceptance of the estimate and authorization to proceed by the CG KO, the Control Console shall be overhauled in accordance with OEM recommended procedures and as follows:
OVERHAUL REQUIREMENTS:
Each Control Console shall be overhauled to a condition, which shall restore the operating and performance characteristics to the "ORIGINAL" design and technical specifications. Overhaul shall be performed in accordance with the original equipment manufacturer (OEM) specifications and standards. All repair parts shall be genuine OEM manufactured parts. All replacement parts used in the overhaul shall be new OEM parts or parts of equal or better quality. Reclaimed or recycled parts are not acceptable and shall not be used.
OUALITY ASSURANCE:
Following completion of overhaul, the contactor shall perform standard production tests and inspections to assure maximum design performance. The Contractor shall provide certifications of successful standard production tests and inspections. One certification shall be placed in the box with each unit and a copy for each unit shall be forwarded to the Coast Guard Contracting Officer.
Example of Marking Layout:
NATIONAL STOCK NUMBER: 2030-01-612-7381
ITEM NAME: Console, Ship Control
PART NUMBER: 60576
SERIAL NUMBER: as applicable GOVERNMENT ORDER NUMBER: as applicable DATE OF REPAIR: as applicable Coast Guard SFLC Material, Condition Code ?A".
WARRANTY:
X A. Standard Manufacturer's Warranty
B. Item being repaired as an "onboard repair" or a "system stock" item and will be put into inventory. NOT FOR IMMEDIATE INSTALLATION.
Contractor must guarantee item against defects that lead to failure for days after installation for a period of up to two (2) years after delivery to Coast Guard.
GOVERNMENT ACCEPTANCE:
Acceptance will be made at destination by a Government representative.
Acceptance will be contingent upon the representative's verification of no damage in transit, correctness and completeness of order and contractor's conformance to preservation/packaging, packing and marking requirements.
OVERHAUL DESCRIPTION
PACKAGING AND MARKING FOR SHIPMENT:
X A. Each unit shall be packed individually in it's own wooden box which shall be capable of providing adequate protection to the item during multiple shipments. Mark each box in legible black print lettering with the following information:
NATIONAL STOCK NUMBER
ITEM NAME
PART NUMBER
GOVERNMENT ORDER NUMBER
2030-01-612-7381
CONSOLE,SHIP CONTROL
60576
PRESERVATION / PACKAGING:
X A. Each unit shall be individually preserved and wrapped for protection against deterioration for a period of two (2) years minimum.
B. See Attachments
B. See Attachments
And the words: "Coast Guard SFLC Material, Condition "A"
RECOMMENDED SOURCES:
ALLIED SYSTEMS COMPANY INC DBA ALLI
21433 SW OREGON ST
SHERWOOD, OR 97140-9769
KELLY.WILSON@ALLIEDSYSTEMS.COM
503-825-3426
WRITTEN BY:
DATE :
MARK LOVINGOOD
22 FEB 24
Cost Estimate for Overhaul NOT TO EXCEED: $45,616.64