This document is a sole source justification form completed for a contract award. The Mid-Atlantic Regional Council on the Ocean (MARCO) launched the Mid-Atlantic Ocean Data Portal in 2012 to support development and implementation of the Mid-Atlantic Ocean Plan. The Portal has become a critical resource for the Bureau of Ocean Energy Management (BOEM) for environmental analyses and sharing products. BOEM contributed data to the portal. The contract was awarded on April 29, 2022 to Coastal States Stewardship Foundation for an unknown amount to periodically assess future needs and requirements and review commercial alternatives, as none currently exist. The period of performance is until October 21, 2021. The contracting office is located in Sterling, Virginia.
View the file
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Department of the Interior Bureau of Safety and Environmental Enforcement
SOLE SOURCE JUSTIFICATION
FAR Subpart 13.5 - For Certain Commercial Items
(Mandatory for Acquisitions > SAT) (Optional for Acqs. ≤ SAT)
1. Bureau and Contracting Activity [FAR 13.501(a)(1)(ii) and 6.303-2(b)(1)]
2. Description of Supplies or Services [FAR 13.501(a)(1)(ii) and 6.303-2(b)(3)]
3. Requisition No.
4. Cost Estimate (including options)[FAR 6.303-2(b)(3)]
5. Name of Proposed Source(s)
6. REQUESTING OFFICE CERTIFICATION
I certify that this recommendation contains the information required by FAR 13.501(a)(1)(ii) and 6.303-2(b) and its contents are accurate.
Date:Phone No:Signature:Requesting Office Rep. (Name &Title)
7. ACQUISITION OFFICE CERTIFICATION
I certify that this justification is accurate and complete to the best of my knowledge and belief.
Signature: Phone No: Date:Contracting Officer (Name)
Identify the authority being used to justify a sole source acquisition [FAR 13.501(a)(1)(ii)]. Refer to block number 10 for justification details.
8. Section 4202 of the Clinger-Cohen Act of 1996 .
9. 41 U.S.C. 428a - Services Acquisition Reform Act of 2003.
10. JUSTIFICATION (Attach additional pages if needed)
(a) Demonstration that the proposed contractor's unique qualifications or the nature of the acquisition requires use of the authority cited [FAR 6.303-2(b)(5)]. [Prepared by Program Office]
(b) Describe the efforts taken to ensure offers were solicited from as many potential sources as is practicable, including whether a Government-wide point of entry (GPE) notice was or will be published as required by FAR 5.2 and, if not, which exception under FAR
5.202 applies. [FAR 6.303-2(b)(6)]. [Prepared by Program Office]
10. JUSTIFICATION CONTINUED (Attach additional pages if needed)
(c) Demonstration that the anticipated cost to the Government will be fair and reasonable [FAR 6.303-2(b)(7)]. [Prepared by Contracting Officer]
(d) Describe the market research conducted and the results or a statement of the reason market research was not conducted. [FAR 6.303-2(b)(8)]. [Initiated by the Program Office and finalized in collaboration with the Contracting Officer]
10. JUSTIFICATION CONTINUED (Attach additional pages if needed)
(e) Any other facts supporting the use of a sole source acquisition. [FAR 6.303-2(b)(9)]. [Prepared by Program Office]
(f) List sources, if any, that expressed, in writing, an interest in the acquisition. [FAR 6.303-2(b)(10)]. [Prepared by Program Office]
(g) Statement of the actions, if any, the agency may take to remove or overcome any barriers that led to competition before any subsequent acquisition for supplies and services. [FAR 6.303-2(b)(11)] [Initiated by the Program Office and finalized in collaboration with the Contracting Officer]
APPROVALS [FAR 6.304]
12. Competition Advocate (Name & Title)
APPROVE
DISAPPROVE
(Phone No.)
(Date)
13. Head of the Contracting Activity (Name & Title)
(Date)
(Phone No.)
(Signature)
(Signature)
(Signature)
APPROVE
DISAPPROVE
14. Departmental Senior Procurement Executive (Name & Title) APPROVE
DISAPPROVE
(Phone No.)
(Date)
O ve r $7
,0
O ve r
$1 m ill io n
O ve r $7 m ill io n
(Signature)11. Chief of the Contracting Office (Name & Title)
APPROVE
DISAPPROVE
(Phone No.)
(Date)O ve r
SA
T
INSTRUCTIONS FOR COMPLETING FORM
Block No.
Identify Bureau initiating the requirement and Acquisition Office processing the requirement.
- Bureau of Safety and Environmental Enforcement (BSEE), or Bureau of Ocean Energy Management (BOEM)
- Acquisition Operations Branch - Headquarters, or Acquisition Operations Branch - NOLA
Provide a clear, concise description of the product(s) and/or service(s) to be procured, including the delivery schedule and/or the period of performance (including all option periods). Always include the estimated value in Section 4 below.
This provides the reviewing and approving official with a better understanding of the scope, magnitude, and complexity of the requirement.
4 Include all applicable options and system life-cycle costs.
Include more than one source as a proposed vendor. For example, if the procurement is based on an urgent need, you must still contact as many potential sources as is practicable unless the justification for urgency contains detailed documentation to show that it is not practicable under the circumstances to solicit additional sources.
6 & 7 Obtain certification from the requesting office and contracting officer prior to submitting for approval.
8-9 Check the box next to the justifying authority. Only one authority can be cited.
10(a)
Provide an explanation of the contractor's unique qualifications or the nature of the acquisition that requires the use of the statutory authority cited. This is the most important part of the justification because it demonstrates that the prospective contractor has unique qualifications and/or specialized capabilities or expertise that is not prevalent in the marketplace. Also, explain what unique qualifications and special capabilities the contractor possesses. Unique qualifications and expertise is defined as knowledge that is currently very limited within the marketplace; there is only one company or individual that has the expertise to provide the product or perform the required services.
10(b)
If the requirement was not publicized, explain why it was not publicized. When an acquisition contains brand name specifications, the contracting officer shall include with the solicitation the justification or required documentation. See FAR 5.102(a) (6) for the requirement to post the brand name justification. The justification should normally be prepared after the requirements notification is posted on Federal Business Opportunities, to allow the requirements office an opportunity to examine the results of industry inquiries and reach a conclusion concerning the potential degree of competition. If the justification is staffed prior to satisfying the synopsis requirement, state the reasons why this was done after the justification was processed. This paragraph should provide a description of the type of action, i.e., purchase and/or delivery order, task orders, and estimated quantities. This section should also include a description of the efforts by the program office and contracting office to ensure that offerors are solicited from as many potential sources as possible.
10(c)
Provide a narrative of the measures performed by the contracting officer to ensure that the costs and/or prices will be fair and reasonable before negotiations commence. In addition, provide the methodology used in the market research analysis that supports a determination of fair and reasonable costs/prices. Provide any information, such as commercial pricelists or prior acquisition history that will help the contracting officer determine that the anticipated cost is fair and reasonable.
INSTRUCTIONS FOR COMPLETING FORM
Block No.
10(d)
Issuance of a synopsis as required in FAR Part 5 does not satisfy the requirement to conduct a market survey. A survey can include announcements in trade journals or telephone surveys with interested/knowledgeable individuals in or out of government. Market research requires collecting and analyzing product/service information on the technical capabilities and prices/costs within the marketplace to satisfy agency needs. If market research was not conducted, the reasons it was not conducted should be stated. Since this is a sole source acquisition, the only possible way to state that there is only one contractor who can fulfill the agency's needs, is to conduct market research and it must be summarized here.
10(e)
Explanation of why technical data packages, specifications, engineering descriptions, statements of work, or purchase descriptions suitable for full and open competition have not been developed or are not available.
-When FAR 6.301-2 is cited for follow-on acquisitions as described in 6.302-1(a) (2) (ii), an estimate of the cost to the Government that would be duplicated and how the estimate was derived.
-When FAR 6.302-2 is cited, data, estimated cost, or other rationale as to the extent and nature of the harm to the Government.
10(f)
Include a listing of the sources that expressed written interest in the acquisition. If applicable, clearly state "To date, no other sources have expressed an interest in writing." [Also state that the notices required by FAR 5.201 shall be/have been published and any proposals received shall be considered. If a FedBizOpps notice will not be published, state which exception in FAR 5.202 applies.
10(g)
Describe actions taken, or that will be taken, to remove or overcome any barriers to competition before any subsequent acquisitions for the item/service or brand name item(s), including challenges to restrictive data markings, data rights, preparation of a performance based work statement, etc. If planning a competition, include the estimated date when the competitive procurement will occur. If competition is not planned, state so and provide the appropriate justification. Include written responses to synopsis announcements and other expressions of interest. All responses must be addressed prior to the approval of the justification. State the reasons why it is sole source. If this is a follow-on procurement, state the measures initiated to eliminate or reduce competitive barriers.
11-14 If any person required to sign-in these blocks does not approve, the procurement shall not proceed any further and the justification shall be returned to the requisitioner through the contracting officer. All signatures required on the form (as applicable to the particular acquisition) must appear in order for the procurement to proceed.
Department of the Interior Bureau of Safety and Environmental Enforcement
SOLE SOURCE JUSTIFICATION
FAR Subpart 13.5 - For Certain Commercial Items (Mandatory for Acquisitions > SAT)(Optional for Acqs. ≤ SAT)
1. Bureau and Contracting Activity [FAR 13.501(a)(1)(ii) and 6.303-2(b)(1)]
2. Description of Supplies or Services [FAR 13.501(a)(1)(ii) and 6.303-2(b)(3)]
3. Requisition No.
4. Cost Estimate (including options)[FAR 6.303-2(b)(3)]
5. Name of Proposed Source(s)
6. REQUESTING OFFICE CERTIFICATION
I certify that this recommendation contains the information required by FAR 13.501(a)(1)(ii) and 6.303-2(b) and its contents are accurate.
Date:
Phone No:
Signature:
Requesting Office Rep. (Name &Title)
7. ACQUISITION OFFICE CERTIFICATION
I certify that this justification is accurate and complete to the best of my knowledge and belief.
Signature:
Phone No:
Date:
Contracting Officer (Name) Identify the authority being used to justify a sole source acquisition [FAR 13.501(a)(1)(ii)]. Refer to block number 10 for justification details.
8. Section 4202 of the Clinger-Cohen Act of 1996 .
9. 41 U.S.C. 428a - Services Acquisition Reform Act of 2003.
10. JUSTIFICATION (Attach additional pages if needed)
(a) Demonstration that the proposed contractor's unique qualifications or the nature of the acquisition requires use of the authority cited [FAR 6.303-2(b)(5)]. [Prepared by Program Office]
(b) Describe the efforts taken to ensure offers were solicited from as many potential sources as is practicable, including whether a Government-wide point of entry (GPE) notice was or will be published as required by FAR 5.2 and, if not, which exception under FAR 5.202 applies. [FAR 6.303-2(b)(6)]. [Prepared by Program Office]
10. JUSTIFICATION CONTINUED (Attach additional pages if needed)
(c) Demonstration that the anticipated cost to the Government will be fair and reasonable [FAR 6.303-2(b)(7)]. [Prepared by Contracting Officer]
(d) Describe the market research conducted and the results or a statement of the reason market research was not conducted. [FAR 6.303-2(b)(8)]. [Initiated by the Program Office and finalized in collaboration with the Contracting Officer]
12. JUSTIFICATION CONTINUED (Attach additional pages if needed)
(d) Statement of the actions, if any, the agency may take to remove or overcome any barriers that led to restricted consideration before any subsequent acquisition for supplies and services is made [FAR 8.405-6(c)(2)(viii)] [Initiated by the Program Office and finalized in collaboration with the Contracting Officer]
(e) Any other facts supporting the justification [FAR 8.405-6(c)(2)(vii)] [Prepared by the Program Office and Contracting Officer] APPROVALS [FAR 8.405-6(d)]
16. Competition Advocate (Name & Title) (Phone No.)
(Date)
17. Head of the Contracting Activity (Name & Title) (Date) (Phone No.)
(Signature) (Signature) (Signature)
18. Departmental Senior Procurement Executive (Name & Title) (Phone No.)
(Date) Over $650,000 Over $12.5 million Over $62.5 million
10. JUSTIFICATION CONTINUED (Attach additional pages if needed)
(e) Any other facts supporting the use of a sole source acquisition. [FAR 6.303-2(b)(9)]. [Prepared by Program Office]
(f) List sources, if any, that expressed, in writing, an interest in the acquisition. [FAR 6.303-2(b)(10)]. [Prepared by Program Office]
(g) Statement of the actions, if any, the agency may take to remove or overcome any barriers that led to competition before any subsequent acquisition for supplies and services. [FAR 6.303-2(b)(11)] [Initiated by the Program Office and finalized in collaboration with the Contracting Officer]
INSTRUCTIONS FOR COMPLETING FORM
Block No.
Identify Bureau initiating the requirement and Acquisition Office processing the requirement.
- Bureau of Safety and Environmental Enforcement (BSEE), or Bureau of Ocean Energy Management (BOEM)
- Acquisition Operations Branch - Headquarters, or Acquisition Operations Branch - NOLA Provide a clear, concise description of the product(s) and/or service(s) to be procured, including the delivery schedule and/or the period of performance (including all option periods). Always include the estimated value of the order or BPA in Section 4 below. This provides the reviewing and approving official with a better understanding of the scope, magnitude, and complexity of the requirement.
Include all applicable options and system life-cycle costs.
Include more than one source as a proposed vendor, unless you are citing FAR 8.405-6(a)(1)(i)(B). For example, if the procurement is based on unusual and compelling need, you must still contact as many potential sources as is practicable unless the justification for urgency contains detailed documentation to show that it is not practicable under the circumstances to solicit additional sources.
6 & 7 Obtain certification from the requesting office and contracting officer prior to submitting for approval.
8-11 Check the box next to the justifying authority. Only one authority can be cited.- Include an explanation of the contractor's unique qualifications, the nature of the acquisition that requires the use of the same vendor as part of a logical follow on, or the reasons for urgency and an explanation of how using the procedures would result in unacceptable delays. This is the most important part of the LSJ because it demonstrates that the prospective contractor has unique qualifications and/or specialized capabilities or expertise that is not prevalent elsewhere on the schedules. If the order contains a brand name specification, the ordering activity must show evidence that the Request for Quotation and the following information was posted on GSA e-Buy. You must explain what unique qualifications and special capabilities the vendor possesses.
- When FAR 8.405-6 (a)(1)(i))(A) is cited, provide data, estimated cost, or other rationale as to the extent and nature of the harm to the government following schedule procedures would cause.- When an urgent or compelling need exists, discuss the nature of the urgency. Discuss how any follow-on work will be competed (mandatory). Also, provide supporting rationale and a concise description of the extent, nature, and impact of the unacceptable delay.- When FAR 8.405-6 (a)(1)(i)(C) is cited for logical follow on, include an estimate of the duplicative cost and methodology used to formulate the estimated cost.- The justification on pages 3 and 4 must be clear and concise as to how the cited authority is related to the acquisition.- When applicable, include documentation that demonstrates the prospective vendor's unique qualifications to provide the required supply of service.
12(a) Describe the type of action being issued, e.g., Federal Supply Schedule (FSS) order or blanket purchase agreement (BPA) for supplies, services not requiring a statement of work, or services that require a statement of work. Also, identify the contemplated contract type, i.e. firm fixed price, time and materials, etc. Provide sufficient information so the reviewer clearly understands the proposed approach under consideration.
12(b) The Contracting officer needs to determine, after considering the level of effort and the mix of skills available for the tasks needed, that the proposed order or BPA represents a reasonable total price and will be the best value for the government. Include explanation of what techniques will be used to determine prices fair and reasonable.
APPROVALS [FAR 6.304]
12. Competition Advocate (Name & Title) (Phone No.)
(Date)
13. Head of the Contracting Activity (Name & Title) (Date) (Phone No.)
(Signature) (Signature) (Signature)
14. Departmental Senior Procurement Executive (Name & Title) (Phone No.)
(Date) Over $750,000 Over $15 million Over $75 million (Signature)
11. Chief of the Contracting Office (Name & Title) (Phone No.)
(Date) Over
SAT
INSTRUCTIONS FOR COMPLETING FORM
Block No.
12(c) Market research requires collecting and analyzing product/service information on the technical capabilities and prices/costs from appropriate FSS contracts. If market research was not conducted, the reasons why it was not conducted should be stated.
If above the SAT, a copy of the proposed LSJ prepared in accordance with this guide; if an exception permitted by 8.405-6(b)(3)(ii) exists, documentation of the exception should be provided here in lieu of the E-buy posting.
12(d) Describe actions taken, or that will be taken, to remove or overcome any barriers to competition before any subsequent acquisitions for the supplies or services required, including challenges to restrictive data markings, data rights, preparation of a performance based work statement, etc. If planning a competition, include the estimated date when the competitive procurement will occur. If this is a follow-on order, state the measures initiated to eliminate or reduce competitive barriers.] 12(e) Provide any additional documents that will support the justification.
INSTRUCTIONS FOR COMPLETING FORM
Block No.
Identify Bureau initiating the requirement and Acquisition Office processing the requirement.
- Bureau of Safety and Environmental Enforcement (BSEE), or Bureau of Ocean Energy Management (BOEM)
- Acquisition Operations Branch - Headquarters, or Acquisition Operations Branch - NOLA Provide a clear, concise description of the product(s) and/or service(s) to be procured, including the delivery schedule and/or the period of performance (including all option periods). Always include the estimated value in Section 4 below. This provides the reviewing and approving official with a better understanding of the scope, magnitude, and complexity of the requirement.
Include all applicable options and system life-cycle costs.
Include more than one source as a proposed vendor. For example, if the procurement is based on an urgent need, you must still contact as many potential sources as is practicable unless the justification for urgency contains detailed documentation to show that it is not practicable under the circumstances to solicit additional sources.
6 & 7 Obtain certification from the requesting office and contracting officer prior to submitting for approval.
8-9 Check the box next to the justifying authority. Only one authority can be cited.
10(a) Provide an explanation of the contractor's unique qualifications or the nature of the acquisition that requires the use of the statutory authority cited. This is the most important part of the justification because it demonstrates that the prospective contractor has unique qualifications and/or specialized capabilities or expertise that is not prevalent in the marketplace. Also, explain what unique qualifications and special capabilities the contractor possesses. Unique qualifications and expertise is defined as knowledge that is currently very limited within the marketplace; there is only one company or individual that has the expertise to provide the product or perform the required services.
10(b) If the requirement was not publicized, explain why it was not publicized. When an acquisition contains brand name specifications, the contracting officer shall include with the solicitation the justification or required documentation. See FAR 5.102(a) (6) for the requirement to post the brand name justification. The justification should normally be prepared after the requirements notification is posted on Federal Business Opportunities, to allow the requirements office an opportunity to examine the results of industry inquiries and reach a conclusion concerning the potential degree of competition. If the justification is staffed prior to satisfying the synopsis requirement, state the reasons why this was done after the justification was processed. This paragraph should provide a description of the type of action, i.e., purchase and/or delivery order, task orders, and estimated quantities. This section should also include a description of the efforts by the program office and contracting office to ensure that offerors are solicited from as many potential sources as possible.
10(c) Provide a narrative of the measures performed by the contracting officer to ensure that the costs and/or prices will be fair and reasonable before negotiations commence. In addition, provide the methodology used in the market research analysis that supports a determination of fair and reasonable costs/prices. Provide any information, such as commercial pricelists or prior acquisition history that will help the contracting officer determine that the anticipated cost is fair and reasonable.
INSTRUCTIONS FOR COMPLETING FORM
Block No.
10(d) Issuance of a synopsis as required in FAR Part 5 does not satisfy the requirement to conduct a market survey. A survey can include announcements in trade journals or telephone surveys with interested/knowledgeable individuals in or out of government. Market research requires collecting and analyzing product/service information on the technical capabilities and prices/costs within the marketplace to satisfy agency needs. If market research was not conducted, the reasons it was not conducted should be stated. Since this is a sole source acquisition, the only possible way to state that there is only one contractor who can fulfill the agency's needs, is to conduct market research and it must be summarized here.
10(e) Explanation of why technical data packages, specifications, engineering descriptions, statements of work, or purchase descriptions suitable for full and open competition have not been developed or are not available.
-When FAR 6.301-2 is cited for follow-on acquisitions as described in 6.302-1(a) (2) (ii), an estimate of the cost to the Government that would be duplicated and how the estimate was derived.
-When FAR 6.302-2 is cited, data, estimated cost, or other rationale as to the extent and nature of the harm to the Government.
10(f) Include a listing of the sources that expressed written interest in the acquisition. If applicable, clearly state "To date, no other sources have expressed an interest in writing." [Also state that the notices required by FAR 5.201 shall be/have been published and any proposals received shall be considered. If a FedBizOpps notice will not be published, state which exception in FAR 5.202 applies.
10(g) Describe actions taken, or that will be taken, to remove or overcome any barriers to competition before any subsequent acquisitions for the item/service or brand name item(s), including challenges to restrictive data markings, data rights, preparation of a performance based work statement, etc. If planning a competition, include the estimated date when the competitive procurement will occur. If competition is not planned, state so and provide the appropriate justification. Include written responses to synopsis announcements and other expressions of interest. All responses must be addressed prior to the approval of the justification. State the reasons why it is sole source. If this is a follow-on procurement, state the measures initiated to eliminate or reduce competitive barriers.
11-14 If any person required to sign-in these blocks does not approve, the procurement shall not proceed any further and the justification shall be returned to the requisitioner through the contracting officer. All signatures required on the form (as applicable to the particular acquisition) must appear in order for the procurement to proceed.
JOFOC
| PrintButton1: |
| ResetButton1: |
| TextField1: The U.S. Department of the Interior, Bureau of Safety and Environmental Enforcement/Acquisition Operations Branch, on behalf of the Bureau of Ocean Energy Management. |
| TextField1: The Mid-Atlantic Regional Council on the Ocean (MARCO) launched the Mid-Atlantic Ocean Data Portal in 2012 to support development and implementation of the Mid-Atlantic Ocean Plan. The Portal is a centralized, peer-reviewed source of data and interactive maps of the ocean ecosystem and ocean-related human activities in the mid-Atlantic of the United States. BOEM has contributed to this portal through providing data sources available through the portal. The Portal has become a critical resource used by BOEM as a source of data for environmental analyses and a location to share products. This is a new requirement. |
| TextField2: 0040551204 |
| TextField2: -------------- |
| TextField2: Coastal States Stewardship Foundation |
| DateTimeField1: 2021-10-07 |
| DateTimeField1: 2021-10-12 |
| TextField3: (703) 787-1635 |
| TextField3: Stephen Creed |
| TextField3: Cheryl Perdue |
| TextField3: (703)-787-1432 |
| Button1: |
| CheckBox1: 0 |
| CheckBox2: 0 |
| TextField4: The Coastal States Stewardship Foundation is only source capable to meet the Government's Requirements. A pre-solicitation notice (Special Notice of Intent to Sole Source) will be issued via Sam.gov announcing the Government’s intent to solicit and negotiate with a sole source. Therefore, the notice will be issued in accordance with the Federal Acquisition Regulation (FAR) Subpart 5.2, Synopses of Proposed Contract Actions. |
| TextField4: The Coastal States Stewardship Foundation is a partner and facilitator of the The Mid-Atlantic Regional Council on the Ocean (MARCO) portal and is designated to receive Government awards to procure Support for the The Mid-Atlantic Regional Council on the Ocean (MARCO) portal. Correspondingly, the Government has determined that no vendor, other than the Coastal States Stewardship Foundation, can receive award necessary for the administrative and management support to the The Mid-Atlantic Regional Council on the Ocean (MARCO) Portal without disrupting operational functions of and causing unreasonable delays to the Government. This is a new requirement. |
| TextField4: This is a new requirement, however, there have been three (3) sole source awards similar to this requirement for the Northeast Ocean Data Portal that was awarded to Coastal States Stewardship Foundation and based on firm-fixed-pricing determined to be fair and reasonable. The current acquisition will be based on firm-fixed-pricing (this contract type places upon the contractor maximum risk and full responsibility for all costs and resulting profit or loss) and the firm-fixed-pricing will be compared with the firm-fixed-pricing of past acquisitions. |
| TextField4: The past three (3) similar sole source awards (140M0118P0042, 140M0119P0031 and 140M0120P0029), for the Northeast Ocean Data Portal (Portal), were awarded to Coastal States Stewardship Foundation, in which the Government's Requirements can only be met by a sole source. This acquisition will be conducted in accordance with the FAR Subpart 13.5 - Simplified Procedures for Certain Commercial Items. The Contracting Officer’s Representative provided information supporting the sole source nature of the Government's Requirements as documented in the Sole Source Justification prepared in accordance with the FAR Subpart 13.5. The historical data available for the Government's Requirements provide enough information to be able to rule out either setting the Government's Requirements aside for the participation of small businesses in a solicitation or soliciting only to GSA Schedule Contractors, since only one source can provide the service. |
| TextField4: The Mid-Atlantic Regional Council on the Ocean (MARCO) has funds management partnership with the Coastal States Stewardship Foundation that is, by default, the recipient of the funding and the identified and capable sole source. If the Government were to choose another vendor, there may be substantial costs incurred to re-establish the support function with another vendor and the delivery of critical services from the Northeast Ocean Data Portal may be delayed. The Coastal States Stewardship Foundation has previously exhibited a timely and high quality performance in the management and maintenance support for the Northeast Ocean Data Portal. |
| TextField4: To date: No other source have expressed, in writing, an interest in meeting the Government's Requirements nor this sole source acquisition. |
| TextField4: The Government will periodically reassess its future needs and requirements and review the market place for viable commercial sources and alternatives. At this time, no commercial sources and alternatives exist. |
| TextField5: |
| CheckBox3: 0 |
| CheckBox3: 0 |
| CheckBox3: 0 |
| CheckBox3: 0 |
| CheckBox3: 0 |
| CheckBox3: 0 |
| CheckBox3: 1 |
| CheckBox3: 0 |
| CheckBox3: 0 |
| CheckBox3: 0 |
| CheckBox3: 0 |
| CheckBox3: 0 |
| CheckBox3: 1 |
| CheckBox3: 0 |
| DateTimeField2: 2021-10-21 |
| DateTimeField2: 2021-10-21 |
| TextField6: (703) 787-1324 |
| TextField6: (703)787-1828 |
| TextField7: Douglas M. Marr |
Chief, Acquisition Management Division TextField7: Rebecca L. Kruse Chief, Acquisition Operations Branch
File details come from the government source that posted it. Updated .