Burley_Fire_Bldg_Spec.pdf

PDF 174 KB Posted

Attached to
Burley Fire Office Painting Federal contract opportunity
Solicitation number
140L0723Q0017
Issued by
Department of the Interior Bureau of Land Management

About this file

This document provides specifications for interior painting services at the Burley Fire Office in Burley, Idaho. The project includes painting interior office space walls, ceilings, door frames and windowsills. Products required include Sherwin-Williams Emerald Interior Latex Satin or approved equal for walls and ceilings, and Sherwin-Williams Emerald Urethane Trim Enamel Semi-gloss or approved equal for metal surfaces. Contractors must be licensed and certified to perform painting services in Idaho and must follow manufacturer specifications for applying two coats of each product. Color samples must be approved by the contracting officer before work begins.

View the file

Other files for this federal contract opportunity

Other files attached to Burley Fire Office Painting, newest first.
File Type Posted
General_Decision_ID20230022_8-4-23.docx DOCX document
BURLEY_Fire_Bldg_Painting_2023.pdf PDF
Sol_140L0723Q0017.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BURLEY FIRE OFFICE PAINTING

SPECIFICATION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

011000....... SUMMARY

012700....... UNIT PRICES AND SCHDULE OF VALUES

013100....... PROJECT MANAGEMENT AND COORDINATION

013200....... CONSTRUCTION PROGRESS DOCUMENTATION

013300....... SUBMITTAL PROCEDURES

014000....... QUALITY REQUIREMENTS

014200....... REFERENCES

016000....... PRODUCT REQUIREMENTS

017000....... EXECUTION REQUIREMENTS

017700....... CLOSEOUT PROCEDURES

DIVISION 09 - FINISHES

099123....... INTERIOR PAINTING ……

END OF TABLE OF CONTENTS

MAY 2023

BURLEY FIRE OFFICE

TABLE OF CONTENTS

TOC-1

SUMMARY

011700-1

SECTION 011000 - SUMMARY

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes the following:

1. Work covered by the Contract Documents.

2. Use of premises.

3. Specification formats and conventions.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Identification: Burley Fire Office

1. Project Location: 3562 Overland Ave., Burley, Cassia County, Idaho

B. The Work consists of the following:

1. Painting of the interior office space walls, ceilings, door frames and windowsills.

C. Project will be completed under a single prime contract.

1.3 USE OF PREMISES

A. Contractor shall have full use of premises for construction operations, including use of Project site, during construction period. Contractor's use of premises is limited only by Government right to perform work or to retain other contractors on portions of Project.

B. Schedule operations so that Work is conducted during regular office hours which are 7:00 am to

5:00 pm.

C. Schedule and sequence operations necessary to complete the work, including coordination with the government relative to the Contractor's requirements. Schedule Work in such manner as to avoid delays in overall construction and permit proper installation of work.

D. Use of Site: Limit use of premises to work in areas indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.

SUMMARY

011700-2

1.4 SPECIFICATION FORMATS AND CONVENTIONS

A. Specification Format: The Specifications are organized into Divisions and Sections using the 33-division format and CSI/CSC's "MasterFormat" numbering system.

1. Division 1: Sections in Division 1 govern the execution of the Work of all Sections in the

Specifications.

B. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.

These conventions are as follows:

1. Abbreviated Language: Language used in the Specifications and other Contract Documents is abbreviated. Words and meanings shall be interpreted as appropriate. Words implied, but not stated, shall be inferred as the sense requires. Singular words shall be interpreted as plural, and plural words shall be interpreted as singular where applicable as the context of the Contract Documents indicates.

2. Imperative mood and streamlined language are generally used in the Specifications.

Requirements expressed in the imperative mood are to be performed by Contractor.

Occasionally, the indicative or subjunctive mood may be used in the Section Text for clarity to describe responsibilities that must be fulfilled indirectly by Contractor or by others when so noted.

a. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

C. Terminology: In Divisions 2 through 33 specifications sections, all references to “Owner” have been replaced with the term “Government” or “Contracting Officer” (when referring to the person acting for the government). All references to “Architect” have been replaced with the term “Contracting Officer”.

D. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the work of all Sections in the Specifications.

E. Contract Times: “Days” referred to in the Specifications are defined as calendar days.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 011000

UNIT PRICES AND SCHEDULE OF VALUES

012700-1

SECTION 012700 - UNIT PRICES AND SCHEDULE OF VALUES

A. This Section includes administrative and procedural requirements for unit prices and requirements to prepare schedule of values.

1.2 PROCEDURES

A. Unit prices include all necessary material, plus cost for delivery, installation, insurance, applicable taxes, overhead, and profit.

B. Government reserves the right to reject Contractor's measurement of work-in-place that involves use of established unit prices and to have this work measured, at Government expense, by an independent surveyor acceptable to Contractor.

C. List of Unit Prices: A list of unit prices is included in Part 3. Specification Sections referenced in the schedule contain requirements for materials described under each unit price.

1.3 SCHEDULE OF VALUES

A. Coordination: Coordinate preparation of the Schedule of Values with preparation of Contractor's Construction Schedule.

1. Correlate line items in the Schedule of Values with other required administrative forms and schedules, including Contractor's Construction Schedule.

2. Submit the Schedule of Values to Contracting Officer at earliest possible date but no later than ten calendar days after the Notice to Proceed.

B. Format and Content: Use the Project Manual table of contents as a guide to establish line items for the Schedule of Values. Provide at least one line item for each Specification Section.

1. Identification: Include the following Project identification on the Schedule of Values:

a. Project name and location.

b. Name of Contracting Officer.

c. Contractor's name and address.

d. Date of submittal.

2. Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation of Applications for Payment and progress reports. Coordinate with the Project Manual table of contents. Provide several line items for principal subcontract amounts, where appropriate.

3. Round amounts to nearest whole dollar; total shall equal the Contract Sum.

012700-2

4. Provide a separate line item in the Schedule of Values for each part of the Work where Applications for Payment may include materials or equipment purchased or fabricated and stored, but not yet installed.

5. Provide separate line items in the Schedule of Values for initial cost of materials, for each subsequent stage of completion, and for total installed value of that part of the Work.

6. Each item in the Schedule of Values and Applications for Payment shall be complete.

Include total cost and proportionate share of general overhead and profit for each item.

a. Temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown either as separate line items in the Schedule of Values or distributed as general overhead expense, at Contractor's option.

7. Schedule Updating: Update and resubmit the Schedule of Values before the next

Applications for Payment when Modifications result in a change in the Contract Sum.

PART 3 - EXECUTION

3.1 LUMP SUM PAYMENT ITEMS

A. Payment items for the work of this Contract for which contract lump sum payments will be made are listed in the BIDDING SCHEDULE and described below.

B. All costs for items of work, which are not specifically mentioned to be included in a particular lump sum or unit price payment item, shall be included in the listed lump sum item most closely associated with the work involved.

C. The lump sum price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

012700-3

3.2 SUMMARY OF BID ITEMS

A. The intent of the following paragraphs is to explain, in general, what is and what is not included in a bid item, and the limits or cut-off points where one bid item ends, and another begins. If no bid item exists for a portion of the work, include the costs in a related bid item.

B. BID ITEM 0001A – INTERIOR OFFICE SPACE PAINTING: This item includes all preparatory work and operations, including those necessary to the movement of personnel, equipment, supplies and incidentals to the project site; bonds, work layout; other work and operations which must be performed, or costs incurred prior to beginning work on the various items on the project site. Bid breakdown will include interior surface paining, interior metal door casings painting, and interior wood window seals painting. It will be paid for as a lump sum.

END OF SECTION 012700

MAY 2023 PROJECT MANAGEMENT AND COORDINATION

BURLEY FIRE OFFICE 013100-4

SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION

A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. Coordination Drawings.

2. Project meetings.

3. Requests for Interpretation (RFIs).

1.2 COORDINATION

A. Coordination: Coordinate construction operations with the government to ensure efficient and orderly installation of each part of the Work.

1. Schedule construction operations in sequence required to obtain the best quality results.

2. Coordinate painting schedule with the government to allow for the removal of items ahead of painting, to maintain the flow of the painting process.

B. Administrative Procedures: Administrative activities include, but are not limited to, the following:

1. Preparation of Contractor's Construction Schedule. Installation and removal of temporary facilities and controls.

2. Delivery and processing of submittals.

3. Progress meetings.

4. Preinstallation conferences.

5. Project closeout activities.

1.3 SUBMITTALS

A. Coordination Drawings: Prepare submittals as required in Section 099123 – Interior Painting

1. Submit color samples timely for the contracting officer to provide approval.

2. Product Data Sheet Size: 8-1/2 by 11.

3. Number of Copies: Submit one electronic copy of each submittal. Contracting Officer will return one copy.

4. Refer to individual Sections for Coordination of required samples.

1.4 PROJECT MEETINGS

A. General: Schedule and conduct meetings and conferences at Project site, unless otherwise indicated.

BURLEY FIRE OFFICE 013100-5

1. Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Notify Contracting Officer of scheduled meeting dates and times.

2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees.

3. Minutes: Record significant discussions and agreements achieved.

B. Preconstruction Conference: Schedule a preconstruction conference before starting construction, at a time convenient to Contracting Officer, but no later than 15 calendar days after execution of the Contract. Hold the conference at Project site. Conduct the meeting to review responsibilities and personnel assignments, review required work, project drawings, specifications, construction schedules, payroll, payments, and administrative provisions of the Contract. Be prepared to summarize and explain procedures planned for the project and present specified preconstruction submittals.

1. Attendees: Authorized representatives of Government; Contractor and its superintendent;

major subcontractors; suppliers; and other concerned parties shall attend the conference.

All participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.

2. Agenda: Discuss items of significance that could affect progress, including the following:

a. Tentative construction schedule.

b. Phasing, if applicable.

c. Critical work sequencing and long-lead items.

d. Designation of key personnel and their duties.

e. Procedures for processing field decisions and Modifications.

f. Procedures for RFIs.

g. Procedures for testing and inspecting.

h. Procedures for processing Applications for Payment.

i. Distribution of the Contract Documents.

j. Submittal procedures.

k. Preparation of Record Documents.

l. Use of the premises.

m. Work restrictions.

n. Government occupancy requirements.

o. Responsibility for temporary facilities and controls.

p. Construction waste management and recycling.

q. Parking availability.

r. Office, work, and storage areas.

s. First aid.

t. Security.

u. Progress cleaning.

v. Working hours.

C. Progress Meetings: Conduct progress meetings at regular intervals. Hold the meetings at the project site. Coordinate dates of meetings with preparation of payment requests. Additional progress meetings may be requested by either the Contracting Officer or Contractor.

1. Attendees: In addition to representatives of Government, each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.

BURLEY FIRE OFFICE 013100-6

2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.

a. Contractor's Construction Schedule: Review progress since the last meeting.

Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to Contractor's Construction Schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do

so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.

1) Review schedule for next period.

b. Review present and future needs of each entity present, including the following:

1) Interface requirements.

2) Sequence of operations.

3) Status of submittals.

4) Deliveries.

5) Off-site fabrication.

6) Access.

7) Site utilization.

8) Temporary facilities and controls.

9) Work hours.

10) Hazards and risks.

11) Progress cleaning.

12) Quality and work standards.

13) Status of correction of deficient items.

14) Field observations.

15) RFIs.

16) Status of proposal requests.

17) Pending changes.

18) Status of Modifications.

19) Pending claims and disputes.

20) Documentation of information for payment requests.

3. Minutes: Record the meeting minutes.

4. Schedule Updating: Revise Contractor's Construction Schedule after each progress meeting where revisions to the schedule have been made or recognized. Issue revised schedule concurrently with the report of each meeting.

1.5 REQUESTS FOR INTERPRETATION (RFIs)

A. Procedure: Immediately on discovery of the need for interpretation of the Contract Documents, and if not possible to request interpretation at Project meeting, prepare and submit an RFI in the form specified.

1. RFIs shall originate with Contractor. RFIs submitted by entities other than Contractor will be returned with no response.

2. Coordinate and submit RFIs in a prompt manner to avoid delays in Contractor's work or work of subcontractors.

BURLEY FIRE OFFICE 013100-7

B. Content of the RFI: Include a detailed, legible description of item needing interpretation and the following:

1. Project name.

2. Date.

3. Name of Contractor.

4. Name of Contracting Officer.

5. RFI number, numbered sequentially.

6. Specification Section number and title and related paragraphs, as appropriate.

7. Drawing number and detail references, as appropriate.

8. Field dimensions and conditions, as appropriate.

9. Contractor's suggested solution(s). If Contractor's solution(s) impact the Contract Time or the Contract Sum, Contractor shall state impact in the RFI.

10. Contractor's signature.

11. Attachments: Include drawings, descriptions, measurements, photos, Product Data, Shop

Drawings, and other information necessary to fully describe items needing interpretation.

C. Contracting Officer's Action: Contracting Officer will review each RFI, determine action required, and return it. Allow seven (7) calendar days for Contracting Officer's response for each RFI. RFIs received after 1:00 p.m. will be considered as received the following working day.

1. The following RFIs will be returned without action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for coordination information already indicated in the Contract

Documents.

d. Requests for adjustments in the Contract Time or the Contract Sum.

e. Requests for interpretation of Contracting Officer's actions on submittals.

f. Incomplete RFIs or RFIs with numerous errors.

2. Contracting Officer's action may include a request for additional information, in which case Contracting Officer's time for response will start again.

D. On receipt of Contracting Officer's action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify Contracting Officer within seven

(7) days if Contractor disagrees with response.

E. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number.

Submit log monthly. Include the following:

1. Project name.

2. Name and address of Contractor.

3. Name and address of Contracting Officer.

4. RFI number including RFIs that were dropped and not submitted.

5. RFI description.

6. Date the RFI was submitted.

7. Date Contracting Officer's response was received.

8. Identification of related bilateral or unilateral modifications, extensions, and changes in scope, as appropriate.

BURLEY FIRE OFFICE 013100-8

END OF SECTION 013100

MAY 2023 CONSTRUCTION PROGRESS DOCUMENTATION

BURLEY FIRE OFFICE 013200-1

SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION

A. This Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:

1. Contractor's Construction Schedule.

2. Daily construction reports.

3. Field condition reports.

B. See Division 1 Section "Unit Prices and Schedule of Values" for submitting the Schedule of

Values.

1.2 SUBMITTALS

A. Contractor's Construction Schedule: Submit one electronic copy of initial schedule, large enough to show entire schedule for entire construction period.

B. Daily Construction Reports: Submit one electronic copy of reports at weekly intervals.

1. Submit on Mondays for prior week reports.

C. Field Condition Reports: Submit one electronic copy at time of discovery of differing conditions.

1.3 COORDINATION

A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate contractors.

B. Coordinate Contractor's Construction Schedule with the Schedule of Values, list of subcontracts, progress reports, payment requests, and other required schedules and reports.

1. Secure time commitments for performing critical elements of the Work from parties involved.

2. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.

BURLEY FIRE OFFICE 013200-2

PART 2 - PRODUCTS

2.1 CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL

A. Time Frame: Extend schedule from date established for the Notice to Proceed to date of Final Completion.

1. Contract completion date shall not be changed by submission of a schedule that shows an early completion date, unless specifically authorized by Modification.

B. Constraints: Include constraints and work restrictions indicated in the Contract Documents and as follows in schedule and show how the sequence of the Work is affected.

1. Work by Government: Include a separate activity for each portion of the Work performed by Government.

2. Work Stages: Indicate important stages of construction for each major portion of the Work.

C. Milestones: Include milestones indicated in the Contract Documents in schedule, including, but not limited to, the Notice to Proceed, Substantial Completion, and Final Completion.

D. Contract Modifications: For each proposed contract modification and concurrent with its submission, prepare a time-impact analysis to demonstrate the effect of the proposed change on the overall project schedule.

2.2 CONTRACTOR'S CONSTRUCTION SCHEDULE (GANTT CHART)

A. Gantt-Chart Schedule: Submit a comprehensive, fully developed, horizontal Gantt-chart-type, Contractor's Construction Schedule within 15 days of date established for the Notice to Proceed.

Base schedule on the Preliminary Construction Schedule and whatever updating and feedback was received since the start of Project.

2.3 REPORTS

A. Daily Construction Reports: Prepare a daily construction report recording the following information concerning events at Project site:

1. Contract Name and Number.

2. Date.

3. List of construction personnel at Project site.

4. Work completed.

5. Equipment at Project site.

6. Material deliveries.

7. Accidents.

8. Stoppages, delays, shortages, and losses.

9. Orders and requests of authorities having jurisdiction.

BURLEY FIRE OFFICE 013200-3

3.1 CONTRACTOR'S CONSTRUCTION SCHEDULE

A. Contractor's Construction Schedule Updating: At monthly intervals, update schedule to reflect actual construction progress and activities. Issue schedule one week before each regularly scheduled progress meeting.

1. Revise schedule immediately after each meeting or other activity where revisions have been recognized or made. Issue updated schedule concurrently with the report of each such meeting.

2. Include a report with updated schedule that indicates every change, including, but not limited to, changes in logic, durations, actual starts and finishes, and activity durations.

3. As the Work progresses, indicate Actual Completion percentage for each activity.

END OF SECTION 013200

SUBMITTAL PROCEDURES

013300-4

SECTION 013300 - SUBMITTAL PROCEDURES

A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, Design Computations, and other submittals.

B. See Division 1 Section "Construction Progress Documentation" for submitting schedules and reports, including Contractor's Construction Schedule.

C. See Division 1 Section "Quality Requirements" for submitting test and inspection reports.

D. See Division 1 Section "Closeout Procedures" for submitting warranties.

1.2 DEFINITIONS

A. Action Submittals: Written and graphic information that requires Contracting Officer's responsive action.

B. Informational Submittals: Written information that does not require Contracting Officer's responsive action. Submittals may be rejected for not complying with requirements.

1.3 SUBMITTAL PROCEDURES

A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.

B. Processing Time: Allow enough time for submittal review, including time for resubmittals, as follows. Time for review shall commence on Contracting Officer's receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals.

1. Initial Review: Allow 7 calendar days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required. Contracting Officer will advise Contractor when a submittal being processed must be delayed for coordination.

2. Intermediate Review: If intermediate submittal is necessary, process it in same manner as initial submittal.

3. Resubmittal Review: Allow 7 calendar days for review of each resubmittal.

C. Identification: Place a permanent label or title block on each submittal for identification.

1. Indicate name of firm or entity that prepared each submittal on label or title block.

2. Provide a space approximately 6 by 8 inches on label or beside title block to record

Contractor's review and approval markings and action taken by Contracting Officer.

3. Include the following information on label for processing and recording action taken:

013300-5

a. Project name.

b. Date.

c. Name and address of Contractor.

d. Name and address of subcontractor.

e. Name and address of supplier.

f. Name of manufacturer.

g. Submittal number or other unique identifier, including revision identifier.

1) Submittal number shall use Specification Section number followed by a decimal point and then a sequential number (e.g., 061000.01). Resubmittals shall include an alphabetic suffix after another decimal point (e.g., 061000.01.A). Work schedule and value schedule shall be numbers

011000.01 and 011000.02.

h. Number and title of appropriate Specification Section.

i. Drawing number and detail references, as appropriate.

j. Other necessary identification.

D. Cover Sheet:

1. Ensure that cover sheet includes following information:

a. Submittal Number.

b. Contract Number.

c. Specification section number and title, paragraph, and complete description of item being submitted. Be specific and clearly identify what is being submitted.

d. Signature and date.

e. Name and telephone number of individual to contact for further information, if other than Contractor.

2. Submitted Information: Link submittal to cover sheet by contract number, project name, and submittal number. Stamp is recommended, but may be hand-written on each copy;

ensure submittal stamp includes project name and contract number and blank space in which to write submittal number. Stamp or write this information on all copies.

E. Additional Copies: Unless additional copies are required for final submittal, and unless

Contracting Officer observes noncompliance with provisions in the Contract Documents, initial submittal may serve as final submittal.

F. Transmittal: Package each submittal individually and appropriately for transmittal and handling.

Transmit each submittal using a transmittal form. Contracting Officer will return submittals, without review received from sources other than Contractor.

G. Resubmittals: Make resubmittals in same form and number of copies as initial submittal.

1. Note date and content of previous submittal.

2. Note date and content of revision in label or title block and clearly indicate extent of revision.

3. Resubmit submittals until they are marked "APPROVED."

H. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.

013300-6

I. Use for Construction: Use only final submittals with mark indicating "APPROVED" taken by

Contracting Officer.

2.1 ACTION SUBMITTALS

A. Prepare and submit Action Submittals required by individual Specification Sections.

B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. Mark each copy of each submittal to show which products and options are applicable.

2. Include the following information, as applicable:

a. Manufacturer's written recommendations.

b. Manufacturer's product specifications.

c. Manufacturer's installation instructions.

d. Manufacturer's catalog cuts.

e. Compliance with specified referenced standards.

f. Testing by recognized testing agency.

3. Number of Copies: Submit one electronic copy of Product Data, unless otherwise indicated. Contracting Officer will return one copy. Mark up and retain returned copy as a Project Record Document.

C. Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other elements and for a comparison of these characteristics between submittal and actual component as delivered and installed.

1. Identification: Attach label on unexposed side of Samples that includes the following:

a. Generic description of Sample.

b. Product name and name of manufacturer.

c. Sample source.

d. Lot.

e. Style.

f. Color.

g. Locations of use.

h. Number and title of appropriate Specification Section.

2. Disposition: Maintain sets of approved Samples at Project site, available for quality-control comparisons throughout the course of construction activity. Sample sets may be used to determine final acceptance of construction associated with each set.

3. Samples for Initial Selection.

a. Number of Samples: Submit one full set(s) of available choices that match existing color(s).

b. Submit 8 inch square samples on rigid backing. Contracting Officer will retain Sample set.

013300-7

D. Product Schedule or List: As required in individual Specification Sections, prepare a written summary indicating types of products required for the Work and their intended location.

1. Number of Copies: Submit one electronic copy of product schedule or list, unless otherwise indicated. Contracting Officer will return one copy.

E. Schedule of Values: Comply with requirements specified in Division 1 Section "Unit Prices and

Schedule of Values."

F. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work.

1. Number of Copies: Submit on electronic copy of subcontractor list, unless otherwise indicated. Contracting Officer will return one copy.

2.2 INFORMATIONAL SUBMITTALS

A. Prepare and submit Informational Submittals required by other Specification Sections.

1. Number of Copies: Submit one electronic copy of each submittal, unless otherwise indicated. Contracting Officer will not return copy.

B. Contractor's Construction Schedule: Comply with requirements specified in Division 1 Section

"Construction Progress Documentation."

C. Installer Certificates: Prepare written statements on manufacturer's letterhead certifying that Installer complies with requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project.

D. Manufacturer Certificates: Prepare written statements on manufacturer's letterhead certifying that manufacturer complies with requirements in the Contract Documents. Include evidence of manufacturing experience where required.

E. Product Certificates: Prepare written statements on manufacturer's letterhead certifying that product complies with requirements in the Contract Documents.

F. Material Certificates: Prepare written statements on manufacturer's letterhead certifying that material complies with requirements in the Contract Documents.

G. Maintenance Data: Prepare written and graphic instructions and procedures for operation and normal maintenance of products and equipment. Comply with requirements specified in Division 1 Section "Operation and Maintenance Data."

H. Manufacturer's Instructions: Prepare written or published information that documents manufacturer's recommendations, guidelines, and procedures for installing or operating a product or equipment. Include name of product and name, address, and telephone number of manufacturer.

013300-8

3.1 CONTRACTOR'S REVIEW

A. Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to Contracting Officer.

B. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.

3.2 CONTRACTING OFFICER'S ACTION

A. General: Contracting Officer will not review submittals that do not bear Contractor's approval stamp and will return them without action.

B. Action Submittals: Contracting Officer will review each submittal, make marks to indicate corrections or modifications required, and return it. Contracting Officer will stamp each submittal with an action stamp and will mark stamp appropriately to indicate action taken, as follows:

1. APPROVED.

2. APPROVED, SUBJECT TO COMPLIANCE WITH THE ATTACHED COMMENTS.

3. NOT APPROVED.

C. Informational Submittals: Contracting Officer will review each submittal and will not return it, or will return it if it does not comply with requirements. Contracting Officer will forward each submittal to appropriate party.

D. Partial submittals are not acceptable, will be considered nonresponsive, and will be returned without review.

E. Submittals not required by the Contract Documents may not be reviewed and may be discarded.

F. Written approval of submittals is indication that Contractor's submittals have been reviewed and there are no objections, except as noted.

G. Installation of material on basis of written approval of submittals shall not relieve Contractor of responsibility for incorporating material that conforms to requirements of Contract Documents.

H. Written approval of deviations shall apply only to those deviations or omissions from the requirements of Contract Documents brought to Contracting Officer's attention in writing.

I. After written approval of an item, Contractor may submit substitution for approval, if approved item cannot be purchased or delivered in time to avoid delay in completion of the project.

END OF SECTION 013300

BURELY FIRE OFFICE

QUALITY REQUIREMENTS

014000-9

SECTION 014000 - QUALITY REQUIREMENTS

A. This Section includes administrative and procedural requirements for quality assurance and quality control.

B. Testing and inspecting services are required to verify compliance with requirements specified or indicated. These services do not relieve Contractor of responsibility for compliance with the Contract Document requirements.

1. Specified tests, inspections, and related actions do not limit Contractor's other quality-assurance and -control procedures that facilitate compliance with the Contract Document requirements.

2. Requirements for Contractor to provide quality-assurance and -control services required by Government or authorities having jurisdiction are not limited by provisions of this Section.

C. See Divisions 2 through 33 Sections for specific test and inspection requirements.

A. Quality-Assurance Services: Activities, actions, and procedures performed before and during execution of the Work to guard against defects and deficiencies and substantiate that proposed construction will comply with requirements.

B. Quality-Control Services: Tests, inspections, procedures, and related actions during and after execution of the Work to evaluate that actual products incorporated into the Work and completed construction comply with requirements. Services do not include contract enforcement activities performed by Contracting Officer.

C. Installer/Applicator/Erector: Contractor or another entity engaged by Contractor as an employee, Subcontractor, or Sub-subcontractor, to perform a particular construction operation, including installation, erection, application, and similar operations.

1. Using a term such as "carpentry" does not imply that certain construction activities must be performed by accredited or unionized individuals of a corresponding generic name, such as "carpenter." It also does not imply that requirements specified apply exclusively to tradespeople of the corresponding generic name.

D. Experienced: When used with an entity, "experienced" means having successfully completed a minimum of five previous projects similar in size and scope to this Project; being familiar with special requirements indicated; and having complied with requirements of authorities having jurisdiction.

BURELY FIRE OFFICE

QUALITY REQUIREMENTS

014000-10

1.3 CONFLICTING REQUIREMENTS

A. General: If compliance with two or more standards is specified and the standards establish different or conflicting requirements for minimum quantities or quality levels, comply with the most stringent requirement. Refer uncertainties and requirements that are different, but apparently equal, to Contracting Officer for a decision before proceeding.

B. Minimum Quantity or Quality Levels: The quantity or quality level shown or specified shall be the minimum provided or performed. The actual installation may comply exactly with the minimum quantity or quality specified, or it may exceed the minimum within reasonable limits.

To comply with these requirements, indicated numeric values are minimum or maximum, as appropriate, for the context of requirements. Refer uncertainties to Contracting Officer for a decision before proceeding.

C. Permits, Licenses, and Certificates: For Government records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations bearing on performance of the Work.

1.4 QUALITY ASSURANCE

A. General: Qualifications paragraphs in this Article establish the minimum qualification levels required; individual Specification Sections specify additional requirements.

B. Installer qualifications: Painting Contractor shall be certified / Licensed in the state of Idaho to perform service.

1.5 QUALITY CONTROL

A. Painter will conform to manufacturer's installation procedures stated in approved submittal for each product.

B. Government will verify that applied paint color matches the approved color and sheen submitted at various locations throughout the project.

3.1 REPAIR AND PROTECTION

A. Protect construction exposed by or for quality-control service activities.

B. Repair and protection are Contractor's responsibility, regardless of the assignment of responsibility for quality-control services.

END OF SECTION 014000

REFERENCES

014200-1

SECTION 014200 - REFERENCES

1.1 DEFINITIONS

A. Basic Contract definitions are included in the Conditions of the Contract.

B. "Approved": When used to convey Contracting Officer's action on Contractor's submittals, applications, and requests, "approved" is limited to Contracting Officer's duties and responsibilities as stated in the Conditions of the Contract.

C. "Directed": A command or instruction by Contracting Officer. Other terms including "requested,"

"authorized," "selected," "approved," "required," and "permitted" have the same meaning as "directed."

D. "Indicated": Requirements expressed by graphic representations or in written form on Drawings, in Specifications, and in other Contract Documents. Other terms including "shown," "noted," "scheduled," and "specified" have the same meaning as "indicated."

E. "Regulations": Laws, ordinances, statutes, and lawful orders issued by authorities having jurisdiction, and rules, conventions, and agreements within the construction industry that control performance of the Work.

F. "Furnish": Supply and deliver to Project site, ready for unloading, unpacking, assembly, installation, and similar operations.

G. "Install": Operations at Project site including unloading, temporarily storing, unpacking, assembling, erecting, placing, anchoring, applying, working to dimension, finishing, curing, protecting, cleaning, and similar operations.

H. "Provide": Furnish and install, complete and ready for the intended use.

I. "Project Site": Space available for performing construction activities. The extent of Project site is shown on Drawings and may or may not be identical with the description of the land on which Project is to be built.

1.2 INDUSTRY STANDARDS

A. Applicability of Standards: Unless the Contract Documents include more stringent requirements, applicable construction industry standards have the same force and effect as if bound or copied directly into the Contract Documents to the extent referenced. Such standards are made a part of the Contract Documents by reference. Where a conflict occurs between reference documents and project specifications, submit a request for clarification to the Contracting Officer.

B. Publication Dates: Comply with standards in effect as of date of the Contract Documents, unless otherwise indicated.

014200-2

C. Copies of Standards: Each entity engaged in construction on Project should be familiar with industry standards applicable to its construction activity. Copies of applicable standards are not bound with the Contract Documents.

1. Where copies of standards are needed to perform a required construction activity, obtain copies directly from publication source.

D. Abbreviations and Acronyms for Standards and Regulations: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the standards and regulations in the following list.

ADAAG Americans with Disabilities Act (ADA)

Architectural Barriers Act (ABA)

CFR Code of Federal Regulations

CRD Handbook for Concrete and Cement

FS Federal Specification

ICC-ES ICC Evaluation Service, Inc.

MILSPEC Military Specification and Standards

NES National Evaluation Service (See ICC-ES)

UFAS Uniform Federal Accessibility Standards

1.3 ABBREVIATIONS AND ACRONYMS

A. Industry Organizations: Where abbreviations and acronyms are used in Specifications or other

Contract Documents, they shall mean the recognized name of the entities indicated in Gale Research's "Encyclopedia of Associations" or in Columbia Books' "National Trade & Professional Associations of the U.S."

B. Industry Organizations: Where abbreviations and acronyms are used in Specifications or other

Contract Documents, they shall mean the recognized name of the entities in the following list.

AASHTO American Association of State Highway and Transportation Officials

ACI ACI International (American Concrete Institute)

AGC Associated General Contractors of America (The)

AIA American Institute of Architects (The)

AISC American Institute of Steel Construction

AISI American Iron and Steel Institute

014200-3

ANSI

APA

ASCE

American National Standards Institute

Architectural Precast Association

American Society of Civil Engineers

ASTM ASTM International (American Society for Testing and Materials International)

AWS American Welding Society

CRSI Concrete Reinforcing Steel Institute

CSA CSA International (Formerly: IAS - International Approval Services)

CSI Construction Specifications Institute (The)

EJMA Expansion Joint Manufacturers Association, Inc.

GSI Geosynthetic Institute

ICRI International Concrete Repair Institute, Inc.

ISO International Organization for Standardization

MPI Master Painters Institute

NAAMM National Association of Architectural Metal Manufacturers

NFPA NFPA

(National Fire Protection Association)

NRMCA National Ready Mixed Concrete Association

NSSGA National Stone, Sand & Gravel Association

PCI Precast/Prestressed Concrete Institute

PDCA Painting & Decorating Contractors of America

PTI Post-Tensioning Institute

RCSC Research Council on Structural Connections

SEI Structural Engineering Institute

SSINA Specialty Steel Industry of North America

SSPC SSPC: The Society for Protective Coatings

014200-4

UL Underwriters Laboratories Inc.

USGBC U.S. Green Building Council

C. Code Agencies: Where abbreviations and acronyms are used in Specifications or other Contract

Documents, they shall mean the recognized name of the entities in the following list.

ICC International Code Council (Formerly: CABO - Council of American Building Officials)

ICC-ES ICC Evaluation Service, Inc.

D. Federal Government Agencies: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities in the following list.

EPA Environmental Protection Agency

NIST National Institute of Standards and Technology

OSHA Occupational Safety & Health Administration

E. State Government Agencies: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities in the following list.

ISPWC Idaho Standard for Public Works Construction

END OF SECTION 014200

TEMPORARY FACILITIES AND CONTROLS

015000-7

PRODUCT REQUIREMENTS

016000-1

SECTION 016000 - PRODUCT REQUIREMENTS

A. This Section includes administrative and procedural requirements for selection of products for use in Project; product delivery, storage, and handling; manufacturers' standard warranties on products; special warranties; product substitutions; and comparable products.

B. See Division 1 Section "Closeout Procedures" for submitting warranties for Contract closeout.

C. See Divisions 2 through 33 Sections for specific requirements for warranties on products and installations specified to be warranted.

A. Products: Items purchased for incorporating into the Work, whether purchased for Project or taken from previously purchased stock. The term "product" includes the terms "material," "equipment," "system," and terms of similar intent.

1. Named Products: Items identified by manufacturer's product name, including make or model number or other designation shown or listed in manufacturer's published product literature that is current as of date of the Contract Documents.

2. New Products: Items that have not previously been incorporated into another project or facility, except that products consisting of recycled-content materials are allowed, unless explicitly stated otherwise. Products salvaged or recycled from other projects are not considered new products.

3. Comparable Product: Product that is demonstrated and approved through submittal process, or where indicated as a product substitution, to have the indicated qualities related to type, function, dimension, in-service performance, physical properties, appearance, and other characteristics that equal or exceed those of specified product.

B. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the Contract Documents and proposed by Contractor.

1.3 SUBMITTALS

A. Substitution Requests: Submit one electronic copy of each request for consideration. Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.

016000-2

1. Documentation: Show compliance with requirements for substitutions and the following, as applicable:

a. Detailed comparison of significant qualities of proposed substitution with those of the Work specified. Significant qualities may include attributes such as performance, weight, size, durability, visual effect, and specific features and requirements indicated. Provide sufficient calculations and data to justify selection of proposed item and permit comparisons.

b. Product Data, including technical data, drawings, performance information, and descriptions of products and fabrication and installation procedures. Show complete layout of system, except that which is identical to Contract Documents, unless unchanged portion must be shown to indicate clearances. Include drawings, same (or larger) scale as Contract Drawings, marked to show differences. Include detail drawings of supports for equipment and load calculations, stamped and signed by a registered professional engineer.

c. Samples, where applicable or requested.

d. Cost information, including a proposal of change, if any, in the Contract Sum.

e. Contractor's certification that proposed substitution complies with requirements in the Contract Documents and is appropriate for applications indicated.

f. Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.

2. Government Action: If necessary, Contracting Officer will request additional information or documentation for evaluation within 7 days of receipt of a request for substitution.

Contracting Officer will notify Contractor of acceptance or rejection of proposed substitution within 15 days of receipt of request, or 7 days of receipt of additional information or documentation, whichever is later.

a. Form of Acceptance: Modification or Instruction to Contractor.

b. Use product specified if Contracting Officer cannot make a decision on use of a proposed substitution within time allocated.

B. Comparable Product Requests: Submit one electronic copy of each request for consideration.

Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.

1. Government Action: If necessary, Contracting Officer will request additional information or documentation for evaluation within one week of receipt of a comparable product request. Contracting Officer will notify Contractor of approval or rejection of proposed comparable product request within 15 days of receipt of request, or 7 days of receipt of additional information or documentation, whichever is later.

a. Form of Approval: As specified in Division 1 Section "Submittal Procedures."

b. Use product specified if Contracting Officer cannot make a decision on use of a comparable product request within time allocated.

C. Basis-of-Design Product Specification Submittal: Comply with requirements in Division 1 Section "Submittal Procedures." Show compliance with requirements.

016000-3

1.4 QUALITY ASSURANCE

A. Compatibility of Options: If Contractor is given option of selecting between two or more products for use on Project, product selected shall be compatible with products previously selected, even if previously selected products were also options.

1.5 PRODUCT DELIVERY, STORAGE, AND HANDLING

A. Deliver, store, and handle products using means and methods that will prevent damage, deterioration, and loss, including theft. Comply with manufacturer's written instructions.

B. Delivery and Handling:

1. Schedule delivery to minimize long-term storage at Project site and to prevent overcrowding of construction spaces.

2. Coordinate delivery with installation time to ensure minimum holding time for items that are flammable, hazardous, easily damaged, or sensitive to deterioration, theft, and other losses.

3. Deliver products to Project site in an undamaged condition in manufacturer's original sealed container or other packaging system, complete with labels and instructions for handling, storing, unpacking, protecting, and installing.

4. Load and unload products in manner that protects from damage.

5. Inspect products on delivery to ensure compliance with the Contract Documents and to ensure that products…