BISC_Adams_Key_Generator_SOW.pdf
PDF 204 KB Posted
- Attached to
- SERVICE, ADAMS KEY GENERATOR REPLACEMENT AND INSTA Federal contract opportunity
- Solicitation number
- 140P5424Q0031
About this file
This document is a Statement of Work (SOW) for the replacement of a 30kW generator at Adams Key in Biscayne National Park. The contractor shall provide all labor, tools, equipment, materials, and supervision required to remove the current generator and supply and install a new 30kW single phase diesel generator. The work shall be completed within 180 days after the Notice to Proceed is issued. The contractor shall comply with OSHA, environmental, and safety regulations, and provide proof of required insurance. The contractor's quality control plan and the government's quality assurance plan are outlined.
The related federal contract opportunity is a solicitation (Solicitation Number: 140P5424Q0031) issued by the Department of the Interior National Park Service Southeast Region to procure one generator and associated installation services for Adams Key in Biscayne National Park. Questions are due 12:00PM EST on July 8, 2024, and quotes are due 12:00PM EST on July 18, 2024.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P5424Q0031_Amd_0001.pdf | ||
| BISC_Solicitation_140P5424Q0031_Questions_and_Responses_0001.pdf | ||
| B03_SCA_WD_2015-4543_REV__27.pdf | ||
| Sol_140P5424Q0031.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work (SOW)
Replace Adams Key Prime Generator
National Park Service Contracting Operation East - South
1. Background:
Adams Key is a remote Key located in Biscayne National Park and the only source of power is from generators and solar. The one 30KW generator engine at Adams Key has a life cycle of approximately 3 years due to the harsh island environmental conditions of salt air and Seasonal Hurricanes. Generator has in excess of 10,000 hours as of Fiscal Year 21 and needs to be replaced based on EUL and Site conditions.
2. Objectives:
The contractor shall provide all labor, tools, equipment, materials, and supervision required to remove current 30kW (C30 D6) single phase diesel generator, supply and install new 30kW single phase diesel generator Cummins Power Generation (Model: C30 D6) with weather cover of the same make, model and size, conduct start up and testing to ensure proper function.
Removal of all debris offsite shall be the responsibility of the contractor.
3. Place of Performance:
Contract Site Remote Location Biscayne National Park, Adams Key
Headquarters Location:
Biscayne National Park, Convoy Point 9700 SW 328th Street Sir Lancelot Jones Way Homestead, FL 33033
Park will provide vessel transportation for material and personnel leaving Convoy Point at 7:30am and picking up from Adams Key at 2:30pm. If contractor cannot work those hours, contractor will need to provide transportation to and from Elliott Key for personnel and materials.
4. Scope of Work:
• Supply one C30D6 single phase diesel generator.
• Contractor will provide transportation of personnel to the job site.
• Remove current generator and turn over to the park for other use.
• Install new C30D6 single phase generator.
• Perform all required start up tests and ensure functionality of new generator.
• Clean job site of any and all debris prior to completion inspection and contract closeout.
• Contractor is responsible for the final disposal of any service debris that may be generated during the performance of this contract.
5. Government Furnished Property, Materials & Supplies.
The park will provide transportation of new equipment and any materials to/from the job site by barge to ensure protection of the natural resources of the park from damage.
6. Business Hours:
The contractor shall complete on-site work during normal business hours of 7:30 am to 4:30 pm, Monday through Friday, excluding Federal holidays. The contractor shall coordinate specific on-site work schedule with the Contracting Officer and Contracting Officer Representative (COR) five days prior to performance start date. While on site, the COR may be reached by mobile phone during normal business hours. Work shall be completed within 180 days after Contracting Officer issues notice to proceed. Any work outside of normal business hours shall be pre-approved by the Contracting Officer and COR.
7. Management:
The contractor shall manage the total work effort in accordance with effective and efficient management principles and safe working practices to ensure on-time completion of this contract.
8. Safety & Environmental Compliance:
• The contractor shall comply with pertinent provisions of the Occupational Safety and Health Act (OSHA), and state, local, safety, laws.
• The contractor shall comply with pertinent Environmental Protection Agency laws and regulations.
• The Park safety officer has the authority to issue restraint or cease-and-desist orders to the contractor when violations or unsafe acts are present and threaten Government and contractor employees or damage to Government property.
• The contractor shall immediately report to the Contracting Officer, COR, and Park safety officer all accidents resulting in employee injury or death or damage to property while performing this contract.
9. Insurance:
The Contractor shall be insured in accordance with State of Florida insurance regulations. The Government is not responsible for damage to Contractor’s equipment, vehicles, tools or materials or their employees and the personal property brought on-site. The Government will not accept any liability due to contractor employee negligence.
• Workers Compensation: The contractor shall furnish proof of workers compensation insurance to the Contracting Officer for those employees performing work related to this contract and shall comply with the Workman’s Compensation Laws of the State of Florida.
• Liability: The Contractor shall maintain a level of insurance that will protect the contractor and the Government from any claims as a result of bodily injury (including death) and property damage which may arise from and during the performance of this contract and shall submit proof of insurance to the Contracting Officer.
10. Performance Requirements Summary (PRS):
The contractor performance requirements are summarized into required services that relates directly to successful contract completion. The performance standard identifies the minimum acceptable levels of service allowed.
PWS
Section Required Service Standard Monitoring
Method Incentive/
Disincentive Insert Para 3
Remove current Generator.
100% compliance
Random Inspection Performance Evaluation
3 Install new C30D6 Generator
100% compliance
Random Inspection Performance Evaluation
Perform initial startup of generator
100% compliance
Random Inspection Performance Evaluation
11. Motor Vehicle & Traffic Regulations:
Contractor employees operating motor vehicles shall possess a valid driver's license. Driver and vehicle permit, licenses, registrations, and proof of insurance shall be maintained in the vehicle at all times and made available upon request. Contractor employees shall comply with federal vehicle motor law requiring seat belts be worn at all times. Contractor employees shall adhere to the posted speed limits.
12. Employee Badges/Parking:
All contractor employees shall comply with parking procedures published for the Park.
Contractor employees shall return any PARK issued personal or vehicle identification badges immediately upon termination of employment or completion of this contract.
13. Replacement of Contractor Employee for Security Reasons:
The Government retains the right to request removal of the contractor’s employee(s), regardless of prior clearances.
14. Non-Payment for Additional Work:
Any additional contractor performed services not specified in contract, either at its own volition or at the request of an individual other than an appointed Contracting Officer, except as may be explicitly authorized in the contract, shall be performed at the financial risk of the contractor.
Only an appointed Contracting Officer is authorized to bind the Government to a change in specifications, contract terms, or conditions.
15. Conflict of Interest:
The contractor shall not employ off-duty COR’s or other Government employees if such employment would create a conflict of interest or be contrary to the policies contained in conflict-of-interest directives.
16. Quality Control:
The contractor shall establish and maintain a Quality Control Plan (QCP) to ensure the work performed conforms to the contract requirements. The Performance Requirements Summary establishes performance standards that are the minimum requirements for acceptable performance of required services. The contractor’s QCP shall address methods for remedying poor performance. The Contractor shall develop QCP and submit with proposal package. The Contractor’s QCP includes:
• Required services identified in Performance Requirements Summary
• Contractor’s surveillance methodology
• Method and timeframe for responding to COR or customer complaints
• Progress meetings with Government stakeholders
17. Quality Assurance:
The COR will monitor the contractor’s performance under this contract using the quality assurance procedures specified in the Government’s Quality Assurance Surveillance Plan (QASP). The QASP may be modified after contract award upon review and acceptance of the contractor’s QCP to ensure both plans are mutually supportive. The purpose of the QASP is to ensure that the required services are performed in accordance with the contract requirements.
The plan ensures reliable and continued operation by precluding unnecessary complaints and unacceptable performance. Government’s QASP includes:
• Acceptance of the contractor’s quality control plan
• Random inspection of the contractor’s work
• Communicating customer complaints
• Progress meetings with the contractor
The implementation of this QASP does not relieve the contractor of its responsibility to implement and abide by the QCP incorporated into this contract, and to provide acceptable performance of all required services listed herein. At the CO’s discretion, the contractor may incur a payment deduction for lack of compliance with the QCP, PWS or PRS.
18. Inspection:
The Government will conduct inspection upon completion of required services. Final payment will be processed upon confirming that all noted contractor performance deficiencies have been satisfactorily corrected.