Bid_Schedule.docx
DOCX document 16 KB Posted
- Attached to
- FUEL BREAK MOWING, TWIN FALLS DIST Federal contract opportunity
- Solicitation number
- 140L2625Q0044
About this file
The Bid Schedule for the 2025 TFD Fuel Break Mowing (Solicitation Number 140L2625Q0044) outlines a mowing project for the Bureau of Land Management in the Idaho Region. The solicitation covers four line items for fuel break mowing across different areas, totaling 1,430 acres to be completed between 10/15/2025 and 11/17/2025 (34 total days). The project involves mowing with two 14-foot mowers, estimated to cover approximately 60 acres per day, with individual line items ranging from 3 to 9 calendar days of work.
Key project parameters include performance during fall/early winter, with work contingent on ground conditions to prevent soil and vegetation damage. The contractor must be prepared to start work within three days of notification by the Contracting Officer Representative (COR). The estimated performance period is from 10/01/2025, with specific line items having varying completion timelines. Work may be impacted by potential road inaccessibility and backcountry limitations due to muddy or wet conditions during the mowing period.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140L2625Q0044.pdf | ||
| maps.pdf | ||
| Work_Statement.docx | DOCX document | |
| Wage_Determination.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BID SCHEDULE
SCHEDULE OF SUPPLIES AND SERVICES
2025 TFD FUEL BREAK MOWING
| Line Item Number |
| Item Description |
| Estimated Quantity |
| Unit of Measure |
| Unit Price |
| Total |
| 0001 |
| HMA 2 Fuel Break |
| 485 |
| AC |
| $ |
| $ |
| 0002 |
| HMA 4 North Fuel Break |
| 444 |
| AC |
| $ |
| $ |
| 0003 |
| HMA 3 Fuel Break |
| 368 |
| AC |
| $ |
| $ |
| 0004 |
| HMA Middle Fuel Break |
| 133 |
| AC |
| $ |
| $ |
| 2025 TFD Fuel Break Mowing Total (All or None) |
| $ |
AC = Acre
Estimated Start Date: 10/01/2025.
Performance Time: 10/15/2025 – 11/17/2025. 34 Days Total (including holidays and weekends).
Item 0001: 9 Calendar Days
Item 0002: 8 Calendar Days
Item 0003: 7 Calendar Days
Item 0004: 3 Calendar Days
*Calculated based upon two 14-foot mowers accomplishing 60 acres per day.
Total Acreage: 1,430 Acres
The mowing will coincide with fall/early winter weather and ground conditions for the period of performance. During the mowing, roads may not be passable and backcountry access may be limited due to muddy or wet conditions. Work will not be permitted if conditions will result in damage to soils and non-target vegetation. The contractor shall be required to start work within three (3) days after being notified by the Contracting Officer Representative (COR).