BID SCHEDULE CONTINENTAL WATER WELLS.xlsx

XLSX spreadsheet 14 KB Posted

Attached to
RSFO CONTINENTAL PEAK WATER WELLS Federal contract opportunity
Solicitation number
140L6220Q0110
Issued by
Department of the Interior Bureau of Land Management Wyoming Region

View the file

Other files for this federal contract opportunity

Other files attached to RSFO CONTINENTAL PEAK WATER WELLS, newest first.
File Type Posted
02 01009 CONTINENTAL WATER WELLS.docx DOCX document
04 WORKDATASHEET CONTINENTAL WATER WELLS.docx DOCX document
Sol_140L6220Q0110.pdf PDF
06 Continental Peak Well Map Reservoirs A and B.pdf PDF
05 Continental Peak Well Map Windmill European.pdf PDF
03 02674 CONTINENTAL WATER WELLS.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

BID SCHEDULE "A"
EUROPEAN WATER WELL CONSTRUCTION
ItemPay ItemEstimatedUnitTotal
No.NumberDescriptionQuantityUnitPriceAmount
1WY-02674(1)Drilling Pilot Hole (5 inch min diameter)500LF$0.00
2WY-02674(2)Drilling Well Hole (9-1/2 inch min diameter)500LF$0.00
3WY-02674(3)Furnish and Install 5-inch PVC Casing400LF$0.00
4WY-02674(4)Furnish and Install 5-inch Slotted PVC Casing100LF$0.00
5WY-02674(5)Gravel Packing/Bentonite Seal120LF$0.00
6WY-02674(6)Formation Stablilizer/Grout, Surface Grout380LF$0.00
7WY-02674(7)Well Development6Hours$0.00
8WY-02674(8)Well Testing6LS$0.00
9WY-02674(9)Mobilization1LS$0.00
TOTAL EUROPEAN WATER WELL CONSTRUCTION =$0.00
BID SCHEDULE "A"
RESERVOIR A WATER WELL CONSTRUCTION
ItemPay ItemEstimatedUnitTotal
No.NumberDescriptionQuantityUnitPriceAmount
1WY-02674(1)Drilling Pilot Hole (5 inch min diameter)800LF$0.00
2WY-02674(2)Drilling Well Hole (9-1/2 inch min diameter)800LF$0.00
3WY-02674(3)Furnish and Install 5-inch PVC Casing700LF$0.00
4WY-02674(4)Furnish and Install 5-inch Slotted PVC Casing100LF$0.00
5WY-02674(5)Gravel Packing/Bentonite Seal120LF$0.00
6WY-02674(6)Formation Stablilizer/Grout, Surface Grout680LF$0.00
7WY-02674(7)Well Development6Hours$0.00
8WY-02674(8)Well Testing6LS$0.00
9WY-02674(9)Mobilization1LS$0.00
TOTAL RESERVOIR A WATER WELL CONSTRUCTION =$0.00
BID SCHEDULE "B"
WINDMILL EXTENSION WATER WELL CONSTRUCTION
ItemPay ItemEstimatedUnitTotal
No.NumberDescriptionQuantityUnitPriceAmount
1WY-02674(1)Drilling Pilot Hole (5 inch min diameter)500LF$0.00
2WY-02674(2)Drilling Well Hole (9-1/2 inch min diameter)500LF$0.00
3WY-02674(3)Furnish and Install 5-inch PVC Casing400LF$0.00
4WY-02674(4)Furnish and Install 5-inch Slotted PVC Casing100LF$0.00
5WY-02674(5)Gravel Packing/Bentonite Seal120LF$0.00
6WY-02674(6)Formation Stablilizer/Grout, Surface Grout380LF$0.00
7WY-02674(7)Well Development6Hours$0.00
8WY-02674(8)Well Testing6LS$0.00
9WY-02674(9)Mobilization1LS$0.00
TOTAL WINDMILL EXTENSION WATER WELL CONSTRUCTION =$0.00
BID SCHEDULE "B"
RESERVOIR B WATER WELL CONSTRUCTION
ItemPay ItemEstimatedUnitTotal
No.NumberDescriptionQuantityUnitPriceAmount
1WY-02674(1)Drilling Pilot Hole (5 inch min diameter)800LF$0.00
2WY-02674(2)Drilling Well Hole (9-1/2 inch min diameter)800LF$0.00
3WY-02674(3)Furnish and Install 5-inch PVC Casing700LF$0.00
4WY-02674(4)Furnish and Install 5-inch Slotted PVC Casing100LF$0.00
5WY-02674(5)Gravel Packing/Bentonite Seal120LF$0.00
6WY-02674(6)Formation Stablilizer/Grout, Surface Grout680LF$0.00
7WY-02674(7)Well Development6Hours$0.00
8WY-02674(8)Well Testing6LS$0.00
9WY-02674(9)Mobilization1LS$0.00
TOTAL RESERVOIR B WATER WELL CONSTRUCTION =$0.00
TOTAL COST FOR SCHEDULE "A" CONTINENTAL PEAK WELLS =$0.00
TOTAL COST FOR SCHEDULE "B" CONTINENTAL PEAK WELLS =$0.00
TOTAL COST FOR SCHEDULE "A" AND "B" CONTINENTAL PEAK WELLS =$0.00

File details come from the government source that posted it. Updated .