Statement_of_Work.pdf
PDF 79 KB Posted
- Attached to
- FTIR Microscope Federal contract opportunity
- Solicitation number
- BEP-RFQ-16-0758
About this file
Statement of Work
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FAR_52.212-3.pdf | ||
| COMBINED_SYNOPSIS_04.11.16.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1 Statement of Work BEP-RFQ-16-0758 Bureau of Engraving and Printing
Statement of Work
FTIR MICROSCOPE
1.0 BACKGROUND
The Bureau of Engraving and Printing (“BEP”) has a requirement for a stand-alone Fourier transform infrared (FT-IR) microscope with an integrated FT-IR spectrometer to support currency manufacturing process.
2.0 SCOPE
The contractor shall deliver and install all equipment at the BEP Eastern Currency Facility (DCF) in Washington, DC.
3.0 TECHNICAL REQUIREMENTS
3.1 Contractor shall supply equipment with the following features:
The instrument must be a stand-alone FT-IR microscope with an integrated FT-IR spectrometer. Systems comprised of an FTIR spectrometer and separate FTIR compatible microscope are not acceptable.
Fully automated data acquisition in mapping, transmission, reflection and Attenuated Total Reflection (ATR) modes including background
The FT-IR microscope shall be fully motorized. This includes (but is not limited to), ATR crystal, XY sample stage, Z motion of sample stage, aperture
The working distance of the objective must be higher than 25 mm. Samples of a thickness of at least 35 mm shall be measurable without the need for any change in the hardware
Autofocus
Automatic calibration of optics and stage
Wavelength: 750 – 4000 cm-1
Resolution: at least 2 cm-1 (lower values are better)
Stage/Probe adjustment accuracy (smallest step size): 0.1 μm
Repeatability: < 1 μm
Dry air purge is not required
Zinc Selenide (ZnSe) windows to allow operation at up to 70% relative humidity
Windows 7 software
The detector system shall contain a dedicated technology to re-establish the necessary vacuum. The detector shall not need to be removed from its mounting position for re-evacuation.
The FT-IR microscope shall be a one objective microscope without nose piece.
Sample probe/stage movable by joystick.
2 Statement of Work BEP-RFQ-16-0758 Bureau of Engraving and Printing
3.2 Contractor shall provide annual routine maintenance and recalibration of the equipment.
Contractor shall provide a point of contact for maintenance and recalibration support.
3.3 All parts should be new. The above listing must be provided to specification without replacement. If any supply is unavailable, Contractor shall notify the BEP technical representative with recommended replacement part.
3.4 Contractor shall supply and install all equipment within 120 days of award. If any item is deemed insufficient or damaged, the Contracting Officer Representative (COR) will notify the contractor.
3.5 Contractor shall provide a minimum 1-year warranty for all parts under this contract.
3.6 Contractor shall provide training for at least three (3) BEP personnel.
4.0 PERFORMANCE REQUIRED
4.1 Responsibility for Inspection and Testing: The BEP reserves the right to perform any inspections and tests set forth for this equipment, to include inventory of parts list and supplies listed in contract.
4.2 BEP Testing: The BEP will evaluate all the parts for compliance with the requirements stated in Section 3.0