Responses_to_Questions_(20140130)_-_Continued.doc
DOC document 35 KB Posted
- Attached to
- W/V-band Satellite Communications Experiment (WSCE) program Federal contract opportunity
- Solicitation number
- BAA-RVKV-2014-0002
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Responses_to_Questions_(20140128)_-_Continued.doc | DOC document | |
| Responses_to_Questions_(20140128).doc | DOC document | |
| BAA-RVKV-2014-0002_Amd_1_-_28_Jan_2014.docx | DOCX document | |
| Revised_WSCE_Phase_2_BAA_20140114_1000.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RESPONSES TO QUESTIONS (Continued)
BAA-RVKV-2014-0002
30 Jan 2014
15) Under paragraph I.A.iv, does the contractor have to price the materials for the ground stations or just provide a design?
I. PROGRAM Description
A. Statement of Objectives/Needs
iv. The W/V-band Satellite Communications Experiment (WSCE) program intends to procure the necessary flight-qualified space system and validated prototype ground system through this BAA. SMC/MC will identify and provide a satellite host for the WSCE space system. AFRL and NASA Glenn will assemble, install, and operate experiment ground systems.
RESPONSE: The contractor will develop the ground system concept during Task 1 (I.B.ii). The contractor will develop and deliver a prototype ground system during Task 2 (I.B.iii); therefore, the contractor must price the materials for their proposed ground system concept.