B08(e)_-_Quality_Assurance_Surveillance_Plan_-_Attachment_4.docx

DOCX document 31 KB Posted

Attached to
Parking Meter Maintenance Federal contract opportunity
Solicitation number
140P3023Q0006
Issued by
Department of the Interior National Park Service National Office

View the file

Other files for this federal contract opportunity

Other files attached to Parking Meter Maintenance, newest first.
File Type Posted
Sol_140P3023Q0006_Amd_0001.pdf PDF
B08(b)_-_Pricing_Sheet_-_Attachment_1.xlsx XLSX spreadsheet
B08(d)_-_WD_2015-4281_Rev__24_dated_6-27-2022_-_Attachment_3.pdf PDF
B08(c)_-_Map_for_contract_-_Attachment_2.pdf PDF
Sol_140P3023Q0006.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Quality Assurance Surveillance Plan (QASP)

Parking Meter Maintenance & Cost of Collections

For the National Park Service National Mall & Memorial Parks

Contents

1.0INTRODUCTION3
1.1PURPOSE3
1.2PERFORMANCE MANAGEMENT APPROACH3
1.3PERFORMANCE MANAGEMENT STRATEGY3
2.0ROLES AND RESPONSIBILITIES4
2.1Contracting Officer4
2.2Contracting Officer Representative4
3.0IDENTIFICATION OF REQUIRED PERFORMANCE STANDARDS/QUALITY LEVELS4
4.0METHODOLOGIES TO MONITOR PERFORMANCE4
4.1Surveillance Techniques4
4.2 Customer Feedback4
4.3 Acceptable Quality Levels5
5.0QUALITY ASSURANCE DOCUMENTATION5
5.1The Performance Management Feedback Loop5
5.2Monitoring Forms5
6.0ANALYSIS OF QUALITY ASSURANCE MONITORING RESULTS5
6.1Determining Performance5
6.2Reporting5
6.3Reviews and Resolution5
6.4List of Attachments6
ATTACHMENT A2 – PERFORMANCE REQUIREMENTS SUMMARY7
ATTACHMENT A3 – QUALITY ASSURANCE MONITORING FORM9
ATTACHMENT A4 – CUSTOMER COMPLAINT INVESTIGATION10

1.0 INTRODUCTION

This quality assurance surveillance plan (QASP) sets forth the procedures and guidelines the National Park Service (NPS), National Mall & Memorial Parks (NAMA) will use in ensuring the required performance standards or services levels are achieved by the contractor.

1.1 PURPOSE

The purpose of the QASP is to describe the systematic methods used to monitor performance and to identify the required documentation and the resources employed. The QASP provides a means for evaluating whether the contractor is meeting required performance standards.

This QASP defines the roles and responsibilities of all members of the project team, identifies the performance objectives, defines the methodologies used to monitor and evaluate the contractor’s performance, describes quality assurance (QA) documentation requirements, and describes the analysis of the QA monitoring results.

1.2 PERFORMANCE MANAGEMENT APPROACH

This QASP will define the performance management approach taken by the NPS NAMA to monitor the contractor’s performance to ensure realization of performance standards. Performance management rests on developing a capability to review and analyze information generated through performance assessment. The ability to make decisions based on the analysis of performance data is the cornerstone of performance management; this analysis yields information that indicates whether the contractor is achieving acceptable performance.

1.3 PERFORMANCE MANAGEMENT STRATEGY

The contractor is responsible for the quality of all work performed and shall measure quality through the contractor’s quality control (QC) program. QC is the output of work and includes all work performed regardless of whether the work is performed by direct employees, contractor employees, other teaming partners or subcontractors.

The government representative(s) will monitor performance and review performance reports furnished by the contractor to determine how the contractor is performing against performance standards. The contractor is responsible for making required changes in processes and practices to ensure effective performance management.

2.0ROLES AND RESPONSIBILITIES
2.1Contracting Officer

The contracting officer (CO) is responsible for monitoring compliance and administration, and for resolving any differences between the observations documented by the NPS/NAMA contracting officer’s representative (COR) and the contractor. The CO will designate a COR as a government authority for performance management.

2.2 Contracting Officer Representative

The contracting officer’s representative (COR), designated in writing by the CO to act as his or her authorized representative, assists in administering the contract. COR’s limitations are contained in the written appointment letter. The COR is responsible for technical administration of the project and ensures proper government surveillance of the contractor’s performance. The COR is not empowered to make any contractual commitments or to authorize any contractual changes on the government’s behalf. The COR shall refer any changes that the contractor deems may affect price, terms, or conditions to the CO for action. The COR is responsible for completing the QA monitoring forms used to document the inspection and evaluation of the contractor’s work performance. Attachment A3 includes the Quality Assurance Monitoring Form.

3.0 IDENTIFICATION OF REQUIRED PERFORMANCE STANDARDS/QUALITY LEVELS

The required performance standards and/or quality levels are included in Attachment A2, “Performance Requirements Summary.”

4.0METHODOLOGIES TO MONITOR PERFORMANCE
4.1Surveillance Techniques

To minimize the performance management burden, the government’s evaluation of contractor performance (when appropriate) shall use simplified surveillance methods. The primary methods of surveillance are:

· Documentation - Monitoring performed by the COR and to include photographic and written materials provided by the contractor. Includes monthly reporting review.

· 100% Inspection – Each month the COR shall review the generated documentation and enter summary results into the Quality Assurance Monitoring Forms

· Periodic Inspection – The COR will perform up to three (3) inspections, virtual and/or in-person.

4.2 Customer Feedback

The contractor shall establish and maintain professional communication between its employees and customers. The primary objective of this communication is customer satisfaction. Customer satisfaction is the most significant external indicator of the success and effectiveness of all services provided and is measurable through customer complaints and surveys.

Performance management drives the contractor to be customer focused through initially and internally addressing customer complaints and investigating the issues and/or problems but the customer always has the option to communicate complaints to the COR, as opposed to the contractor. Customer feedback may be obtained either from the results of formal customer satisfaction surveys or from random customer complaints. Any customer complaints will be investigated by the COR using the Quality Assurance Monitoring Form – Customer Complaint Investigation, identified in Attachment A4.

4.3 Acceptable Quality Levels

The acceptable quality levels (AQLs) included in Attachment A2, Performance Requirements Summary Table for contractor performance, are structured to allow the contractor to manage how the work is performed while providing negative incentives for performance shortfalls.

5.0 QUALITY ASSURANCE DOCUMENTATION

5.1 The Performance Management Feedback Loop

Communication of expected outcomes initiates the performance management feedback loop.

Attachment A2 expresses the performance standards expected of the contractor, and the performance monitoring techniques used to assess performance.

5.2 Monitoring Forms

The government’s QA surveillance, accomplished by the COR, will be reported using the monitoring forms in Attachments A3 and A4. The forms, when completed, will document the government’s assessment of the contractor’s performance to ensure achieving the required results.

The COR will retain a copy of all completed QA surveillance forms.

6.0 ANALYSIS OF QUALITY ASSURANCE MONITORING RESULTS

6.1 Determining Performance

Government shall use the monitoring methods cited to determine whether the contractor has met performance standards, service levels, and AQLs. If the contractor has not met the minimum requirements, the government may request the contractor develop a corrective action plan to show how, and by what date, it intends to bring performance up to required levels.

6.2 Reporting

At the end of each month, the COR will prepare a written report for the CO summarizing the overall results of the quality assurance surveillance of the contractor’s performance. This written report, which includes the contractor’s submitted monthly report and the completed quality assurance monitoring forms (Attachments A3 and A4), will become part of the QA documentation. It will enable the government to demonstrate whether the contractor is meeting the stated objectives and/or performance standards including customer satisfaction regarding Task Order cost/technical/scheduling performance.

6.3 Reviews and Resolution

The COR may require the contractor’s project manager or designated alternate, to meet with the CO and other government personnel as deemed necessary to discuss a performance evaluation. The CO or COR will define a frequency of in-depth reviews with the contractor, however, if the need arises, the contractor will meet with the CO or COR as often as required or per the contractor’s request. The agenda of the reviews may include performance assessment data, issues and concerns of both parties, the projected outlook for upcoming months and progress against expected trends, including a corrective action plan analysis, recommendations for improved efficiency and/or effectiveness, and issues arising from the performance monitoring process.

The COR must coordinate and communicate with the contractor to resolve issues and concerns regarding marginal or unacceptable performance.

The COR and contractor should jointly formulate tactical and long-term courses of action. Decisions regarding changes to metrics, thresholds, or service levels require clear documentation. A modification can incorporate changes to service, procedures, and metrics.

6.4List of Attachments
Attachment A2 – Performance Requirements Summary
Attachment A3 – Quality Assurance Monitoring Form
Attachment A4 – Customer Complaint Investigation Form

ATTACHMENT A2 – PERFORMANCE REQUIREMENTS SUMMARY

Task / Critical Subtask
Quality/Performance Standard
Acceptable Quality Levels
Surveillance Method
Incentive
Revenue Collection (5)
Contractor shall provide services for the safe and secure electronic collection from the multi- space parking meters and daily deposit of collections into a specified NPS account.
100%
Reviewed by Park Budget for accuracy and checked by COR
Positive: Contractor has ability to ensure payments are processed and transferred and ensures all errors in reporting/transferring funding are reported and rectified monthly; CPARS report

Negative: Contractor can be held liable for deficiencies in the operations and collections of fees and transfers. Monthly payment will be withheld until corrections are made. Negative CPARS report

Revenue Collection (5)
Meters and Parkmobile APP setup and software maintained to receive payments and transmit data.
100%
Reviewed by Park Budget for accuracy and checked by COR
Positive: Contractor has ability to ensure payments are processed and transferred and ensures all errors in reporting/transferring funding are reported and rectified monthly; CPARS report

Negative: Contractor can be held liable for deficiencies in the operations and collections of fees and transfers. Monthly payment will be withheld until corrections are made. Negative CPARS report

Maintenance Schedule (6)

The Contractor shall ensue that the equipment is functioning at all times and compliant with the Department of Treasury and NPS security standards for receiving payments.
100%
Reviewed by Park Budget for accuracy and checked by COR
Positive: Contractor sets a schedule with the COR for maintenance and checks; keeps the COR informed of all times that they will be on site doing work; Provides reports of maintenance done to meters Positive CPARS report

Negative: Inability to positively track performance; Delay of monthly payment; Negative CPARS report; Cure Notice; Termination of Contract

Software (6)

The Contractor shall ensure, through monitoring software that the meters are functional and communicating properly.
100%
COR and Budget Monitoring
Positive: CPARS report

Negative: Delay of monthly payment; CPARS report; Cure Notice; Termination of Contract

Paper Levels (6)

The Contractor shall monitor paper levels and keep meters loaded with paper at all times ensuring that no meter is ever without paper.
100%
Random Inspection, Customer Complaints
Positive: CPARS report

Negative: Delay of monthly payment; CPARS report; Cure Notice; Termination of Contract

Batteries (6)

The Contractor shall monitor battery levels and ensure they are charging properly through maintaining and cleaning the solar charging device.
100%
Random Inspection, Customer Complaints
Positive: CPARS report

Negative: Delay of monthly payment; CPARS report; Cure Notice; Termination of Contract

Telephone Number Displayed (6)

The Contractor must display an attended telephone number on the meter for patrons and park staff members to report maintenance and transaction issues.
100%
Random Inspection, Customer Complaints
Positive: CPARS report

Negative: Delay of monthly payment; CPARS report; Cure Notice; Termination of Contract

Reporting (7)
Contractor will provide reports monthly by location.
100%
Received and reviewed by Budget and COR
Positive: CPARS report

Negative: Delay of monthly payment; CPARS report; Cure Notice; Termination of Contract

Training (7)
The contractor must provide a comprehensive training session for NPS personnel to access the reporting web-based applications.
100%
Received and reviewed by Budget and COR
Positive: CPARS report

Negative: Delay of monthly payment; CPARS report; Cure Notice; Termination of Contract

Enforcement Support (8)
The contractor shall coordinate with all enforcement entities to ensure the successful implementation and operation of the metered parking system
100%
Law Enforcement and COR ensure operation
Positive: CPARS report

Negative: Delay of monthly payment; CPARS report; Cure Notice; Termination of Contract

Transition Assistance (9)
At the end of the contract the contractor shall meet with the government to outline all necessary duties required to maintain meters and software. Contractor shall turn over all historical data and work documents such as standard operating procedures and work instructions.
100%
COR confirms this is done
Positive: CPARS report and final payment.

Negative: Final payment withheld until completed; CPARS report; Cure Notice

Invoicing (10)

Invoicing is performed as specified in scope
100%
COR ensures
Positive: CPARS report

Negative: Delay of monthly payment; CPARS report; Cure Notice; Termination of Contract

ATTACHMENT A3 – QUALITY ASSURANCE MONITORING FORM

CONTRACT OR TASK ORDER:

TEAM LEAD:

SURVEY PERIOD:

SURVEILLANCE METHOD (Check):

Random Inspection 100% Inspection Periodic Inspection Customer Complaint LEVEL OF SURVEILLANCE (Check):

Monthly Quarterly As needed

ANALYSIS OF RESULTS:

Service Provider’s Performance (Check):Meets Standards
Does Not Meet Standards

Narrative of Performance During Survey Period:

PREPARED BY: ___________________________________ DATE: _________________

ATTACHMENT A4 – CUSTOMER COMPLAINT INVESTIGATION

CONTRACTOR: _______________________________________________________________

CONTRACT/TASK ORDER NUMBER: ______________________________________________

DATE/TIME COMPLAINT RECEIVED: ___________________________ ________ AM / PM

SOURCE OF COMPLAINT: ___________________________________________ (NAME)

__________________________________________ (ORGANIZATION)

__________________________________________ (PHONE NUMBER)

__________________________________________ (EMAIL ADDRESS)

NATURE OF COMPLAINT: ______________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________ RESULTS OF COMPLAINT INVESTIGATION: ___________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

DATE/TIME SERVICE PROVIDER INFORMED OF COMPLAINT:

___________________ AM / PM

CORRECTIVE ACTION TAKEN BY SERVICE PROVIDER: _________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

RECEIVED AND VALIDATED BY: ____________________________________________________________________________

PREPARED BY: ___________________________________

DATE: _________________________________________

File details come from the government source that posted it. Updated .