B08_Solicitation-_Specifications.pdf

PDF 6 MB Posted

Attached to
STANFORD / GOIA ROOF REPLACEMENT Federal contract opportunity
Solicitation number
140P6423B0010
Issued by
Department of the Interior National Park Service Midwest Region

View the file

Other files for this federal contract opportunity

Other files attached to STANFORD / GOIA ROOF REPLACEMENT, newest first.
File Type Posted
B08_Solicitation-Bid_Schedule.xlsx XLSX spreadsheet
B08_Solicitation-DOL_Wage_Determination.pdf PDF
Sol_140P6423B0010.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Cuyahoga Valley National Park

Brecksville, Ohio

Replace Roofs at Goia Main House and George Stanford Farm

PMIS 329636

PROJECT SPECIFICATIONS

NATIONAL PARK SERVICE

March 31, 2023

Div. 1 V. 2022-9-6 Page | 2

TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

Section 01 10 00 - Division 01 Short Form General Requirements

DIVISION 07 – THERMAL AND MOISTURE PROTECTION

Section 07 31 13 – Asphalt Shingles Section 07 31 29 – Wood Shingles Section 07 53 23 – EPDM Roofing

DRAWINGS AND PHOTOGRAPHS

Appendix A- Location and Site Plan Appendix B- Photographs Appendix C- Drawings

Page | 3

SECTION 01 10 00

DIVISION 1 SHORT FORM GENERAL REQUIREMENTS

PART 1 – GENERAL

ITEM 1 - DESCRIPTION OF WORK

1.1 Background: The George Stanford House is significant for its long association with a prominent

Boston Township family. Its associated outbuildings and rural environment illustrate Boston

Township’s agricultural heritage and preserve, intact, a fine nineteenth-century farm in the

Cuyahoga Valley. The Goia Main House serves as the main office for the park partner

Conservancy for Cuyahoga Valley National Park. In order to preserve these historic assets, the aging and failing roof systems and associated components must be replaced. The current roofs exhibit material failure, cedar shingles are severely decayed and broken or missing in numerous locations. Asphalt shingles are worn, cracked, and missing in locations. Gutters are rusted through, misshapen, or missing. Continued deterioration will lead to failure and leaking, potentially resulting in structural damage and mold. This will pose a risk to the health and safety of visitors of the farm, overnight guests of the house, and to the Conservancy staff. This roofing project will extend the asset life cycle and reduces service-wide maintenance backlog, as well as preserve important cultural resources.

1.2 Work Covered by the Contract Documents:

A. Project Location: George Stanford House, 6093 Stanford Road, Peninsula, OH 44264 and

Goia House (Hines Hill Campus), 1403 West Hines Hill Road, Peninsula, OH 44264

B. Work consists of: This project will replace the roof and gutters on three structures of the historic George Stanford Farm. The cedar shingle roofs of the house, and smoke house will be replaced with new cedar shingles laid over new skip sheathing to resist moisture entrapment. The asphalt shingle roofs of the garage will be replaced with new asphalt shingles. At the Goia House the roof will be replaced with new asphalt shingles. Roof work will also include removal and replacement of damaged sheathing and wood fascia trim, and the installation of new metal flashing, drip edge, gutters, and downspouts. This project will replace approximately: 2,650 square feet of cedar shingles, 6,110 square feet of asphalt shingles, 320 square feet of EPDM roofing, and 740 lineal feet of gutters and downspouts.

Significant improvements will be made to the moisture protection of 3 important historic structures and the Goia Main House. The longevity of the new cedar shingles will be greatly increased by the installation of skip sheathing, which will allow the shingles to dry through improved ventilation.

1. Work includes removal of existing roof system and installation of new system including:

a. George Stanford House (all quantities and measurements are approximate):

i. 2515 SF of skip sheathing system (detail included for reference)

ii. 2515 SF of No.1 Grade 18” Perfection Class B fire rated Alaskan Yellow

Cedar Shingles

iii. 2515 SF of ice and water shield

Page | 4 iv.

v. 90 LF of ridge cap

vi. 90LF of ridge vent

vii. 90 LF of rake edge flashing

viii. 185 LF of eave edge flashing

ix. 60 LF of step flashing

x. 25 LF of counterflashing (includes two chimneys)

xi. 2 vent boots

xii. 165 LF of 6” half round gutters, mill finish aluminum, standard bead

xiii. 70 LF of 4” smooth round downspouts, mill finish aluminum

xiv. Gutter and downspout accessories including mill finish aluminum endcaps, elbows, outlets, downspout brackets, and hangers

xv. Leaf guards on all gutters

xvi. 2 permanent roof top fall protection anchors

b. George Stanford Garage (all quantities and measurements approximate):

i. 1100 SF of three-tab asphalt shingles in “Dark Grey”

ii. 1100 SF of ice and water shield

iii. 40 LF of ridge cap

iv. 65 LF of rake edge flashing

v. 85 LF of eave edge flashing

vi. 10 LF of step flashing

vii. 2 roof vents covered by 12 SF shingled cupola

viii. 80 LF of 5” K-style gutters, white painted aluminum

ix. 35 LF of 2” x 3” rectangular downspout, white painted aluminum

x. Gutter and downspout accessories including white painted aluminum endcaps, elbows, outlets, downspout brackets, and hangers

xi. Leaf guards on all gutters

xii. 1 permanent roof top fall protection anchor

c. George Stanford Smoke House (all quantities and measurements approximate):

i. 135 SF of No.1 Grade 18” Perfection Class B fire rated Alaskan Yellow

Cedar Shingles

ii. 135 SF of ice and water shield

iii. 15 LF of ridge cap

iv. 25 LF of rake edge flashing

v. 25 LF of eave edge flashing

vi. 25 LF of 1” x 6” nominal Western Red Cedar rake board

vii. 25 LF of 1” x 6” nominal Western Red Cedar fascia board

d. Goia House (all quantities and measurements approximate, includes multiple gabled and flat roof systems with both asphalt shingle and EPDM roofing; ensure flashing and weathertight assembly where dissimilar materials interact):

i. 5010 SF three-tab asphalt shingles in “Dark Grey”

ii. 320 SF EPDM roofing

iii. 5010 SF of ice and water shield

iv. 120 LF of step flashing

v. 160 LF of counterflashing (includes three chimneys)

vi. 80 LF of W-valley flashing

vii. 130 LF of ridge vent

viii. 160 LF of cap shingle

ix. 500 LF of drip edge

Page | 5

x. 3 boots at roof penetrations

xi. 2 fan vent boots

xii. 300 LF of 5” K-style gutters, seamless

xiii. 150 LF of 2” x 3” rectangular downspout

xiv. Gutter and downspout accessories including endcaps, elbows, outlets, brackets and hangers

xv. Leaf guards on all gutters

xvi. 4 permanent roof top fall protection anchors

e. Replacement of up to 10% roof decking, as necessary. Limits of replacement to be determined by contractor and COR after removal of existing roof system. Roof decking to be replaced in kind.

f. Ice and water shield to be installed on the George Stanford House, George

Stanford Garage, George Stanford Smoke House, and Goia House roofs to cover the entire roof surface.

g. Temporary roofing during construction where required. Temporary roofing shall maintain the project roof is watertight and able to prevent leaks and damage to the building and structure until the reroofing work is completed. Contractor is to make sure that at the completion of work each day the projects roof is 100% watertight.

h. Contractor receiving award is expected to field verify conditions prior to commencing work.

C. All work will be performed under a single contract. There are two (2) accounting codes for this project. George Stanford Farm project will be billed as a single charge and Goia House will be billed as a separate charge. The contractor will be responsible for separating this work and billing the Government accordingly.

D. Period of performance: Work shall be completed within 120 calendar days of the start date provided on the Notice to Proceed. The period of performance is inclusive of 5 weather days.

Work on the Stanford property must be completed between September 1, 2023 and October

31, 2023, due to existing reservation schedule for occupants on the property.

ITEM 2 – PROTECTING EXISTING UTILITIES

2.1 Protecting Existing Utilities: Notify Contracting Officer (CO), Contracting Officer’s Representative

(COR) and utility companies as required to request location services prior to and to coordinate any excavation/digging operations, and/or for demolition if within Scope of Work.

2.2 Contractor shall be responsible for locating and preventing damage to known utilities on site or indoors. If contractor damage occurs, alert CO and COR as soon as safely possible, and repair utility at no additional expense to the Government. If damage occurs to an unknown utility, contact CO and COR as soon as safely possible.

2.3 Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated below:

A. Notify CO and COR not less than two business days in advance of proposed utility

Page | 6 interruptions.

B. Hours for Utility Shutdowns: Shutdowns shall not exceed 2 to 3 hours. Temporary provisions will be needed by the Contractor for periods longer than stated allowance or if required for critical systems as determined by COR.

ITEM 3 - CONTRACTOR’S USE OF PREMISES

3.1 Conduct of Operations: At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park

Service, and applicable park rules and regulations prescribed by the Park Superintendent.

https://www.nps.gov/cuva/learn/management/superintendents-compendium.htm

A. No signs or advertisements (except those specified herein and as required for safety) shall be displayed on the construction site or within the park unless approved by the Contracting

Officer.

B. Smoking is not permitted within any Federal building or within 25 feet of entrances, operable windows, or outdoor air intakes.

C. Public Use of Site: Contractor shall at all times conduct operations to ensure the least inconvenience to the public. Both the Stanford and Goia properties will be in use by the public throughout the duration of the project. Contractor must adhere to the work hours and site plans included in these specifications. Contractor must maintain safe access to and from the buildings at all times. Deviation from this is unacceptable.

3.2 On-site work hours: Work shall be generally performed during normal business working hours of

7 a.m. to 5 p.m., Monday through Thursday, except when otherwise indicated.

A. Work on Fridays, Saturdays, Sundays, Federal holidays, early morning, or at night may not be performed without prior consent from the CO and COR. Submit requests for work outside of the stated normal business hours to the CO and COR for approval at least 48 hours in advance of the work.

The following Federal holidays are observed by the National Park Service:

New Year Day

Martin Luther King, Jr’s Birthday

Washington’s Birthday

Memorial Day

Juneteenth National Independence Day

Independence Day

Labor Day

Columbus Day

Veterans Day

Thanksgiving Day

Christmas Day

B. Note: Any of the above holidays falling on a Saturday will be observed on the preceding

Friday; holidays falling on Sunday will be observed on the following Monday. The specific https://www.nps.gov/cuva/learn/management/superintendents-compendium.htm

Page | 7 day that each holiday is recognized for each year can be found at the following site:

https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=2022.

3.3 Contractor Use of Site:

A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to construction area as shown on site plan. Do not disturb portions of Project site beyond areas in which the Work is indicated.

B. Driveways and Entrances: Keep driveways, access roads, and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize use of driveways and entrances.

C. Define site disturbance area, including earthwork and clearing of vegetation, to: N/A

D. Utilities

1. General: Cost or use charges for temporary facilities shall be included in the Contract Sum as required.

2. Water Service: Water from existing water system is not available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations without any additional permit costs. Use resources wisely and minimize waste of water.

3. Electric Power Service: Electric power from existing system is not available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations without any additional permit costs. Power may or may not meet your construction power tool requirements, provide generators if questionable. Use power in a resourceful manner and avoid excess power waste.

4. Waste Operation: Both toilet facility and dumpster locations (contractor provided) are shown on the attached site plans.

a. Toilets: Contractor provided for contracting personnel, sufficiently lighted and ventilated toilet facilities in weatherproof, sight proof, handicap accessible (if required), sturdy enclosures with privacy locks. Coordinate with COR for approved location if not shown on attached site plan.

b. Waste Removal / Recycling: Contractor is responsible for removing all waste created by the project. Contractor shall recycle to the highest degree possible and empty dumpsters as necessary to avoid debris on site. Locate as shown on site plan or coordinated with COR.

E. Security and Protection facilities:

1. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with state and federal environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.

2. Cleaning of Equipment: The Contractor shall ensure that prior to moving on to the Project Area, all equipment, is free of soil, seeds, vegetative matter, or other debris that could https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=2022

Page | 8 contain or hold seeds. Ensure that all equipment has been pressure washed and is free of exotic species prior to start-up of operations and moving of equipment to Project Area.

Equipment shall be considered free of soil, seeds, and other debris when a visual inspection does not disclose such material. Disassembly of equipment components or specialized inspection tools are not required.

3. Tree and Plant Protection: Provide Tree Protection fence at drip line of trees impacted in construction area. Coordinate with COR. Restore damaged areas to original condition, repairing or replacing damaged trees and plants, at no additional expense to the Government.

i. Provide temporary barriers to protect existing trees and plants and root zones.

j. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer Representative and remove agreed-on roots and branches that interfere with construction.

k. Do not fasten ropes, cables, or guys to trees.

l. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.

4. Pest Control: Follow best practices to minimize attraction and harboring of rodents, roaches, and other pests and to perform extermination and control procedures at regular intervals so Project will be free of pests and their residues at project completion. Perform control operations lawfully, using environmentally safe materials.

5. Temporary Enclosures: N/A

6. Site Enclosure Fence: N/A

7. Security Enclosure and Lockup: N/A

3.4 Storage - Staging Areas:

A. Confine Storage of materials and equipment to the project staging area noted on the plans/aerial. Specific storage and staging area’s may be discussed at the preconstruction briefing. Both locations are open to the public and materials should be stored in a secure manner. Materials should not be staged on the lawn, parking, or driveway areas other than the locations specifically called out on the site plan. No exceptions will be made for this. At both locations, any materials or tools that have been brought to the work area during the day must return to the material storage area every night. Both locations are utilized for private events in evening and weekend hours where photography is common, and the tenants of both houses require the site to be free of tools, materials, and construction debris during those events.

3.5 Preservation of Natural Features: N/A.

3.6 Hauling Restrictions: Contractor to verify path to site and meet state and county road requirements and height restrictions for all park work/access.

3.7 Housekeeping:

A. Keep project neat, orderly, and in a safe condition at all times.

Page | 9

1. Dispose of waste materials and recycling legally outside the park. The contractor shall not use park dumpsters.

2. Address Recycling: Government goal is to salvage and recycle as much nonhazardous construction waste as possible. Use sustainable methods to extent possible during this project, recycling material as is probable with local means. Maintain accurate documentary records for submittal of all recycled materials used including fly ash and slag cement.

3.8 Occupancy Requirements for Buildings:

A. Existing Buildings:

1. Full Government Occupancy: Government will occupy buildings that will be under construction during the entire contract period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government's day-to-day operations. Maintain existing exits, unless otherwise indicated.

a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the CO or COR.

b. Maintain existing building in a weather tight condition throughout construction period. Repair damage caused by construction operations. Protect building and its occupants during construction period. All entrances will be used regularly during construction; protect those passing through entrances from falling construction debris, tools, etc.

B. New /Existing Buildings Unoccupied: N/A

3.9 Photo Documentation:

A. Contractor must provide existing condition, progress, and completion photos. All photos shall be in focus, show maximum range of depth of field general photo and then close up detail photo as needed. Shall be in JPEG digital form and submitted electronically by email or via

CD-R Archival Gold or DVD-R Archival Gold media with printed labels and 8 mega pixels minimum within 7 days from time of taken or as approved by COR.

B. Existing Condition Images:

1. Before starting construction, take color, dated, digital images of project site and adjacent property/roads/etc. that may be impacted by construction activity/traffic. Include existing items to remain or be salvaged from different vantage points and with context for location identification.

C. Construction Progress Images:

Page | 10

1. Document all sub-surface work/ trenches etc. prior to backfill with photos covering enough overall field view to show location and then zoom in for details. (Locations and dimensions shall also be noted on as built drawing set.)

2. Maintain organized index for photos with date, description, etc.

3. Additional images as needed when questions or emergency situations occur. Submit within 24 hours.

D. Completion Images:

1. Document all completed work within scope of work.

2. Maintain organized index for photos with date, description, etc...

3. Additional images as needed when questions or emergency situations occur. Submit within 24 hours.

3.10 Fire and Life Safety:

A. As a minimum, conduct one weekly 15 minute "toolbox" safety meetings. These meetings shall be conducted by a foreman or supervisor and attended by all construction personnel at the worksite. Topics need to coincide with work scheduled for the following week. Document and submit meeting minutes to the CO and COR within one day after the meeting and document the meetings on the daily reports.

B. Comply with the requirements of NFPA 241 (Standard for Safeguarding Construction, Alteration, and Demolition Operations). Take all necessary precautions to prevent fire during construction. Provide adequate ventilation during use of volatile or noxious substances.

C. Store and handle hazardous materials in accordance with manufacturers and OSHA 29CFR1926 Subpart D requirements 1926 | Occupational Safety and Health Administration (osha.gov). Maintain readily available, on site, MSDS/Safety Data Sheets (SDS) for each chemical.

1. Immediately report all spills of hazardous materials to the CO, COR, and park.

2. Maintain a spill emergency response kit.

3. Train employees how to respond to a spill and use the emergency response kit.

3.11 Noise and Acoustics Management: N/A

ITEM 4 - COMMENCEMENT, PROSECUTION, AND COMPLETION

4.1 The Contractor shall commence work in accordance with the terms and conditions of the contract.

Contractor shall coordinate and incorporate long lead and delivery time items within the schedule.

ITEM 5 - EXAMINATION OF THE SITE

5.1 All bidders are urged to visit the job site and examine existing conditions before submitting bids.

Contractors will be accountable for understanding existing conditions. No cost changes for items viewable during site visit will be allowed.

ITEM 6 - ABBREVIATIONS

https://www.osha.gov/laws-regs/regulations/standardnumber/1926 https://www.osha.gov/laws-regs/regulations/standardnumber/1926

Page | 11

6.1 The list of abbreviations, standards and organizations which may be used in/referred within the

Construction Specifications or Special Provisions, may be found linked from the listed page below. On the home page, follow the link under “Contracting and Procurement” labeled “NPS

Reference Standards.” https://www.nps.gov/orgs/1671/do-business-with-us.htm

ITEM 7 - ACCIDENT PREVENTION

7.1 Description: The work of this section consists of establishing and implementing an effective accident prevention program (APP) and providing a safe environment for all personnel and visitors.

7.2 Submittals:

A. Accident Prevention (Safety) Plan (APP): Submit a site-specific accident prevention (safety) plan. The Plan shall be written to comply with OSHA and project requirements (a generic plan is not acceptable) including but not limited to the following:

1. Name and qualifications of responsible supervisor to carry out the program.

2. First aid and rescue procedures.

3. Training, both initial and continuing.

4. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to provide for property protection and safety of the public, National

Park Service personnel, and Contractor's employees. Identify the work included under each phase, with a Job Hazard Analysis (JHA)/Job Safety Analysis (JSA), etc. A sample

JHA template may be provided upon request.

5. Planning for possible emergency situations, such as cave-ins, earthquake, explosions, fires, floods, power outages, slides, and windstorms. Such planning shall take into consideration the nature of construction, site conditions, and degree of exposure of persons and property.

6. Contractor to identify nearest location of medical facility for emergencies

7. Recognition that works will be performed in remote areas with limited communication or cell phone coverage if applicable.

8. Supplemental hazard specific plans may be required IAW 29 CFR 1926 or 1910.

B. Meeting and Inspection Reports: Safety Meetings: As a minimum, conduct 15 minute

"toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite. Submit a report of safety meetings and inspections to CO and COR within one day after the meeting and document the meetings on the daily reports.

7.3 Qualification of Employees:

A. Ensure that employees are physically qualified to perform their assigned duties in a safe manner to include operators of vehicles and equipment. Provide operating instructions for all equipment.

B. Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.

https://www.nps.gov/orgs/1671/do-business-with-us.htm

Page | 12

7.4 Accident Reporting: The Contractor shall report all accidents to the CO and COR as soon as safely possible and assist the CO and COR and other officials as required in the investigation of the accident.

7.5 First Aid Facilities: Provide access to facilities for the number of employees and appropriate to the hazards associated with the types of ongoing construction work at the site.

7.6 Emergency Instructions: Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.

7.7 Personal Protective Equipment (PPE): It is the Contractor's responsibility to require all those working on or visiting the site to wear necessary protective equipment at all times.

A. PPE must meet requirements of applicable ANSI standards. Selection shall conform to OSHA

29CFR 1926 Subpart E.

B. A hard hat use area shall be designated by the Contractor. The hard hat area shall be posted by the Contractor in a manner satisfactory to the Contracting Officer.

C. All PPE will be serviceable at all times. At a minimum, maintain four sets of PPE including hard hats and all other Accident Prevention Plan required equipment.

7.8 Hazardous Materials: It shall be the responsibility of all operators and contractors, functioning within the park to properly cleanup, mitigate and remediate, if necessary, all unauthorized discharges of hazardous materials or non-hazardous chemical and biological products released from fleet and/or other support vehicles or stationary sources. Response shall be consistent with guidelines established by federal, state, and local regulations, and as outlined within the operator's Safety or Hazardous Materials Business Plan.

A. If a spill, leak, or other release occurs, the operator shall as soon as possible, without impeding cleanup, notify the local 911 Emergency Response, COR and or the National Park

Service Emergency Dispatch.

ITEM 8 - PRECONSTRUCTION CONFERENCE

8.1 If the Contracting Officer decides to conduct a preconstruction conference, the successful offeror will be notified and will be required to attend. The Contracting Officer’s notification will include specific details regarding the date, time, and location of the conference, any need for attendance by subcontractors, and information regarding the items to be discussed. See Item 9.1C below.

ITEM 9 - SUBMITTALS

9.1 General Contracting Submittal Procedures:

A. General: Prepare and submit submittals required by individual Technical Specification

Sections. Types of submittals are indicated in individual specific sections.

Page | 13

1. CM-16 Transmittal Form: All submittals shall be transmitted via electronic email using

National Park Service form CM-16 form. The form will be provided by the Contracting

Officer. No action will be taken on a submittal item unless accompanied by the CM-16 transmittal form. Submit completed CM-16 forms to the CO and the COR

B. Submittal List: administrative required submittals are listed below in 9.1.C and does not include technical section submittal requirements included in each technical section.

C. Preconstruction Conference Submittal: Satisfactory evidence of liability insurance coverage and workman’s compensation, and any applicable bonds, must be submitted within 10 calendar days of Notice of Award. The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. If all of these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to Proceed may not be issued, and the Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to

Proceed has been issued. Contracting Officer will notify Contractor of tentative date for the

Pre-Construction Conference:

1. Letter designating Project Superintendent.

2. Construction Schedule. (Must include shop drawings, procurement time including long lead time items, mobilization, trade work progression and completion at minimum.)

3. A comprehensive breakdown of the Schedule of Values.

4. Accident Prevention (Safety) Plan (see section 7 of this document).

5. A list of Subcontractors for this project.

6. Written statements from subcontractors certifying compliance with applicable labor standard clauses (SF1413).

7. Quality Control Plan.

8. Waste Management Plan: Contractor is required to provide and maintain dumpsters for construction debris through the duration of the project. Location of these dumpsters is identified on the attached site plan.

9.2 Project Shop Drawings, Product Data, and Samples: Contracting Officer will provide sample cover sheet and a list of required submittals is included in each technical specification or attached at the end of this document.

A. Shop Drawings: Indicate all coordinating materials and work impacting the installation coordination, connection details, anchorage requirements, hardware locations, and installation details and locations.

1. Submit Shop Drawings according to Part 9.1 of this section to include one digital file (.PDF or .TIF) and two full size hardcopy documents to COR.

B. Product Data: Provide component construction and specification data sheets, anchorage requirements and any other product specific data.

1. Submit Product Data according to Part 9.1 of this section to include one digital file (.PDF or .TIF) to COR.

Page | 14

C. Samples: Submit 2 color samples 4” x 6” minimum in size for all color and product selections.

Paint samples shall be actual paint finish drawdown for all project colors.

1. Submit Samples CM-16 Transmittal Form according to Part 9.1 of this section to include one digital file (.PDF or .TIF) and physical samples of actual material to COR.

D. For submittals specified above, forward submittals to Contracting Officer and COR at least 15 days before need for approval (depends on length of project).

E. After approving submittals, Contracting Officer and/or COR will return one copy to the

Contractor. If submittals are not approved, Contracting Officer will return all copies to

Contractor with reasons for rejection. Resubmit, identifying changes. Any work done before approval shall be at Contractor's own risk.

9.3 Approved Equals: If an item in this solicitation is identified as “brand name or equal” or lists more than 1 manufacturer, the description of the proposed item must reflect the characteristics and level of quality that will satisfy the Government’s needs as demonstrated by the salient physical, functional, or performance characteristics that “equal” products must meet and/or exceed that as specified in the solicitation or relevant specification.

A. For each item proposed as an “approved equal,” submit supporting data, including:

1. Drawings and samples as appropriate.

2. Comparison of the characteristics of the proposed item with that specified and with the salient characteristics provided.

3. Changes required in other elements of the work because of the substitution.

4. Name, address, and telephone number of vendor.

5. Manufacturer’s literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists.

Describe availability of maintenance service, and state source of replacement materials.

B. A request for approval constitutes a representation that Contractor:

1. Has investigated the proposed item and determined that it is equal or superior in all respects to that specified.

2. Will provide the same warranties for the proposed item as for the item specified.

3. Has determined that the proposed item is compatible with interfacing items.

4. Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.

5. Waives all claims for additional expenses that may be incurred as a result of the substitution.

C. Approved Equals will be evaluated and approved/disapproved during the submittal process.

9.4 Schedule of Values: Submit the Schedule of Values a minimum of one week prior to the

Preconstruction Conference for COR review. Schedule of Values shall include defined work line items with cost break downs including labor, material, and equipment for COR approval.

Page | 15

9.5 Progress Reporting: The initial Construction Schedule and Schedule of Values are required a minimum of one week prior to the Preconstruction Conference. After the Notice to Proceed is issued and after on-site work begins, progress will be documented via daily logs and by providing an updated Construction Schedule and Schedule of Values when requested, but minimally with each pay application. Submit digital copy electronically (PDF preferred) of all required documents.

Construction Schedules are normally in bar chart form and indicate estimated starting and completion dates for each part of the work. For a pay application to be reviewed and processed in a timely manner, the following information must either be submitted prior to or accompany submission of the pay application:

A. Daily/weekly progress reports during construction as part of the administration process.

B. Updated Schedule of Values: Breakdown each lump-sum item into component work activities used in the schedule, for which progress payments may be requested. The Schedule of

Values will form the basis for payment. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the construction baseline schedule submitted under this specification. The total costs for the component work activities shall equal the contract price for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. A sample Schedule of Values format may be provided upon request.

ITEM 10 – TEMPORARY SERVICES

10.1 It is the Contractor’s responsibility to provide temporary services, equipment, tools, and skilled labor as required for the chosen means and methods to perform the work in accomplishing this

Contract.

ITEM 11 - PROJECT CLOSEOUT

11.1 Description: The work of this section consists of final cleanup, closeout submittals, final inspection procedures working toward Final Acceptance.

11.2 Cleaning: Remove all tools, equipment, surplus materials, and rubbish. Move attic stock to location coordinated with COR. At time of final inspection, project shall be thoroughly clean and ready for intended use. Inspector holds the right to reschedule if project is not ready for inspection.

11.3 Completion and Final Inspection: Contractor shall submit written certification of project completion and request a final inspection to the Contracting Officer and COR. The Contracting

Officer or designee will make an inspection within 10 days of receipt of request or at a mutually agreeable time.

A. If the work is determined to be complete following the final inspection with minor comments, the COR will prepare and provide the Contractor a Punch List noting outstanding items to be addressed.

B. If the work is not determined to be complete following the final inspection, the Contracting

Officer will notify Contractor in writing, stating reasons. Contractor, after completing the work according to the Contract Documents, shall resubmit completion and request a new final

Page | 16 inspection. Re-inspection costs may be charged against the Contractor in accordance with the Inspection of Construction contract clause.

C. Contractor shall complete the Punch List within 30 calendar days, or a time directed by the

CO.

D. Once Contractor completes all items of work on the Punch List and all contractually required items are accepted, Contracting Officer will issue Letter of Final Acceptance of Work and request the final pay application.

E. If the Contractor fails to complete the work within the time frame, the Contracting Officer may correct the work with an appropriate reduction in contract price or charge for re-inspection costs in accordance with the Inspection of Construction contract clause.

F. Disposition of any permits and warranties required by the specifications in this section.

11.4 Final Acceptance of the Work: After all punch list deficiencies have been corrected, a Letter of

Final Acceptance will be issued. A Release of Claims document must be executed and submitted to the Contracting Officer before final payment can occur.

11.5 Warranties

A. Construction Warranty shall be based on date of final acceptance of the work and remain in effect for one year.

B. Provide all manufacturer warranty information of products installed organized by Division. All contact information, extent of coverage and conditions shall be clearly noted as well as date of overall final acceptance.

C. Information shall include operation and maintenance manuals for each warranted product.

PART 2 – PRODUCTS (NOT USED)

PART 3 – EXCUTION (NOT USED)

END OF SECTION

CUVA 329636 3/31/2023

Div. 7 V. 2021-10-18 ASPHALT SHINGLES 073113 Page | 17

SECTION 073113

ASPHALT SHINGLES

PART 1 - GENERAL

1.1 SCOPE OF WORK

A. Project Location: George Stanford Farm, 6093 Stanford Road, Peninsula, OH 44264 and Goia House (Hines Hill Campus), 1403 West Hines Hill Road, Peninsula, OH 44264

B. Building(s) Name/Identifier: George Stanford Garage, Goia Main House

C. All roofing components will be recommended by shingle manufacturer and installed in accordance with warranty guidelines. Contractor must show proof of manufacturers certification and submit in accordance with Submittal List.

1.2 SUMMARY

A. Section Includes:

1. Selective Demolition.

2. Glass-fiber-reinforced asphalt shingles.

3. Underlayment materials.

4. Vents and plumbing stack boots.

5. Sheet metal flashing and trim.

6. Gutter and downspouts.

7. PREINSTALLATION MEETINGS

B. Preinstallation Conference: Conduct conference at Project site.

1.3 ACTION SUBMITTALS

A. Product Data: For the following:

1. Asphalt shingles.

2. Gutters and accessories

3. Leaf Filters

4. Ice and water shield

5. Underlayment materials.

6. Ridge vents.

Div. 7 V. 2021-10-18 ASPHALT SHINGLES 073113 Page | 18

7. Asphalt roofing cement.

8. Elastomeric flashing sealant.

9. Vents and plumbing stack boots.

10. Sheet metal flashing and trim.

B. Sustainable Design Submittals:

1. Product Test Reports: For roof materials, documentation indicating that roof materials comply with Solar Reflectance Index requirements.

C. Shop Drawings: For sheet metal flashing and trim.

D. Samples: For each exposed product and for each color and blend specified.

1.4 INFORMATIONAL SUBMITTALS

A. Product test reports.

B. Research reports for synthetic underlayment.

C. Sample warranty.

1. Material warranty.

2. Roofing installers warranty and shingle manufacturer certification.

3. SUBMITTAL COORDINATION

D. Submittal List: A submittal list has been attached to the end of this Specification Section. The intent is to provide an overall summary of the submittal requirements and not a comprehensive list. The requirements of the individual Specification Sections, terms and conditions of the Contract still apply regardless of what is shown on the submittal list.

1.5 CLOSEOUT SUBMITTALS

A. Maintenance data.

1.6 QUALITY ASSURANCE

A. Installer Qualifications: An authorized installer who is trained and approved by manufacturer.

1.7 WARRANTY

A. Materials Warranty: Manufacturer agrees to repair or replace asphalt shingles that fail within specified warranty period.

1. Materials Warranty Period: 25 years from date of Substantial Completion, prorated, with first 10 years non-prorated.

2. Wind-Speed Warranty Period: Asphalt shingles will resist blow-off or damage caused by wind speeds of up to 130 mph (58.1 m/s) for 15 years from date of Substantial Completion.

http://www.arcomnet.com/sustainable_design.aspx?topic=6

Div. 7 V. 2021-10-18 ASPHALT SHINGLES 073113 Page | 19

3. Algae-Resistance Warranty Period: Asphalt shingles will not discolor for 20 years from date of Substantial Completion.

B. Roofing Installer’s Warranty: Roofing installer to provide and sign a Roofing Installer’s Warranty in which Installer agrees to repair or replace components of asphalt-shingle roofing that fail in materials or workmanship within specified warranty period.

1. Warranty Period: Five years from date of Substantial Completion.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Exterior Fire-Test Exposure: Provide asphalt shingles and related roofing materials identical to those of assemblies tested for Class A fire resistance in accordance with American Society of Testing Materials (ASTM) E108 or UL 790 by Underwriters Laboratories or another testing and inspecting agency acceptable to authorities having jurisdiction. Identify products with appropriate markings of applicable testing agency.

B. Wind Resistance: Provide asphalt shingles that comply with requirements of ASTM D7158/D7158M, Class H.

C. Shingles:

1. Mineral granular-surfaced asphalt shingles.

a. Self-sealing.

b. Square tab.

c. Fungus-resistant.

d. Impact resistant shingles, Class 4.

e. Type I, weighing not less than 290 pounds per 100 square feet.

2.2 GLASS-FIBER-REINFORCED ASPHALT SHINGLES

A. Three-Tab Strip Asphalt Shingles: ASTM D3462/D3462M, single-ply construction; glass-fiber reinforced, mineral-granule surfaced, square tab, and self-sealing.

1. Basis of Design: Atlas Pinnacle Pristine High-Performance Shingles.

2. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. Atlas Molded Products; a Division of Atlas Roofing Corporation.

b. CertainTeed Corporation.

c. GAF.

d. Owens Corning.

e. Tamko Building Products, Inc.

f. Other Approved Equals.

3. Strip Size: Manufacturer's standard approximately 36 inch.

4. Algae Resistance: Granules resist algae discoloration.

5. Impact Resistance: Underwriters Laboratory (UL) 2218, Class 4.

6. Fire Resistance: UL 790 for Class A.

7. Color and Blends: GAF Royal Sovereign “Charcoal” or approved equal.

http://www.specagent.com/Lookup?ulid=4726 http://www.specagent.com/Lookup?uid=123457152155 http://www.specagent.com/Lookup?uid=123457152156 http://www.specagent.com/Lookup?uid=123457152154 http://www.specagent.com/Lookup?uid=123457152159 http://www.specagent.com/Lookup?uid=123457152161

Div. 7 V. 2021-10-18 ASPHALT SHINGLES 073113 Page | 20

B. Hip and Ridge Shingles: Manufacturer's standard units to match asphalt shingles.

2.3 UNDERLAYMENT MATERIALS

A. Synthetic Underlayment: UV-resistant polypropylene, polyolefin, or polyethylene polymer fabric with surface coatings or treatments to improve traction underfoot and abrasion resistance;

evaluated and documented to be suitable for use as a roof underlayment under applicable codes by a testing and inspecting agency acceptable to authorities having jurisdiction.

1. Basis of design: RhinoRoof U20, as manufactured by InterWrap, Inc.

a. Product requirements include the following minimum characteristics listed below:

1) Permeability ASTM E96 - .05 perms.

2) Water Transmission ASTM D4869 – pass.

3) Tear Strength ASTM D4533 – MD 30 lbs (14 kg).

4) Tensile Strength ASTM D751 – MD 80 lbs (36 kg).

5) Bursts Strength ASTM D751 – 150 psi (1033 kPa)

6) Nominal Thickness ASTM D1777 – 6 mils (0.15 mm).

7) Width Per Roll – 36 inches.

8) Manufacturers: Subject to compliance with requirements, provide products by one of the following:

b. Atlas Roofing Corporation.

c. CertainTeed Saint-Gobain.

d. GAF.

e. Owens Corning.

f. Tamko Building Products, Inc.

g. Other Approved Equals.

h. Valleys, Eaves, Rake, and Roof/Wall Intersections: Install Self-Adhering, Polymer- Modified Bitumen Sheet: ASTM D1970/D1970M, minimum 55-mil- (1.4-mm-) thick sheet; glass-fiber-mat-reinforced, polymer-modified asphalt; with slip-resistant top surface and release backing; cold applied. Material to be supplied in 36 inch wide rolls. Provide primer for adjoining concrete, masonry, and metal surfaces to receive underlayment as recommended by the manufacturer. Approved product includes but is not limited to the following:

2. Grace Ice & Water Shield; Grace Construction Products.

3. WinterGuard Waterproofing underlayment; CertainTeed.

4. RhinoRoof Granulated Self-Adhered underlayment.

5. Other Approved Equals.

6. VENTS

B. Rigid Ridge Vent: Manufacturer's standard, rigid-section, high-density, UV-stabilized plastic ridge vent for use under ridge shingles. Provide vents to match the size and net free area of the existing vents being replaced.

1. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to the following:

a. VenturiVent Plus, as manufactured by Air Vent Inc.

b. Certainteed Ridge Vent - 12".

http://www.specagent.com/Lookup?ulid=9296 http://www.specagent.com/Lookup?uid=123457152955 http://www.specagent.com/Lookup?uid=123457152918 http://www.specagent.com/Lookup?uid=123457152205 http://www.specagent.com/Lookup?uid=123457152207 http://www.specagent.com/Lookup?uid=123457152209

Div. 7 V. 2021-10-18 ASPHALT SHINGLES 073113 Page | 21

c. Owens Corning VentSure.

d. Other Approved Manufacturers.

2. Minimum Net Free Area: 18 sq. in. per ft.

C. Hood / Static Vent: Where shown on the drawings install slant-back, box type vents with minimum free area of 50 sq. inches (0.35 sq. ft) with filters. Provide vents to match the size and net free area of the existing vents being replaced. Color to be selected by COR from manufacturer’s standard finishes. Approved products as manufactured by but not limited to the following:

1. Air Vent, Inc.

2. CertainTeed.

3. Broan.

4. Other Approved Manufacturers.

5. ACCESSORIES

D. Asphalt Roofing Cement: ASTM D4586/D4586M Type II, asbestos free.

E. Roofing Nails: ASTM F1667, aluminum, stainless steel, copper, or hot-dip galvanized-steel wire shingle nails, minimum 0.120-inch- (3-mm-) diameter, sharp-pointed, with a 3/8- to 7/16-inch- (10-to 11-mm-) diameter flat head and of sufficient length to penetrate 3/4 inch (19 mm) into solid wood decking or extend at least 1/8 inch (3 mm) through sheathing less than 3/4 inch (19 mm) thick.

1. Where nails are in contact with metal flashing, use nails made from same metal as flashing.

F. Synthetic Underlayment Fasteners: As recommended in writing by synthetic-underlayment manufacturer for application indicated.

2.4 SELECTIVE DEMOLITION

A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations and as follows:

1. Full Roof Tear-off: Removal of existing roofing system down to existing roof deck or structure.

2. Temporarily protect existing roofing system and components that are to remain as required from damage.

3. Existing roof drains and roof drainage shall be protected during each stage of reroofing, and roof-drain plugs shall be installed when demolition is taking place so that debris cannot be lost down the drains. Contractor shall remove all drain plugs when demolition is completed in the area affecting the drain.

4. Do not remove more roof than can be replace in a day, and the roof will be made watertight each night.

5. Remove debris and materials so as not to impose excessive loads on supporting roof, structure or framing.

6. Dispose of demolished items and materials promptly.

B. Removed and Reinstalled Items:

1. Clean and repair items to functional condition adequate for intended reuse.

Div. 7 V. 2021-10-18 ASPHALT SHINGLES 073113 Page | 22

2. Reinstall items in locations indicated, or in original locations as required. Comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make item functional for use indicated.

C. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition.

D. Inspect deck after tear-off of roofing system.

1. If broken or loose fasteners that secure deck panels to one another or to structure are observed, or if deck appears or feels inadequately attached, immediately notify COR.

a. Do not proceed with installation until directed by COR.

2. If deck surface is unsuitable for receiving new roofing or if structural integrity of deck is suspect, immediately notify COR.

a. Do not proceed with installation until directed by COR.

b. Disposal of Demolished Materials:

3. General: Except for items or materials indicated to be reused, salvaged, reinstalled, or otherwise indicated to remain NPS's property, remove demolished materials from Project site.

a. Do not allow demolished materials to accumulate on-site.

b. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.

4. Burning: Do not burn demolished materials.

5. Disposal: Transport demolished materials off NPS's property and legally dispose of them.

E. Cleaning:

1. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began.

2. SHEET METAL FLASHING AND TRIM

F. Performance Requirements:

1. General: Sheet metal flashing and trim assemblies shall withstand wind loads, structural movement, thermally induced movement, and exposure to weather without failure due to defective manufacture, fabrication, installation, or other defects in construction. Completed sheet metal flashing and trim shall not rattle, leak, or loosen, and shall remain watertight.

2. Sheet Metal Standard for Flashing and Trim: Comply with National Roofing Contractors Association’s (NRCA's) "The NRCA Roofing Manual" and Sheet Metal and Air Conditioning Contractors National Association’s (SMACNA's) "Architectural Sheet Metal Manual" requirements for dimensions and profiles shown unless more stringent requirements are indicated.

3. Single Ply Roofing Industry (SPRI) Wind Design Standard: Manufacture and install copings and roof edge flashings tested according to SPRI ES-1 and capable of resisting the following design pressure:

a. Design Pressure: 30 psf…